Professional Documents
Culture Documents
ShaftSinkingPracticesfor Mining
ShaftSinkingPracticesfor Mining
J.S. Redpath
C. Heever
Chapter 58
SHAFT SINKING AT NOSE ROCK
by
Mr. James O. Greenslade
Phillips Uranium Corporation
Vice President of Mining & Milling
Crownpoint,New Mexico
Mr. Cherie Tilley
Phillips Uranium Corporation
DevelopmentManager
Crownpoint,New Mexico
Mr. Gerald G. Griswold
Harrison Western Corporation
Vice President of EngineeringServices
Denver, Colorado
Mr. Richard Reseigh
Harrison Western Corporation
Manager of Engineering& Administration
Crownpoint,New Mexico
INTRODUCTION
The Harrison Western Corporation,a leading Denver based mine
contractingand engineeringconcern, is presentlyengaged in
sinking two 1,006 m (3,300 ft) shafts for the Phillips Uranium
Corporationat their Nose Rock Project, approximately13 miles
northeast of the small communityof Crownpoint in McKinley County,
New Mexico. The Nose Rock Project is the first attempt by the
Phillips Uranium Corporationto tap the deep uranium reserves in
what has become known as the Grants Mineral Belt. (See Figure 1)
Project Description
Phillips Uranium Corporations plan for the large 2700 metric
ton per day (2950 tons/day)mining facility calls for a series of
deep access and ventilationshafts ranging from 4.27 m (14 ft) to
5.49 m (18 ft) in diameter to approximatedepths of 1,006 m (3,300
ft). The initial pair of shafts consists of one production shaft and
one ventilationshaft separated by a distance of 91 m (300 ft). The
interbedded
layers
of sedimentary
sandstones
and shales to be
penetrated
by the shafts
contain
several
major water producing
aquifers,
the deepest being the mineralized
zone called
the Westwater
Canyon Member of the Morrison Formation.
955
956
957
(860F).
958
WCI),.OUJCTION
C.EOLCC,C
~.w..!o.
COLUMN
SHAFT
(No,,
v,r4T,.AT,ON
,_L_EPT.
T-
.m. . .
=%%:
M, N, F.,
..s.O
MLLATO
TONG.,
OF . . .
MA.cos
... ..
MC,t.lcos
8120
(26s
1
w,
,,6()
,W.R
w...
FIGURE 2.
w..,.
m,,
, ,...,,
i
SHAFT
959
980
Dakota Sandstone
and six wells in the Westwater Canyon Member.
The casing was slotted
throughout
the total
length of each aquifer
and the pump settings
were generally
just above each aquifer.
Formation
Gallup
Dakota
Westwater
Number
Wells
Months
Pumped
6
4
4-6
17
14
6
Yield
1080 gpm
1120 gpm
1760 gpm
lni.tial
Pressure
1038 psi
1537 psi
1711 psi
Residual
Pressure
135 pai
350 psi
238 pSi
Effect
82$
77%
86%
Formation
With
Wells
Without
Wells
Gallup
1,080 gpm
2,307 gpm
Dakota
1,120 gpm
Westwater
2,212 gpm
2,562 gpm
5,020 gpm
Table 2.
961
962
963
SHAFT SINKING
For the most part, the shaft sinking methods used at the Nose
Rock Project can be classifiedas conventional. Methods and
techniquesemployed on any project depend, to a large extent, on
safety and health regulationspromulgatedby appropriateregulatory agencies at both state and federal levels. At the federal
level, the project falls under the Federal Mine Safety and Health
Act of 1977 (PublicLaw 95-164) and is administeredby the newly
created Mine Safety and Health Administration
of the Department
of
subsequent
to enactment of the ~977 Act, the New Mexico
Labor.
Mine Safety Code has adopted the federal standardsas their own.
In addition, the state of New Mexico periodicallydevelops
stricter standards,mostly as a result of previous serious accidents. The most importantof these to the shaft sinker is a
requirementlimiting unsupportedground in vertical shafts to 3 m
(lo
f%).
964
VERTICMSCME
FMMATION
mri
PLUG
WTER-BEMINC
SANDS
\__!,..51,00
VERTICAL CROSS-SECTION
OFDRILL
HOLE
PLAN-TYPICAL DAKOTA GROUT COVER
965
Sinking Equipment
The permanent productionhoist and headframe are used for
sinking the 5.5 m (I8 ft) diameter production shaft. The hoist is
a 1,119 kw (1,500 hp) double drum, double clutch unit, capable of
610 meters per minute (2,000 fpm) line speed. A temporaryhoist
and headframe are used for sinking the 4.9 m (16 ft) ventilation
shaft.
The hoist is a 1,007 kw (1,350 hp) double drum, single
clutch unit capable of 579 meters per minute (1,900 fpm) line
speed. Hoist ropes are 38.1 mm (1.5 in) diameter and are of 18 x
7 non-rotating right lang lay construction.
Compressed alr is supplied
to both shafts
by seven electrically
powered rotary
compressors
located
on the surface.
A portable
concrete
batching
plant is used to supply concrete
into transit
trucks that mix and deliver
it to t e respe tive shafts.
Concrete
is transported
underground
in 2.7 m9? (95 ft ) buckets.
Galloway stages are suspended by four 25.4 mm (1 in) locked
coil ropes and are used in each shaft as work platforms. Each
Galloway consists of four decks and weighs approximately31,070 kg
(65,000 lb). The locked coil ropes serve as crossheadguides for
the counterbalancedbuckets. The Galloway stages are raised and
lowered by four winches that are electricallywired to operate
together,although any winch can be clutched out by hand in order
to periodicallybalance tension between the ropes. The rope speed
of the Galloway winches is about 2.4 meters per minute (8 fpm).
The Cryderman shaft mucker anchored to the lining with brackets
is used for mucking (excavationof blasted material). Invented
and developed in Canada, the mucker is essentiallyan air powered
clamshellmounted on a telescopingboom. Positioningcylinders
and the telescopingfeatures of the boom itself allow positive
crowd at any location on the muck pile. The machine is controlled
by levers actuating two four-way valves, with the left hand controlling boom position and the right hand controllingthe
clamshelland the telescopingfeature of the boom. Two units are
used in the larger productionshaft and a single unit in the
ventilationshaft. In all cases, the units are suspendedon cable
winches located on the surface with the rail and bracket anchoring
systems al owing v rtical movement only. Muck bucket izes ran e
from 2.7 m 39(95 ft ) in the ventilation
shaft to 3.5 mY!!l
(123 ft )
in the production
shaft.
Drilling
is done with 28 kg (62 lb) hand-held.
piston diameter
of 67 mm (2-5/8 in).
Drills
are
sinkers
lowered
with a
in a
966
FIGURE 4.
967
968
FIGURE 5.
MUCKING
969
Techniques
Instrumental
to the attainment
of high sinking
rates is a
program which controls water that leaks through pour Joints
in the
liming and falls
on the crew below. Left uncontrolled,this water
would eventuallybuild to levels that adversely affect every facet
of a shaft sinking operation from equipmentmaintenanceto overall
crew morale.
Backaheeti~
Also known as panning,
this operation
basically
consists
of placing
thin sheets of metal againat
the exposed rock
when sinking through productiveaquifers and bringing the water
through the lining In pipes. After 3 m (10 ft) is excavated
through the aquifer and before the curb ring is lowered, backsheeting and weep pipes are placed against the upper 2.4 m (8 ft)
of the shaft to be poured. The weep pipes consist of a perforated
leg placed between the metal and the aquifer, a 90 en, a niPPle
that extends from the perforatedleg to the form and a coupling
970
FIGURE 6.
971
that attaches the weep pipe to the form. After the curb ring is
lowered, the pipes are attached to the form with a fastening
device that threads into the coupling and allows the water to come
through the form. The curb ring is then filled with concrete
forming a tight seal for the bottom of the pour. After the
remaining form is lowered and poured, the water flows freely
through the weep pipes. These are later connected to a 10.2 mm
(4) drain line which carries the water into a pump station or a
super water ring!discussed further below.
Super Water Rings
The in-shaft
pumping system consisted
of 43 kw
(58 hp) submersible
pumps on the bottom and staged up the shaft
wall in distances not exceeding 61 m (200 ft). The electric
submersiblepumps of this type require frequentmaintenanceand
normally this must be done on the surface. To facilitatepump
changeout and provide a sump for staged pumps, Harrison Western
engineers developed the !fsuperwater ring. Essentially,the
super water ring is the enlargementof a 3 m (10 ft) vertical
section of the shaft by .6 m (2 ft) in radius with a .6 m (2 ft)
steel dam installed flush with the shaft lining. Submersible
pumps in these rings eventually transfer water to temporaryor
permanent pumping stations.
FiberglassWater Rings The purpose of the fiberglasswater ring
is to collect water running on the inside of the shaft lining.
The rings are installedabove pump stations, super water rings or
periodicallywhen needed, and are connectedwith hose or piping to
the drain line, super water ring or station. They are fabricated
to attach to the concrete form and are easily installed.
Bonus and Incentives
In recent years,
industrial
managers have gravitated
towards
the theories
of motivation
espoused by such management theorists
These theories
stress
job
as Fredrick
Herzburg et al.
enrichment!
or other such enlargementof an individualstask or
area of responsibilityas a motivating force in order to otherwise
offset the boredom and dissatisfactionthat often accompaniesthe
modern industrialwork setting.
For the most part,
these theorists
would deny that additional
remuneration
is a motivating
factor
per se, although
admitting
that substandard
pay scales can be a source of considerabledissatisfactionamoung a work force. Undergroundconstructionand
mining in the Rocky Mountains and in a large portion of Canada are
some of the last bastions of the piece work system still existing
in North America, albeit in modified form.
Seemingly in defiance of modern management theory, the Nose
Rock Project has successfullyapplied two forms of bonus
972
Permanent
973
Pump Stations
974
CONCLUSION
975
REFERENCES
chenowith,
Greenslade,
W.M., Sprouls,
E.P.,
1977, Geotechnical
and
Hydrologic
Investigation,
Production
Shaft,
Mining Unit
Nose Rock Project,
Dames and Moore, Phoenix,
Arizona.
1,