The document discusses power generation requirements for meeting future demand in Abu Dhabi. It notes that generation capacity is projected to range from 2600 MW to 2850 MW through at least 2020. The interconnection between Abu Dhabi and other regions can currently transfer 400 MW but will be upgraded to have more reliable capacity. Existing surplus generation agreements expire at the end of 2015. The document also outlines statutory requirements determining that generation capacity must ensure no more than 24 hours per year of power outages and discusses ensuring adequate capacity through 2014 and projected future capacity needs.
The document discusses power generation requirements for meeting future demand in Abu Dhabi. It notes that generation capacity is projected to range from 2600 MW to 2850 MW through at least 2020. The interconnection between Abu Dhabi and other regions can currently transfer 400 MW but will be upgraded to have more reliable capacity. Existing surplus generation agreements expire at the end of 2015. The document also outlines statutory requirements determining that generation capacity must ensure no more than 24 hours per year of power outages and discusses ensuring adequate capacity through 2014 and projected future capacity needs.
The document discusses power generation requirements for meeting future demand in Abu Dhabi. It notes that generation capacity is projected to range from 2600 MW to 2850 MW through at least 2020. The interconnection between Abu Dhabi and other regions can currently transfer 400 MW but will be upgraded to have more reliable capacity. Existing surplus generation agreements expire at the end of 2015. The document also outlines statutory requirements determining that generation capacity must ensure no more than 24 hours per year of power outages and discusses ensuring adequate capacity through 2014 and projected future capacity needs.
at minimum of prospective range from 2600 MW to 2850 MW.
The capacity upgrade of the Abu Dhabi Interconnection to 400 MW is currently not committed, but is expected to occur around the indicated period. At current capacity, the interconnection will transfer 400 MW but not on a guaranteed basis until the upgrade is complete. c The existing agreements for surplus generation have been recently renewed and will expire again at the end of 2015. The respective firms have indicated the possibility of further contract extension, although the indicated capacities are illustrative as contract terms may be modified. b
1.3
ADDITIONAL POWER GENERATION REQUIREMENTS
Statutory and Regulatory Requirements
OPWP is required by the Sector Law and its license to ensure the adequacy of generation resources to meet future power demands. The Sector Law establishes OPWPs general responsibility to secure sufficient generation resources to meet the aggregated demands of licensed electricity suppliers. Further to this, the license issued to OPWP by the Authority for Electricity Regulation, Oman (AER) stipulates a specific generation security standard for the MIS that OPWP must comply with. The generation security standard stipulated by the AER sets a maximum duration of power outage for the system, termed Loss-of-Load Hours (LOLH). OPWP must enter into agreements for enough contracted capacity to ensure that expected demand does not exceed available contracted capacity for more than 24 hours in any year. This LOLH measure considers relevant uncertainties such as the reliability of generation units. On a short-term basis, OPWP must demonstrate to the AER that such agreements are in place. On a long-term basis, OPWP must demonstrate that it has credible plans to put such agreements in place (via the procurement of new capacity or otherwise). It is important to note that for purposes of the 24-hour LOLH standard, only contracted capacity is considered. Other resources, such as the surplus generation of industries and reserve sharing arrangements with interconnected systems, provide a degree of reserve margin and will generally contribute to reliability of supply. However, they are not considered for purposes of meeting the 24-hour LOLH standard and are viewed instead as providing security against contingencies. 2014 Capacity Requirement OPWP and the AER determined that contracted capacity in 2014 is sufficient to secure the MIS to the 24-hour LOLH standard. However, the prospect of a delay in commissioning of the Sur IPP until mid-summer led OPWP to consider mitigation measures to assure adequate generation capacity, in consultation with the AER. OPWP is looking into several mitigation options, and expects to have contracts in place by April 2014 to assure adequate generation capacity for the summer. Future Capacity Requirements OPWP has estimated the requirement for contracted capacity in order to comply with the 24-hour LOLH standard in each year during the 2014-2020 period. Figure 4 below shows the capacity requirement for each of the three demand projections in comparison to available capacity. Under the Expected Demand scenario, contracted capacity should exceed the sum of peak demand and the margin required to meet the 24 LOLH standard (i.e., the capacity requirement). A deficit implies a need to acquire additional resources. Non-firm contracted resources are not considered in assessing available capacity to meet Expected Demand. 7-Year Statement (2014-2020)