Professional Documents
Culture Documents
Sites Checklist
Sites Checklist
Access Status
No
1
2
3
4
5
Item
Access is clear
Access ladders are installed
Fence is installed
Gate is installed
All of keys (gate, shelter & cabinets) delivered to EMO team
Severity
Critical
Critical
Critical
Critical
Critical
OK
Not Ok
N/A
Comment
Severity
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
OK
Not Ok
Comment
Severity
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
OK
Not Ok
Comment
Severity
Critical
Critical
OK
Not Ok
Comment
Power Source
No
1
2
3
4
5
6
7
8
9
10
11
Item
Power source is three phase
Power source is permanent
Main power cable protection
Main power cable routing and fixation
Power meter panel installation and fixation
Power meter panel grounding
Power meter panel sealing
Power meter panel (IP Quality)
Circuit breakers range (amp) is sufficient to every equipment in the site
Termination of main power cable
PDB installation and fixation
RF System
No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Item
Antennas fixation
Antennas Verticality
Antennas ports sealing
Mechanical and electrical Antennas tilt
Antennas Azimuth
Antenna Height
RBS jumpers fixation and arrangement
Feeders connectors fixation
Feeders connectors sealing
Feeders fixation on the tower by clamps
Earth kits installation
Earth kits sealing
Earth kits connecting to buss bar
Feeders fixation inside cable tray
Cable tray size
Cross feeder check
Sweep test (VSWR, DTF & Return Loss) check
TRM Installation
No
1
2
Item
Mounting of microwave antenna
Azimuth of microwave antenna
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
No
1
2
3
4
5
6
Installation of RAU
Grounding of RAU
IF cable connector weatherproofing
IF cable installation
IF cable over the tower arrangement by clamps
IF cable inside the shelter arrangement
IF cable inside cable tray arrangement
IF cable grounding (earthing) kit installation correctly
IF cable grounding (earthing) kit connected to buss bar
Mounting of TRM rack
Installation of AMM(2P/6P/20P
DCDU is installation
DCDU is grounded
Fan Unit Installation
Traffic cable installation
Installation of other cables (Fan alarm, NCC & DDU)
TRM rack grounding
Separation of DC power cable from signal cables
Far end can be launched by USB
All AMM have working protection power
Ensure MMU is not indicate alarm
Ensure that the DDF is grounded
Grounding all of equipments installed inside TRM cabinet
Dummy boards are installed in AMM if required
Checking RSL ,modulation ,configuration ,near end and far end IDs ,IP address ,and subnet mask
DCN is monitored
RBS Installation
Item
Base frame/cabinet mounting
Leveling of RBS cabinet
Grounding of RBS cabinet
External Alarms cable installation and testing
DC cable installation with lugs and shrinks
ESB cable installation
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Severity
Critical
Critical
Critical
Critical
Critical
Critical
OK
Not Ok
Comment
7
8
9
10
11
12
13
14
15
16
17
No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
No
1
2
3
4
5
6
7
8
9
No
1
2
3
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
Critical
OK
Not Ok
Comment
OK
Not Ok
Comment
OK
Not Ok
Comment
4
5
6
Critical
Critical
Critical
Tower Installation
No
1
2
3
4
5
6
Item
Tower verticality
Tower ladder installation
Safety wire installation
Safety wire fixation
Vertical feeder holder rack installation
All tower members bolts installation
Severity
Critical
Critical
Critical
Critical
Critical
Critical
OK
Not Ok
Comment