The Resource WhereUsed page enables you to view the operations and routings that use a
particular resource.
You can enter the name of the resource for which to view the operation and routing usage, and
the operation information effective on any particular date that you enter. The page displays the
operation details, resource details, and the resource sequence.
In this topic, you will view the resource usage.
Additional Information
Procedure
Step Action
1. Begin by navigating to the Resource WhereUsed page.
Step Action
2. Click the Manufacturing and Distribution Manager link.
Step Action
3. Click the vertical scrollbar.
Step Action
4. Click the Resource WhereUsed link.
Step Action
5. Use the Organizations page to select your organization.
Step Action
6. Click the M1 Seattle Manufacturing list item.
Step Action
7. Click the OK button.
or Press [Alt+O].
Step Action
8. Use the Resource WhereUsed page to view the operations and routings that use
a particular resource.
Step Action
9. Click in the Resource field.
Step Action
10. Enter the desired information into the Resource field. Enter "CDMOLD".
Step Action
11. The operation information effective on this date is displayed.
Step Action
12. Enter the desired information into the Effective Date field. Enter "04-NOV-2008
00:00:00".
Step Action
13. Click the Find button.
or Press [Alt+i].
Step Action
14. The Operation Details tabbed region displays the operation sequence,
department, the effective date range, and the routing in which the resource is
used.
Step Action
15. The Resource Details tabbed region displays the resource, the basis type, the
usage rate (or amount) and its inverse, and the number of resource units assigned.
Step Action
16. You can view the descriptions of the items in the Descriptions tabbed region.
Step Action
17. The More tabbed region displays the resource sequence, the activity for the
resource, the scheduling type (Yes, No, Prior, Next), and whether this is an
engineering routing.
Step Action
18. You have completed the Viewing Resource Usage procedure.
End of Procedure.