Date:
Subcontractor(s) NONE
7:40 a.m. arrived on-site. Spoke with crew about installing fire hydrants on Donner. The
Crew was on Donner last week and only installed 2 hydrants. 2 more hydrants need to be
installed still.
Approx. 9:30 a.m. While digging with a shovel; to build the receiving pit, contractors staff hit
the water service line to the home located at 3054 24 th Street. Contractor did not phone any
city staff to notify of the water hit.
10:00 a.m. Return to site. Reviewed traffic controls on 24 th. They need some correction; as
there is no Construction Ahead or Detour Ahead signs up. I asked Billy to address this.
When I approached the work area I noticed water flowing heavy in the gutter line. I observed
3 holes dug, all were full of water. Billy was in hole dug above the existing main trying to turn
the corp off at the main. He was unable to get water shut down.
10:20 a.m. water was being pumped out of the excavation with no filter bags. Boring rig
began to bore at home adjacent to the leak; 3056 24 th Street.
11:00 a.m. water was shut off and the crew was able to turn the line off at the main. Boring
machine then relocated to 3054 24th Street and began to bore again. I watched to verify the
bore crossed over the existing water main.
11:15 a.m. As the machine pushed through the soil a load gush of gas blasted up. The bore
machine had hit the gas main. I phoned mike Colasanti, Chris Powell and Brett Grant to
report the incident.
11:40 a.m. PG&E supervisor; Erik Kurtz (916-386-5373) arrived on-site with a full crew to
assess the damage. We started evacuations of the following homes: 3056, 3054 and 3048
260831271
Page 1 of 8
Page 2 of 8
sewer service. I asked the Journeyman for PG&E what the status was. He (Casey) stated it
may be around 10pm.
6:10 p.m. Billy with T&S was not comfortable with leaving the resident without City services
any longer and chose to make the repairs themselves. T&S then repaired the sewer and
water. We then flushed the line and informed the homeowner they could use their utilities
again.
6:40 p.m. PG&E still not performing any corrective work. No supervisors on site still. We
informed the 3 man crew we had completed the repairs and backfilled our services. T&S
provided 2 trench plates for PG&E to use as cover; asking them to not backfill the repaired
services so we can ensure they are backfilled with approved material.
7:00 p.m. T&S and I left the site. PG&E still on-site. I asked Billy to come in early and clan the
streets and gutter.
*NO PRODUCTION TODAY- NO PAY ITEMS COMPLETED
Ite
m
No
.
1
2
3
4
Company
Timein
Timeout
MATERIAL QUANTITIES
Description
Preconstruction Photographs
4- Inch diameter water main, to furnish and install
6- Inch diameter water main, to furnish and install
8- Inch diameter water main, to furnish and install
260831271
Page 3 of 8
Location
Purpose
Quanti
ty
Unit
Installed
or
Delivere
d
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
WORKER
William Hinds
James Rutherford
Brodey Thorn
Kevin Pomeroy
Choy Saechao
Rick Tokos
EQUIPMENT
super
Case 210
580 Boring
machine and case
621D loader
Alfredo PAZ-Garcia
C
R
A
F
T
op
op
lab
op
lab
op
lab
HOURS
R
E
G
8
8
6
4
4
8
4
OT
4
2
ITEM No/QUANTITIES
PHOTOGRAPHS (Click on Icons below to insert photos, and then expand to desired size)
260831271
Page 4 of 8
DOW
N OR
IDLE
DI protected
by filter bag.
Bag had to
be pulled to
prevent
flooding
260831271
Page 5 of 8
260831271
Page 6 of 8
260831271
Page 7 of 8
260831271
Page 8 of 8