Professional Documents
Culture Documents
RE Monthly Reports June - Oct 2014
RE Monthly Reports June - Oct 2014
RE Monthly Reports June - Oct 2014
RESIDENT ENGINEERS
MONTHLY REPORT
Monthly Report No.:
Contract Amount
Approved CCO
Current Contract Amount
$ 619,654
$ 0
$ 619,654
$ 120,000 (approx.)
19%
Page 1 of 6
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
Page 2 of 6
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
The contractor has been directed to proceed with a PG&E service tie-in (final routing to be determined)
with a conduit run to the trash enclosure area for potential PV service in the future.
CHANGES
None executed
CM CONTRACT
ACTIVITIES
Obtain quotes from materials testing firms and provide recommendation to City
Set up project filing system
Field inspection
Coordination with City staff, contractor and architect
Coordination of materials testing & special inspections
Tracking/administration of submittals, Requests for Information, Requests for Proposal and potential
changes
Weekly contractor progress meeting
Weekly coordination meeting with City
CONTRACT SUMMARY
Original Budget:
Expenditures this month:
Expenditures to date:
Budget Remaining:
$ 68,670.00
$ 23,050.00
$ 23,050.00
$ 45,620.00
STAFF
Page 3 of 6
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
Page 4 of 6
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
Page 5 of 6
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
Rough layout
Rough grading
Page 6 of 6
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
RESIDENT ENGINEERS
MONTHLY REPORT
Monthly Report No.:
Contract Amount
Approved CCO
Current Contract Amount
Monthly Progress Invoice
Cumulative Invoiced
Progress to Date (budget)
$
$
$
$
$
619,654
0
619,654
86,453
178,890
29%
Page 1 of 5
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
Work on the site resumed immediately after receiving direction to resume work; a concrete placement for all
wall footings occurred within 2 days of resuming work (July 22nd).
The contractors activities included the following:
Placed concrete for all wall footings
Placed concrete for board form test panel
Began forming for building walls
The contractor has expended 66 of the 150 calendar days (approximately 44%) in the contract period; he has
expended approximately 29% of the contract budget at the close of July. The disparity in the time vs. budget
may be attributed to the suspension in work experienced during the reporting period.
The contractor continues every effort to maintain a clean and orderly work site and to minimize disruptions to
traffic, residents and pedestrians while maintaining high safety standards.
1. Building height: The issue of the overall building height continued to be an issue this month. The result
of this issue was a suspension of work (details above) for a period of 10 work days. The issue seems
to have been resolved but will most likely result in a contract time extension commensurate with the
period of suspension.
None executed
Page 2 of 5
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
CM CONTRACT
ACTIVITIES
Field inspection
Coordination with City staff, contractor and architect
Coordination of materials testing & special inspections
Tracking/administration of submittals, Requests for Information, Requests for Proposal and potential
changes
Weekly contractor progress meeting
Weekly coordination meeting with City
CONTRACT SUMMARY
Original Budget:
Expenditures this month:
Expenditures to date:
Budget Remaining:
$ 68,670.00
$ 5,280.00
$ 28,330.00
$ 40,340.00
STAFF
Page 3 of 5
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
Page 4 of 5
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
Page 5 of 5
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
RESIDENT ENGINEERS
MONTHLY REPORT
Monthly Report No.:
Contract Amount
Approved CCO
Current Contract Amount
Monthly Progress Invoice
Cumulative Invoiced
Progress to Date (budget)
$ 619,654
$ 0
$ 619,654
$ 66,689
$ 178,890
29%
The curvature of the wall design required the use of a material that is more flexible than standard
plywood but must still withstand the loads from the concrete when it is placed in the forms. The
contractor utilized a masonite material; it is pliable and able to conform to the design curvatures,
however, the material is not as strong as plywood. Multiple layers of this material were used and the
number of supports was significantly increased to provide a forming system that could withstand the
loads from the concrete when it was placed without failing (bulging or bursting).
The design of the exterior front walls calls for board form finish. To achieve this effect, the contractor
used rough cut board lumber milled to varying thicknesses and cut to random lengths to construct a
form liner that will produce a rustic board form texture on finished the walls when the forms are
stripped.
Building walls are colored concrete; this makes it nearly impossible to patch any imperfections as a
patch would never match. The workability of the concrete was increased by using an admixture in the
concrete and access holes were cut mid-height in the wall forms so that the concrete could be delivered
at an intermediate level; these measures minimized the chance of rock-pockets that could need
remedial work.
The City received confirmation from PG&E that the tie-in for the site electrical can come off of the first power
pole on Santa Lucia; this will significantly decrease the amount of conduit to be installed for the electrical
connection. The contractor has scheduled directional boring to install the electrical conduit for the first week in
September.
Page 1 of 6
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
The contractors activities included the following:
Install reinforcing steel for walls
Completed forming for all walls
Electrical subcontractor installed imbeds
Placed concrete for all walls
The contractor has consistently made every effort to maintain a clean and orderly work site and to minimize
disruptions to traffic, residents and pedestrians while maintaining high safety standards.
The time to budget indicates a lag in the overall project progress. The suspension of work during the month of
July has impacted the completion schedule for the project; the current completion date is projected to be
November 10th (vs. original date of October 24th). During the month of September a number of big ticket
items will complete which will narrow the discrepancy between the expended budget and expended time.
The contractor is being as efficient as possible in his operations and is attempting to make up time wherever
possible.
PROJECT ISSUES (NEW)
1. Break-in at project site intruder(s) cut the chain link fencing material along the pedestrian pathway to
gain access to the project site. The contractor contacted the police department and indicated that all
tools & equipment were stored in the storage container (which was not breached); the only thing
missing was about 20 feet of copper grounding cable that was cut and removed from the site.
REQUEST FOR QUOTE/POTENTIAL CHANGES
No new items
CHANGES
None executed
CM CONTRACT
ACTIVITIES
Field inspection
Coordination with City staff, contractor and architect
Coordination of materials testing & special inspections
Tracking/administration of submittals, Requests for Information and potential changes
Review of contractors invoice
Contractor progress meeting
Weekly coordination meeting with City
Page 2 of 6
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
CONTRACT SUMMARY
Original Budget:
Expenditures this month:
Expenditures to date:
Budget Remaining:
$ 68,670.00
$ 6,400.00
$ 34,740.00
$ 33,940.00
STAFF
Page 3 of 6
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
Page 4 of 6
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
Page 5 of 6
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
Page 6 of 6
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
RESIDENT ENGINEERS
MONTHLY REPORT
Monthly Report No.:
Contract Amount
Approved CCO
Current Contract Amount
Monthly Progress Invoice
Cumulative Invoiced
Progress to Date (budget)
$
$
$
$
$
619,654
0
619,654
148,767
418,286
68.5%
Page 1 of 5
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
While excavating for the percolation trench on site, the contractor encountered bones of an unknown
type/origin. All operations pertaining to the trench excavation were suspended and Carmel PD was contacted.
A representative from the PD observed the bones and took photos; several hours later we were informed that
the bones were not human and that work could resume. The percolation trench was completed the following
day.
The masonry contractor continued work on the stone veneer for the site walls and began work on the building
walls this month. The architect was readily available to review the stone materials when they arrived on site to
confirm that the color and size were appropriate; he was also quite involved in the oversight of the stone
placement/installation itself including directing the placement of select stone pieces to achieve the desired
appearance.
PROJECT ISSUES (NEW)
Encountered bones while excavating for percolation trench; details noted above.
No new items
CHANGES
None executed
CM CONTRACT
ACTIVITIES
Field inspection
Coordination with City staff, contractor and architect
Coordination of materials testing & special inspections
Tracking/administration of submittals, Requests for Information and potential changes
Review of contractors invoice
Contractor progress meeting
Weekly coordination meeting with City
CONTRACT SUMMARY
Original Budget:
Expenditures this month:
Expenditures to date:
Budget Remaining:
$ 68,670.00
$ 7,520.00
$ 42,250.00
$ 26,420.00
STAFF
Page 2 of 5
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
Page 3 of 5
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
Page 4 of 5
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
Page 5 of 5
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
RESIDENT ENGINEERS
MONTHLY REPORT
Monthly Report No.:
Contract Amount
Approved CCO
Current Contract Amount
Monthly Progress Invoice
Cumulative Invoiced
Progress to Date (budget)
$
$
$
$
$
619,654
0
619,654
119,784
551,380
89 %
The contractor placed concrete for the floor slab; this was the final concrete placement for the project. With the
floor slab complete, the piping for the building plumbing could be completed. Wall studs were installed and
sheetrock was hung in preparation for the interior tile. The subcontractor began installation of the wall tile in
both restrooms.
On the roof, the copper flashing was measured and fitted for the roof edges and scuppers. The waterproofing
system (multiple layers of materials) was installed on the roof and the drainage blanket for the green roof
was installed in preparation for the green roof elements.
The masonry contractor continued work on the stone veneer for the building walls this month. The architect
remained readily available to review the progress of the stonework.
PG&E confirmed that they had received payment and signed contract from the City; this allows PG&E to
schedule the work involved in connecting the service to the site. We have been told that there is a six-week
backlog so the anticipated date for setting the meter will be in mid-December.
Project No. _______ File No.
Page 1 of 5
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
The Project Status above indicates that the contractor is beyond the original contract completion date.
However, the contractor is entitled to an adjustment in contract time for several items including issues with the
suspension of work (earlier in the project), changes related to the doors and the delay in getting permanent
power to the site. The contractor has diligently prosecuted the work on the project and the adjustments in
contract time due to owner changes/delays will more than account for the extended completion date.
PROJECT ISSUES (NEW)
PG&E schedule for providing service to the site is anticipated to be mid-December which is well beyond
the anticipated contract completion date. Although almost every item will be complete well before the
PG&E tie-in date, the contractor cannot complete his work nor can we do a final walk-thru without
permanent power; the contractor will be entitled to an extension of contract time commensurate with the
delay in getting power from PG&E.
CHANGES
None executed - A change order will be executed to adjust contract time and costs once we have
power to the site.
CM CONTRACT
ACTIVITIES
Field inspection
Coordination with City staff, contractor and architect
Coordination of materials testing & special inspections
Tracking/administration of submittals, Requests for Information and potential changes
Review of contractors invoice
Site coordination meetings
Weekly coordination meeting with City
CONTRACT SUMMARY
Original Budget:
Expenditures this month:
Expenditures to date:
Budget Remaining:
$ 68,670.00
$ 4,320.00
$ 46,570.00
$ 22,100.00
STAFF
Page 2 of 5
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
Page 3 of 5
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project
Page 4 of 5
CITY OF CARMEL-BY-THE-SEA
Beach Restroom Project