Professional Documents
Culture Documents
Estimating Guide For Woven Mesh Gabions
Estimating Guide For Woven Mesh Gabions
1.
2.
3.
Materials
a.
Gabions: An up-to-date quotation should be obtained. The major differences in price will be between
galvanised units and galvanised units with additional HDPE coating.
b.
Stone: From practical experience, figures of 1.6 to 1.7 Tonnes per m3 for gabion works and 2.0
3
Tonnes per m for mattress work will allow for slight over filling and normal wastage on site. Stone
should be placed as close to the works as practical, double handling may have to be considered.
(The grading for use in box gabions should be between 100 and 150mm, and between 75 and
150mm for Reno Mattress units).
Site Preparation
Excavation and grading of the ground cannot be determined here and should be assessed on site and
according to site conditions.
4.
Mechanical Plant
Use a loading shovel on structures not exceeding 2m in height with free access along the whole length.
Use 360o excavator similar to a 15-18 Ton Kamatsu/Hitachi on high structures where access is restricted.
N.B. There are conditions where other types of machinery are required, e.g. long reach booms,
cranes etc, but this is not very common.
5.
Labour
3-4 men plus a machine operator are suggested as the ideal Gabion gang. For large contracts or if high
production is required, the figures should be 8 men plus 2 machine operators. For economical working the
number of men should match the output of the machine.
6.
Production
6.1.
1. Based on a 3m high gabion retaining wall with three 1m deep courses, 2m, 1.5m and 1m wide
3
respectively. Average production: 20-25 m per day per gang.
2.
6.2.
Based on a 1.5m high retaining wall with two courses, each 1m wide with the second course
stepped back 0.5m. Average Production: 15-20m3 per day per gang.
Reno Mattresses
2
6.3.
Working in Water
(i)
7.
Aesthetic Appearance
The above figures for gabion walls assumes that all the outer vertical faces have been hand-placed or
pitched to present a neat coursed finish.
8.
Pneumatic Fixing Tool. For contracts >200m of gabions a pneumatic tool produces a saving.
9.
Packaging
For ease of handling and transportation the gabions are supplied folded flat and tied in compressed
bundles.
The maximum weight of a bundle is about 700kgs.
Gabions
* HDPE only
Standard
sizes
2x1x1m
2x1x0.5m
3x1x1m
3x1x0.5m
1.5x1x1m
2x0.5x0.5*
Volume
3
2m
3
1m
3m3
3
1.5m
3
1.5m
0.5m3
Mattresses
Standard
sizes
6x2x0.170m
6x2x0.230m
6x2x0.300m
3x2c0.170m
3x2x0.230m
3x2x0.300m
Volume
3
2.04m
3
2.76m
3.60m3
3
1.02m
3
1.38m
1.80m3
STONE
1b 1.6 Tonnes per m3 @ 12.50 per Tonne
MECHANICAL PLANT
Cost Per m
20.75 20.75
20.00
1c. Typical 15-18 Tonne Kamatsu/Hitachi plus driver @ 200.00 per day with output of 20m3 per day
10.00
LABOUR
1d. 3 men @ 65.00 per day total 195.00 with output of 20m3 per day
9.75
60.50
Basic cost per m3
Add say 15% for Contractors OH & P
3
TOTAL per m 69.58
EXAMPLE 2
2
MATTRESSES
Cost Per m
2
2a 3mx2x0.3m deep HDPE coated mattresses complete with tying wire @ 55 each (12m )
9.16m2
STONE
2b 2.0 Tonnes per m2 @ 12.50 per Tonne (6x2x0.170 = 2.04m2) (2.04x2.0x12.50) 12
MECHANICAL PLANT
2c. Typical 15-18 Tonne Kamatsu/Hitachi plus driver @ 200.00 per day with output of 100m2 per day
LABOUR
3
2d. 3 men @ 65.00 per day total 195.00 with output of 100m per day
2
Basic cost per m
Add say 15% for Contractors OH & P
All information is given in good faith but without warranty!
4.25
2.00
1.95
18.03