SCOPE:
Establish the quality of materials, mixing, placing etc. of all type of lean concrete work to be carried
out at site. The procedure is subject to revision depending upon the actual practical requirement at
site at the time of job. This procedure also includes the methodology of record keeping.
REFERENCE DOCUMENTS:
Page 1 of 5
5. Mixing of concrete will be done in Batching plant. The mixing time will be such that all
the ingredients mix properly.
6. Immediately after mixing, the concrete will be transported by transit mixers
& shall be placed at the required locations.
TOOLS USED:
1. Transit Mixer.
2. Solider Channel For Side Shuttering of PCC.
CONCLUSION:
1. Check List Kept Ready for Footing Rebar Work with all approval.
ENCLOSURE:
1. Survey setting Lay-out (CL-01).
2. Pour card Check List (CL-03).
Page 2 of 5
Page 3 of 5
Page 4 of 5
Page 5 of 5