Issues To Be Discuss in Site Meeting
Issues To Be Discuss in Site Meeting
Meeting No. 06
1. Switch yard (Between M4 and M5)
-diameter 400
-make sure the clearance is enough
-request method of statement (MOS)
2. Status of launching shaft (leaking of water at the base)
-Impact of the incident, one and a half month delay. What is the available
float?
Lining segment
What is the progress at factory? How many percent of completion? When
it will be delivered to site?
The backfilling work for the launching shaft had done, now just left the
repairing works at the leaking part.
Lining segment
They will deliver to site before the TBM works start.
3. Other Matters
Point 1: Work under Transmission line
-Owner will forward a person who qualifies the job. (correct the notes
of meeting )
There are 4 options for the method of statement and they are currently
Point 2: Backfilling Work (80m x 80m) South area
-Provide geotextile between clay and sand layer. Geotextile is 1 meter
below the sand layer.
Contractor proposed 5th of February for the presentation. Contractor will
discuss on the geotextile issue.
Point 4: Access Road to M5 site
-Postpone the installation of street light pole & fence by M4
Contractor estimate the Boiler Girders will be delivered at the period from
15th February until 28th February. Therefore, the installation of street light
pole & fence
TNBJ Temporary Jetty
-Contractor has to arrange joint inspection together with consultant
and TNBJ. Follow up with submission of photos and report officially.
Transmission Tower Foundation work in M4 area
-Any outage MOS
-Have to install transducer?
Disposal of excavated material
-Arrange a joint site visit to the designated area. Have to make sure
there is no complaint from the nearby resident.
Attachment 1.
4. Risk assessment