Professional Documents
Culture Documents
RETAININGWALL (DESIGN WITH Equivalent Water Pressure)
RETAININGWALL (DESIGN WITH Equivalent Water Pressure)
RETAININGWALL (DESIGN WITH Equivalent Water Pressure)
Subsection: 5.1
Effective: October 1, 1991
Supersedes: December 1, 1990
5.1.1
5.1.1.A
GENERAL
5.1.1.B
5.1.1.C
The designer should come up with a default detailed design along with the
design alternative(s) if applicable.
The requirements for assigning
alternate wall are described in Subsection 5.8. The default design is
defined to mean the best wall obtained from the selection process. For
earth retaining wall project, regardless of the type of wall actually
constructed (default or alternate), the measurement and payment are based
on the plans of default design as specified in Subsection 5.6. Design
alternatives are the products of the selection process described in
Subsections 5.4 and 5.5.
The design alternatives furnished in the
bidding documents shall be at the level of conceptual designs and in the
form of typical profiles with dimensions.
Using Subsection 5.7 as
guides, the designer shall specify the requirements of the Contractor or
supplier prepared designs and plans for the design alternative(s).
5.1.1.D
For all earth retaining wall design projects the objective and
constraints should be properly defined.
These include, but are not
limited to, wall geometry, such as: 1. Tolerance on finished product;
such as vertical and horizontal position of the wall top line. 2.
Allowable long-term wall settlement.
October 1, 1991
Page
2 of 6
5.1.1.E
5.1.1.F
All walls can be designed with a unit width (except that the plane strain
condition is no longer valid, when conditions exist such as wall
alignment across a ravine, founded on sloped compressible layer, has a
non-uniform seepage force, flood plain erosion is anticipated, etc.).
In case of doubt a cross-section of the soil strata along wall alignment
plus soil strata section(s) across wall alignment are needed, for serious
landsliding potential and a three dimensional study may be needed to
determine the pattern of fill movement and the corresponding deformation
of the wall. Designer must bear this in mind.
5.1.1.G
October 1, 1991
5.1.1.H
Page
3 of 6
5.1.2.A
TOP OF WALL
For a retaining wall without a curb or concrete barrier attached, the top
of the wall shall be a minimum of one foot above the ground at the back
face.
5.1.2.B
5.1.2.D
FOOTING-COVERS
5.1.2.E
GUTTER
5.1.2.F
October 1, 1991
5.1.3.A
Page
4 of 6
5.1.3.B
WALL FACING
5.1.3.C
IMPERVIOUS MEMBRANE
5.1.3.D
DRAINAGE BLANKET
October 1, 1991
5.1.3.E
Page
5 of 6
Fill material shall meet the following requirements when tested with
laboratory sieves:
Sieve Size
Percent Passing
3 Inches
3/4 Inches
No. 40
No. 200
100
20-100
0-60
0-5
TEST Method
Resistivity
Chlorides
Sulfates
PH 6-10
5.1.3.F
15
4
5.1.3.G
and/or
October 1, 1991
5.1.3.H
Page
6 of 6
5.1.3.I
1.
Fill material shall meet the following requirements when tested with
laboratory sieves:
Sieve Size
Percent Passing
3 Inches
No. 40
No.200
100
0-60
0-15
2.
3.
4.
5.
5.1.3.J
1.
2.
During construction the CDOT shall have a plan for sampling and
material testing to ensure that the material meets the
specifications in the contract document.
Subsection: 5.2
Effective: October 1, 1991
Supersedes: December 1, 1990
A.
B.
A cover letter,
DOT Form 595,
Wall Record(s) (Page 5 of 5 of this Subsection)
Supporting documents (10 items described in this Subsection).
The Department will evaluate and approve the system, based on the
following considerations.
*
A letter
product.
from
P.E.
registered
in
Colorado
certifying
the
2.
3.
October 1, 1991
Page 2 of 5
4.
5.
6.
7.
8.
9.
10.
October 1, 1991
Page 3 of 5
October 1, 1991
Page 4 of 5
October 1, 1991
Page 5 of 5
WALL NAME(TM):
PATENT INFORMATION (no. and duration of validity):
RANGE OF WALL HEIGHT:
WALL SCENARIO (if applicable):
* TYPE AND CONDITION OF STRUCTURAL BACKFILL MATERIAL:
* TYPE AND CONDITION OF RETAINED FILL:
* EQUIVALENT STRENGTH PARAMETERS OF REINFORCED SOIL MASS FOR GLOBAL
STABILITY ANALYSIS OF INTERNALLY STABILIZED SYSTEM:
* DRAINAGE DESIGN AND/OR ASSUMED WATER PRESSURE:
* MINIMUM DEPTH OF TOE COVER:
* MAX. ESTIMATED POST-CONSTRUCTION WALL LATERAL MOVEMENT (ROTATION AND
TRANSLATION):
* MAX. ALLOWABLE SETTLEMENT OR DIFFERENTIAL SETTLEMENT:
* MAX. TOE PRESSURES (@ 5 increment to max. height):
* SURFACE TREATMENT OF BACKFILL:
WALL ATTACHMENTS (circle proper applicable items):
*
*
*
*
*
RAIL,
WALL COPING/DRAIN,
RAIL WITH SLEEPER SLAB,
LEVELING PAD.
OTHER (SPECIFY)
* SOUND BARRIER,
* TRAFFIC SIGN,
* RAIL WITH EMBEDDED POST,
* POST WITH CHAIN LINK,
* FACING PANEL,
* BRIDGE ABUTMENT,
* UNDERPASS,
* EMBANKMENT,
* LANDSCAPING.
Subsection: 5.3
Effective: October 1, 1991
Supersedes: December 1, 1990
2.
3.
October 1, 1991
Page 2 of 3
October 1, 1991
Page 3 of 3
Subsection: 5.4
Effective: May 1, 1992
Supersedes: October 1, 1991
SPATIAL CONSTRAINTS
* FUNCTIONS OF WALL*
ROADWAY AT FRONT OF WALL.
ROADWAY AT BACK/TOP OF WALL.
GRADE SEPARATION OR LANDSCAPING OR NOISE CONTROL.
RAMP OR UNDERPASS WALL.
TEMPORARY SHORING OF EXCAVATION.
STABILITY OF STEEP SIDE SLOPE.
FLOOD CONTROL.
BRIDGE ABUTMENT.
OTHER (SPECIFY)
May 1, 1992
5.4.2
-
Page 2 of 9
May 1, 1992
Page
3 of 9
of
May 1, 1992
Page 4 of 9
cantilever
walls,
embedded
May 1, 1992
Page 5 of 9
5.4.3
FILL RETENTION
(bottom-to-top construction)
CUT RETENTION
(top-to-bottom construction)
1.
Earth Walls
(extensible and inextensible
tensile reinforcements)
1.
Earth Walls
(soil nails)
2.
2.
3.
ECONOMIC CONSIDERATIONS
* Environmental constraints *
ECOLOGICAL IMPACTS ON WET LAND.
CORROSIVE ENVIRONMENT ON STRUCTURAL DURABILITY.
WATER POLLUTION, SEDIMENT OR CONTAMINATED MATERIAL.
NOISE/VIBRATION CONTROL POLICY.
STREAM ENCROACHMENT.
FISH/WILDLIFE HABITATION OR MIGRATION ROUTES.
UNSTABLE SLOPE.
OTHER (SPECIFY)
* Economic factors *
CONSTRUCTION SCHEDULE.
AVAILABILITY OF FILL MATERIAL.
SUPPLY OF LABORERS.
HEAVY EQUIPMENT REQUIREMENTS.
FORMWORK, TEMPORARY SHORING.
DEWATERING REQUIREMENTS.
AVAILABLE STANDARD DESIGNS.
BUY COLORADO IMPACT.
TEMPORARY VERSUS PERMANENT WALL AND FUTURE WIDENING
COST OF DRAINAGE SYSTEM.
DESIGN AND INSTALLATION OF WALL ATTACHMENTS.
NEGOTIATED BIDDING AND DESIGN/BUILD ON NON-STANDARD PROJECTS.
MAINTENANCE COST, READJUSTMENT AND REMODELING.
UNCERTAINTY OF SITE AND WALL LOADS.
COMPLEXITY OF PROJECT:
HEIGHT DIFFERENCES IN FINISHED OR BASE GRADES.
NUMBER OF WALL TURNING POINTS.
SCALE OF PROJECT.
LENGTH/HEIGHT OF WALL - QUALITY CONTROL OF FILL MATERIAL.
POST-TENSIONING, GROUTING, TRENCHING, SLURRY.
PILE DRIVING, CAISSON DRILLING.
PRE-CASTING, TRANSPORTATION AND INSPECTION.
QUANTITY OF EXCAVATION.
QUANTITY OF BACKFILL MATERIAL.
May 1, 1992
Page 6 of 9
small figure
May 1, 1992
Page 7 of 9
CONSTRUCTIBILITY
MAINTENANCE
SCHEDULE
AESTHETICS (APPEARANCE)
ENVIRONMENT
DURABILITY OR PROVEN EXPERIENCE
AVAILABLE STANDARD DESIGNS
COST (see page 9 of this Subsection)
5.4.5
1.
2.
The sum of weight points of any two major factors shall be less than
or equal to 70 points.
3.
For simplicity minor factor(s) can be removed from the rating matrix
if they are (is) given the same score on all selected wall types.
May 1, 1992
Page 8 of 9
|* standard design
|* generic software/design aid
|* vendors software
|*
|*
|*
previous cost
data books
vendors information
|*
|*
* excavation/shoring
* structural backfill,
reinforced conc. soil
reinforcements, tieback
anchors
* facing/rail/barrier/drainage
* backfill
|*
old reports
May 1, 1992
Page 9 of 9
WL HT
EXCAV BACKFILL
CONC
STEEL RAIL
$7.00 $14.00
$200
$0.4
$140
1.78
1.89
2.11
0.33
0.51
0.67
17.0
22.0
27.0
1
1
1
4
6
8
-
1.19
1.62
2.38
COST/ST COST/SF
WALL COST
$240.0
$290.0
$339.0
$61.30
$48.27
$42.40
WL HT
EXCAV BACKFILL
GRIL
$6.00 $12.00
$1.25 $7.50
FACING
COST/FT COST/SF
RAIL
WALL COST
$180.
4
6
8
-
STATION
NUMBERS
WALL
LENGTH
PERCENTAGE
OF TOTAL
CPI WALL
$/FT TOTAL
MSE WALL
$/FT TOTAL
64100
63955
36875
145
80
60
15%
22%
25%
350.5 50750.
440.0 35200.
520.5 31200.
340.0 49300.
480.5 38440.
600.0 36000.
900
100%
$850,000.
$650,000.
Subsection: 5.5
Effective: October 1, 1991
Supersedes: December 1, 1990
2.
3.
4.
with
yes,
no
or
question
October 1, 1991
Page 2 of 5
October 1, 1991
Page 3 of 5
October 1, 1991
Page 4 of 5
October 1, 1991
Page 5 of 5
Subsection: 5.6
Effective: October 1, 1991
Supersedes: New
1.
2.
The unit price bid defined above shall be full compensation for
furnishing, handling, and placing of concrete materials; fabricating
curing and finishing the wall face; finishing and placing all means
of soil reinforcements, joint fillers, waterstops, filter material
and incidentals; for all reinforcing steel; for all excavation; for
all backfill, including select backfill; for all labor and material
required to construct wall facing and concrete leveling pads to the
line and grades as shown on the plans; wall erection; sprinkling and
rolling for granular backfill material; for finishing and placing all
temporary shoring, including soldier shafts or piling; cost of all
means of subsoil improvement; deep foundation cost of additional
subsoil exploration; and for all labor, tools, equipments and
incidentals necessary to complete the work. The unit price bid shall
apply for the default wall selection shown on the plans or any
allowable alternate which the Contractor elects to construct.
3.
4.
Pay Unit
Sq Ft
For the purpose of useful record and future selection study, wall
descriptions shall contain wall type, wall length, wall average
height/standard deviation, type of facing, type of foundation
improvement, barrier and rail if applicable.
Subsection: 5.7
Effective: October 1, 1991
Supersedes: New
1.
2.
3.
4.
B.
A plan view of the wall which shall indicate the offset from the
construction centerline to the face of wall at all changes in
horizontal alignment, the limit on the dimension of the widest
mesh or strip and the size and the centerline of any structure
or pipe which is behind or passes under or through the wall.
C.
D.
E.
F.
October 1, 1991
Page 2 of 2
5.
6.
All details for foundations and leveling pads, including details for
steps in the footings or leveling pads, as well as allowable and
actual maximum bearing pressures.
7.
All facing elements shall be detailed. The details shall show all
dimensions necessary to construct the element, all reinforcing steel
in the element, and the location of reinforcement element attachment
devices embedded in the facing.
8.
9.
10.
11.
to internal
settlement,
protection.
any symbols
Subsection: 5.8
Effective: May 1, 1992
Supersedes: October 1, 1991
6. The designer shall provide LOG OF TEST BORINGS on the final plans
which give enough information to support the default wall design and
to facilitate the contractor prepared detail design of the identified
alternative wall.
7. If the designer selects on-site backfill material for the alternative
walls, he shall provide a summary of the site specific material
properties from the soils report as well as the minimal
May 1, 1992
Page 2 of 3
E. Boring logs, and a phone number for accessing the geology report.
The following information shall also be provided as necessary to
implement the designers intent for the foundation:
-
May 1, 1992
Page 3 of 3
DEFAULT
WALL
N/A
YES
YES
ALTERNATE
WALLS
YES
YES
YES
DESCRIPTIONS
Height less or equalt to 16 feet
with class 1 backfill, toe pressure
3 ksf or less, secondary or
temporary wall, no bearing capacity
and/or settlement problems, mse or
modular proprietary walls.
Walls on spread footing with
correctable settlement and bearing
capacity problems, alternate
designs tend to be cost effective,
or need attention on wall geometry,
facade, rail, attachments, site
specific detailed design, on-site
backfills.
Special walls, foundation on
difficult soil or site specific
marginal backfill material, walls
need deep foundation, scour
protection, walls inappropriate to
design separately.
REMARKS:
Case A -
Case B -
Case C -
Subsection: 5.9
Effective: October 1, 1991
Supersedes: New
CDOH Standard Specifications for Road and Bridge Construction will govern
the selection and use of backfill materials, including backfill materials
behind retaining walls. CDOH Specification Item 703.08 makes reference
to Structural Backfill Classes I and II. In most cases these backfill
materials shall be assumed in the design of retaining walls as follows.
1.
2.
2.
3.
D
D
D
D
+
+
+
+
E
E + SC (Surcharge)
E + RI (Rail Impact)
E + SC + W
October 1, 1991
Page 2 of 7
4.
Draw a vertical line from the back face of footing to the top of
fill. This line serves as the boundary of the free body to which
the earth pressure is applied. The applied active earth pressure
shall be estimated by Rankine theory, and direction assumed parallel
to the backfill surface. Compute the resultant (P) of the applied
earth pressure and associated loads. Resolve P into its horizontal
and vertical components (Ph & Pv) and apply it at 1/3 of the total
height (TH) of the imaginary boundary from the bottom of footing.
5.
Take a free body of the stem and compute the loads applied at the
top of stem as well as loads along the stem (height H), and find the
moment and shear envelope to meet all the design cases at several
points along the height. The WSD method and the concept of shear
friction shall be used to calculate the shear strength at the cold
joint between footing and stem.
6.
Compute the weight (Wt) which is the sum of the weight of concrete
and the weight of soil bounded by the back of the concrete wall and
the vertical line defined by the step 4 above. Find the distance
from the extremity of toe to the line of action of Wt which is the
stabilizing moment arm (a).
7.
= RM/OM
= [Wt * a) + (Pv * B)]/(Ph * TH/3).
9.
For simplicity toe pressure (q) can be evaluated and checked by the
following equations:
q = (Wt/B) * (1 + 6 * ec/B),
The toe pressure (q) shall be equal to or less than the allowable
bearing capacity as noted by the soils report. Toe pressure is most
effectively reduced by increasing the toe dimension.
October 1, 1991
Page 3 of 7
10.
The footing, both toe and heel, shall be designed by WSD for soil
reaction acting upward and all superimposed loads acting downward.
The heel design loads shall include a portion of the vertical
component (Pv) of earth pressure which is applied to heel as shown
on page 4 of this Subsection.
For the toe design loads and
stability, the weight of the overburden shall not be used if this
soil could potentially be displaced at some time during the life of
the wall.
11.
Check factor of safety against sliding without using shear key. The
coefficient of friction between soil and concrete is approximated to
be tan(2/3 * ). Neglect the passive soil resistance in front of
toe. The sliding resistance (SR) can be evaluated as:
SR = (Wt + Pv) * tan (2/3 * ).
The required F.S. (sliding) which is (SR/Ph) shall be equal to or
greater than 1.5. If F.S. (sliding) < 1.5, then either the width of
footing shall be increased or a shear key shall be installed at the
bottom of footing.
If shear key is the choice, the depth of the inert block (c) is
computed by the sum of the key depth KD and the assumed effective
wedge depth which is approximated to be half the distance between
the toe and the front face of shear key (b1/2). Using the inert
block concept and knowing the equivalent fluid weight ( p) of passive
soil pressure, and neglecting the top one foot of the toe overburden
(TO), the toe passive resistance (Pp) is
Pp = 0.5 * p * [ (TO + T + c - 1)2 - (TO + T - 1)2 ].
Total sliding resistance (F) from friction is the sum of the
horizontal component of the resistance from toe to shear key (f1)
and the resistance from shear key to heel (f2), then
F
where :
R1:
R2:
Sliding resistance is
SR = F + Pp.
The F.S.(sliding) which is (SR/Ph) shall be equal to or greater than
1.5.
12.
October 1, 1991
Page 4 of 7
CDOT
STRUCTURAL
BACKFILL
CLASS
DESIGNATION
TYPE OF SOIL
COMPACTION
CONFORMS WITH
AASHTO 90-95%
T180
2 (H) ON 1 (V)
BACKFILL
BORROWED
SELECTED
COARSE
GRAINED SOILS
GRADATION PER
703.08
LOOSE SAND OR
GRAVEL
40
(ACTIVE)
50 (ACTIVE)
55
(AT REST)
65 (AT REST)
CLASS I
ON-SITE
INORGANIC
COARSE
GRAINED
SOILS, LOW %
OF FINES
CLASS II-A
ON-SITE
INORGANIC
LL < 50%
CLASS II-B
ON-SITE
INORGANIC
LL > 50%
CLASS II-C
MEDIUM DENSE
SAND OR GRAVEL
35 (ACTIVE)
45 (ACTIVE)
50 (AT REST)
60 (AT REST)
DENSE5 SAND AR
GRAVEL 95% p
T180
30 (ACTIVE)
40 (ACTIVE)
45 (AT REST)
55 (AT REST)
COMPACTED
CLAYEY SANDY
GRAVEL
40 (ACTIVE)
50 (ACTIVE)
60 (AT REST)
70 (AT REST)
COMPACTED
CLAYEY SILTY
GRAVEL
45 (ACTIVE)
55 (ACTIVE)
70 (AT REST)
80 (AT REST)
COMPACTED
SILTY/SANDY
GRAVELLY
LOW/MEDIUM
PLASTICITY
LEAN CLAY
FAT CLAY,
ELASTIC SILT
WHICH CAN
BECOME
SATURATED
NOT RECOMMENDED
FOOTNOTES:
1.
2.
3.
4.
5.
6.
NOT DEFLECT OR
TOP OF WALL OF
BE INDUCED BY
PRESSURE.
October 1, 1991
Page 5 of 7
October 1, 1991
Page 6 of 7
October 1, 1991
Page 7 of 7