You can use the Bill of Material Comparison Report to report the comparison between two
manufacturing assemblies. You can compare primary bills, manufacturing and engineering bills,
alternates, and different revisions. Based on your comparison criteria, if the assemblies have
identical components, item sequences, operation sequences, yields, quantities, and
implementations, one line is printed for each identical component. Otherwise, the report prints a
separate line for each different component.
Additional Information
Procedure
Step Action
1. Begin by navigating to the Report Bill of Material Comparison page.
Step Action
2. Click the Manufacturing and Distribution Manager link.
Step Action
3. Click the vertical scrollbar.
Step Action
4. Click the Comparison link.
Step Action
5. Use the Organizations page to select your organization.
Step Action
6. Click the M1 Seattle Manufacturing list item.
Step Action
7. Click the OK button.
or Press [Alt+O].
Step Action
8. Use the Report Bill of Material Comparison page to enter the items to be
compared.
Step Action
9. Click in the Item field.
Step Action
10. Enter the desired information into the Item field. Enter "CM15138".
Step Action
11. Click in the Item field.
Step Action
12. Enter the desired information into the Item field. Enter "CM15140".
Step Action
13. Click the Report button.
or Press [Alt+R].
Step Action
14. Use the Note page to note the request ID.
Step Action
15. Click the OK button.
or Press [Alt+O].
Step Action
16. Click the View menu.
or Press [Alt+V].
Step Action
17. Click the Requests menu.
or Press [R].
Step Action
18. Use the Find Requests page to enter your request ID.
Step Action
19. Click the Specific Requests option.
Step Action
20. Click in the Request ID field.
Step Action
21. Enter the desired information into the Request ID field. Enter "5597143".
Step Action
22. Click the Find button.
or Press [Alt+i].
Step Action
23. Use the Requests page to view the status of the request that you submitted.
Step Action
24. Click the View Output button.
Step Action
25. Based on the comparison criteria, if the assemblies have identical components, item
sequences, operation sequences, yields, quantities, one line is printed for each
identical component.
Step Action
26. You have completed the Submitting the Bill of Material Comparison Report
procedure.