Professional Documents
Culture Documents
CER15018 (A) GNI Proposals On Connections Policy
CER15018 (A) GNI Proposals On Connections Policy
Contents
Background............................................................................................................................ 2
Rationale for Change............................................................................................................ 2
Proposal 1: Amendments to Financial Security Criteria ............................................ 3
Proposal 2: Inclusion of Transmission Revenue in all appraisals ............................. 8
Proposal 3: Amendment of Institutional I & C Customers .................................... 12
Proposal 4: Proposals on Existing Gas Areas ........................................................... 14
Proposal 5: Group Sites (different entities, same corridor) ..................................... 16
Proposal 6: Group Sites (same entity, different sites)............................................... 17
Proposal 7: Treatment of CNG Connections............................................................ 18
Summary & Conclusions .............................................................................................. 20
Background
The Connections Policy was approved by the CER on 6th April, 2006 and is a
single connections policy dealing with connections to both the Transmission
and Distribution networks. The policy sets out the detailed criteria for the
evaluation of extensions to the gas network, including extensions to towns not
currently served by natural gas.
While there were some changes to the policy in the interim, the current policy
has been in effect since April 2006. This paper seeks to outline some proposed
amendments to the connections policy to enhance the level of economic
connections to the gas network.
The context of this review is that areas of the current policy may be hampering
the full realisation of the potential economically efficient demand and load
growth available for the gas network in Ireland. While the overall risk will be
increased, Gas Networks Ireland (GNI) believe that this is mitigated as these
proposed changes will facilitate additional connections, who would not
otherwise connect to the Natural Gas network under the existing Connections
Policy. The addition of the extra load to the system will have the effect of
reducing tariffs for existing customers in the long term.
Separate to this review of the Connections Policy, GNI is working on the roll-out
of a range of initiatives aimed at furthering public awareness of the availability
and benefits of natural gas versus other fuels. Initiatives to promote the use of
natural gas as a clean, efficient and cost competitive fuel for transport, along
with integration of biogas in the network are also currently being implemented.
ii.
iii.
Adjust the credit rating applied to Letters of Credit for Financial Security
associated with new connections
NPV Positive
in
>= 7 years
4-6 years
<= 3 years
Threshold
500K
750K
1m
LNCA Required
Above Threshold only
Above Threshold only
Above Threshold only
FS Required
Above Threshold only
Above Threshold only
Above Threshold only
Note: For all of the above cases, the current threshold is 250k and a Large
Network Connection Agreement is required.
Initiative
Number
Outline of Initiative
Rationale
02-Oct-2009
27-Nov-2009
22-Jan-2010
19-Mar-2010
14-May-2010
09-Jul-2010
03-Sep-2010
29-Oct-2010
24-Dec-2010
18-Feb-2011
15-Apr-2011
10-Jun-2011
05-Aug-2011
30-Sep-2011
25-Nov-2011
20-Jan-2012
16-Mar-2012
11-May-2012
06-Jul-2012
31-Aug-2012
26-Oct-2012
21-Dec-2012
15-Feb-2013
12-Apr-2013
07-Jun-2013
02-Aug-2013
27-Sep-2013
22-Nov-2013
17-Jan-2014
14-Mar-2014
09-May-2014
04-Jul-2014
29-Aug-2014
0.4
For connections which pay the 30% contribution charge and also pay a
supplemental charge, there should be a decrease (if not removal) of the
supplemental charge as the commercial appraisal will be improved by
the inclusion of the transmission revenues. There should also be a
decrease in the time for which Financial Security is required.
For connections which pay the 30% contribution and are not required to
pay a supplemental charge, the benefit will be that the length of time
that Financial Security is required should decrease.
All appraisals that currently dont recognise transmission revenue will benefit to
a greater or lesser extent from this change, but the inclusion of the
transmission revenue is reflective of the incremental value the new site offers
in contributing to the remuneration of the network. The inclusion of such
revenues should lead to a reduced upfront contribution by the customer and/or
reduced financial security obligations which will make the connection to gas
more commercially attractive to the prospective customer.
Initiative
Number
Outline of Initiative
Rationale
Ports
Bus Stations
The first two additions are institutional types which are built for long term use
(ports/bus stations). The remaining three additions are typically significant long
term investments to provide services on a long term basis to customers:
Waste collection depots are built to provide municipal services to customers
for a 20-30 year lifetime at a specific location
Biogas plants will inject gas into the grid at the specified location for a
prolonged period of time with potential expansion. Including biogas injection
facilities to the institutional I & C list would encourage more installations. This
in turn would support the requirement for EU Member States to undertake
measures to assist the wider use of gas from renewable sources. Note biogas
plants will typically be injecting/entering gas in the system whereas
conventional connections in the connections policy are exit points that offtake
gas from the grid. However, the exercise at the start of connecting the facility to
the gas grid by way of extending the gas network can follow the same
principles.
Retail CNG forecourts would be developed at strategic locations to provide
long-term refuelling services to CNG vehicles.
To summarise, GNI would propose that the list would include new additions as
follows:
Current List
Schools
Ports
Bus Stations
Hospitals
Prisons
Garda Stations
Stadiums
Airports
(airport
infrastructure only)
specific
Railway stations
Museums/Heritage Sites
Fire/Ambulance Station
Army Barracks
Government Buildings
Initiative
Number
Outline of Initiative
Rationale
(ii)
(iii)
(iv)
New Towns Model: As per section 8 of the Connections Policy, New Towns are
evaluated over 25 years for both Industrial Commercial Customers and New
Housing to reflect the lower risk and broader growth opportunities of a
diversified area load base. The economic test includes both Transmission and
Distribution revenue and considers the long term potential of the entire area. It
is proposed that funding for such infill suburb projects would be applied to the
most economic projects with each project scored and appraised by GNI against
an annual funding allowance from the CER.
Initiative
Number
Outline of Initiative
Rationale
Domestic
Housing
contribution for targeted
suburb/urban areas and
new towns allow the
domestic
housing
connection fee to be
waived
under
certain
circumstances
Initiative
Number
Outline of Initiative
Rationale
Initiative
Number
Outline of Initiative
Rationale
This initiative would assist in the rollout of CNG infrastructure particularly in the
event that an existing forecourt operator was interested in building a network
of filling stations to adopt the fuel.
In line with the current Connections Policy, customers will make a contribution
of 30% towards the cost of the connection. An economic test will be
undertaken (in line with existing policy), which will dictate that if the customers
capacity charges over a seven year period do not meet the cost of the
remaining 70% of the cost of connection, the customer must pay the difference
Initiative
Number
Outline
Initiative
of Rationale
Include
compression
and multi-stage
storage in the
connection.
(ii)
(iii)
(iv)
(v)
(vi)
(vii)