Professional Documents
Culture Documents
14v144g Ok Subterraneo
14v144g Ok Subterraneo
14v144g Ok Subterraneo
1 of 10
The equipment that is commonly used can be segmented into four groups that have not had much
change in the equipment features as used. These include the oldest technique which incorporates use of
handheld drills such as Jacklegs or Stopers on ladders or on cribbing. As this method was a highly
skilled technique which had extremely high reportable incidents rate and serious accident associated
with it in addition to being a very time consuming method it has been discontinued at most operations
with the exception of narrow vein mining of very high value ores.
The second group also utilizes handheld drilling equipment but with the mechanized rack and pinion
raise climber equipment.
The third group includes traditional Raise Bore machines, gang hammers, or cluster ITH drill.
The fourth group of tools uses percussion long-hole drills with either top hammer or ITH drill systems.
Sometimes as a community we forget successful techniques used in the past and need to rediscover
them.
The performance criteria today has become more focused on three key components; safety; productivity
rate and the total cost per unit of production. To make a cleaner comparison a real life example was used
as the model for equivalent comparison. This example was a 2.44 by 2.44 meter (8 by 8 ft.) raise that
was 42 meters (140 ft.) long and was developed at an angle of 77 degrees off horizontal. The daily work
hours used at this site was equal to 15 effective hours per day. Using this as the comparison model we
have compared the last three raising methods and focused on Rapid Raising that has shown to be
arguably faster and cheaper than the other raising methods for this size raise. Because of this look back
in time the cost comparisons are based on dollar values from 2000.
Figure 1
2 of 10
Figure 2
The raise climber method produces a raise with fairly uniform walls well suited to ventilation air flow or
as utility passages. It is very simple, requiring a relatively low amount of capital investment. However,
it is dangerous with the miner exposed to the possibility of a rock fall at any time.
Comparative rate
Setup time
Raise advance time
Strip out and move time
1.5
10.6
1.5
days
days (4 meters (13.1 ft.) per day)
days
Total time
Total cost $ 820 meter ($256 foot)
Capital Cost
13.6 days
$34,768 USD
$160,000 USD
3 of 10
The blasting sequence is 2, 3, 4 and 5 (figure 3). The complete raise length is usually blasted as a single
event even if decks are used.
Figure 3
This raising method can be more capital intensive, as it also requires a production drill to drill the blast
holes more equipment is necessary.
Figure 4
Figure 5
The design of the blind boring and raise pulling are similar except one machine can be lighter weight
than the other because it applies force by pushing instead of pulling. To maintain hole straightness, nonrotating stabilisers are used which reduce the bending in the drill string. With the raise pulling method
4 of 10
the highest risk work, comes while attaching the reaming head under the drill string after the break
through is made in the target location.
1.5
.75
3.5
2.0
0.5
days
days
days (0.8 meters (2.6 ft.) per hour)
days
days
Total time
Total cost $ 560 meter ($168 foot)
Capital Cost Raise machine
8.25 days
$23,744 USD
$375,000 USD
Blind boring set-up is executed by moving the machine underneath the collaring point where the back
has been excavated to 5.2 meters (17 ft.) The starting tube can then be lifted into position and drilling
starts by inflating a packer and engaging the Rotation and Thrust. When the stroke is finished, regripping is accomplished by shifting the hydraulically operated steering shoes to hold mode. The packer
is the deflated and repositioned to start another stroke. There is no direct exposure under the hole as it is
covered with the starting tube and the chip deflector so there is significantly less risk to the workers.
Comparative rate, Reaming
Setup time
Raise advance time
Drill and blast 114 mm (4.5in) holes
Strip out and move time
1.5
3.5
1.5
0.5
days
days (12.3 meters (40.5 ft.) per day)
days
days
Total time
Total cost $ 560 meter ($168 foot)
Capital Cost Blind Boring pkg.
7.0
days
$23,744 USD
$750,000 USD
5 of 10
Figure 6
Comparative rate
Set-up Time
Drill Pilot Hole
Ream to 762 mm (30 in.)
Drill and blast 114 mm (4.5 inch) holes
Move out Time
1.0 day
0.75 days
3.5 days
2.0 days
0.5 days
7.75 days
$18,020.00 USD
$375,000.00 USD
Drop Raising
Drop Raising consists of drilling a pattern of blast holes with a long hole drill (Figure 8). For the size
raise being compared top hammer drilling is not a viable option due to drill accuracy over this depth.
Traditionally 20 meter (65 feet) is the longest hole top hammer can dependably be drilled for this type
application. For ITH drilling generally, the larger the hole diameter drilled with a DTH hammer the
longer the hole can be drilled with accuracy. 165 mm (6-1/2" holes) are better for raises greater than 50
meters (164 feet) than 114 mm (4.5 inch) holes.
The blasting sequence of any blasting round is arranged with respect to any drilling deviation so that the
drill holes with the least burden are initiated first. Limited use of sand, pea gravel or water as stemming
because these holes are continually reused until the raise breaks through to the upper level.
6 of 10
Comparative rate
Set-up Time (including
Drill holes
Blast
0.5 days
4.0 days
8.7 days
13.3 days
$25,016.00 USD
No extra expense, use of production drill
Figure 8
Figure 7
7 of 10
Comparative rate
Set-up Time
Drill Slot
Drill and blast 114 mm (4-1/2") holes
Move out Time
0.5 day
3.0 days
2.0 days
0.5 days
6.0 days
$13,907.00
$30,000.00 Slot saddle and tool
Figure 9
Figure 10
Rapid Raising
Rapid Raising is a variation of Drop Raising. It uses ITH equipment and large diameter ITH drill tools
304 mm (12 inch) hammer (Figure 11) to provide sufficient relief within the raise to permit the blasting
of the raise in a single shot without freezing the blast. This has significantly reduced the repetitious
cycle of deck blasting in short lifts without requiring the use of additional capital equipment.
Method Comparative facts
Set-up Time (including
Drill and Ream holes
Change Drill for small holes
Blast
0.5 days
3.9 days
0.5 days
0.5 days
5.4 days
$13,203.00 USD
$38,900.00, DTH hammer and bits
8 of 10
Figure 11
Figure 13
Figure 12
Figure 14
9 of 10
Figure 15
Figure 16
The Rapid Raising chart (Figure 17) at San Francisco del Oro shows raises from 15 meters (50 feet) to
24 meters (79 feet) at a rate of 3 meters (9.6 feet) to 4.8 meters (15.3 feet) per hour of work including
drill and blast.
Figure 17
Conclusion
Rapid Raising as shown in the charts (Figure 13) above is the fastest to complete the example raise. In
the cost charts (Figure 14, Figure 16) it is the least expensive method to complete this raise. The chart
(Figure 17) of Rapid Raises reported on in Chihuahua, Mexico also shows the benefit in raises shorter
than the comparative model.
References
1. Dobran, Mauro 2000, Comparison of Techniques to Develop a Slot Raise, WME Drilling 2000
2. Cortez, Jesus Ignacio Martinez, 1998, Development of Rapid Raises in La Mesa Mine,
Chihuahua Mine Engineers Conference
10 of 10