Professional Documents
Culture Documents
Collateral Warranties
Collateral Warranties
Collateral Warranties
tenants and purchasers to seek other commercial concessions. Similarly providers of funding for projects or for
the purchase of a building will generally expect a full package of collateral warranties, the absence of which will
hamper the developer's or purchaser's ability to get funding;
A clear copyright licence to use and reproduce drawings, specifications and other documents produced
o
o
Collateral warranties are usually only relevant for the first 10 to 12 years after construction has been carried out
because (i) claims under collateral warranties are usually subject to time limits of up to 12 years after practical
completion (handover) of the construction works; and (ii) it becomes increasingly difficult to prove a claim as time
passes by due to a lack of records (such as design documentation, project correspondence and meeting
minutes) or access to relevant personnel who were involved in the construction works. In addition normal wear
and tear or misuse of the building can obscure the assessment of the responsibility of the original construction
team. Nevertheless, we have been involved in raising actions under collateral warranties several years after
construction was completed.
Who gets collateral warranties?
Typically collateral warranties are required by:
Employers/clients - from sub-contractors, sub-consultants and on novation of design consultants if the
o
o
o
design team is transferred to the contractor where the employer wants to place "single point responsibility" for
design and construction on the contractor (this is called "novation");
Providers of finance for a project;
Purchasers of completed projects;
Providers of finance to purchasers; and
Tenants of commercial property where the tenant is responsible for the repair and insurance of the
leased premises and will therefore want to be able to look to the construction team if a problem arises with the
design or construction of the premises during the lifetime of the collateral warranty.
In some cases other parties might require collateral warranties to be granted in their favour. This might be the
owner of the site if it is not the party carrying out the project (e.g. the landlord in relation to a complex fit-out) or
adjoining proprietors whose property could be affected by construction work and whose consent might be
required to allow the project to proceed.
Employers/clients in commercial property projects will want to ensure that they have suitable obligations on the
construction team to grant collateral warranties to purchasers, tenants and funders. If not this will detract from
the "marketability" of their development, as tenants, purchasers and funders will generally look for a full package
of collateral warranties to be available. Indeed , in White Property Company Limited v Birse Construction
Limited, a developer raised a claim against the contractor because the contractor had failed to grant collateral
warranties and procure sub-contractor collateral warranties for a shopping centre on the basis of a dispute that
had arisen between the parties. The property was valued at 45 million, which represented a 2.5 million
diminution in value. The court found that the developer's loss had been mitigated to such an extent that that the
loss was extinguished, in light of the capital appreciation of the building and the rental income that the developer
had received during its longer than anticipated ownership of the centre. This case was decided about 10 years
ago given the impact of the recent recession, a developer in a similar situation today may not have the benefit
of capital appreciation and rental income, and so there may well be a different result if a similar case came to
court.
What is normally covered in collateral warranties?
Collateral warranties may originate as lawyers' or surveyors' individual style documentation or as standard forms
published by industry bodies (e.g. Joint Contracts Tribunal/Scottish Building Contracts Committee or the
Construction Industry Council). Regardless of the origin of the collateral warranty, beneficiaries of collateral
warranties will want to make sure that collateral warranties include:
A duty of care undertaking whereby the granter confirms that it has complied with its obligations in the
building contract, sub-contract or professional appointment and that the granter has exercised the level of
reasonable skill and care to be expected of its peers in relation to any professional services (be that design, cost
advice, project management, contract administration or health and safety advice). It is crucial to note that the
value of any collateral warranty, no matter how robust, is dependent on the terms of the underlying contract to
which it relates, because (i) the granter will only give warranties in relation to the obligations that appear in the
building contract, sub-contract or professional appointment; and (ii) any caps on liability or exclusions of liability in
the building contract, sub-contract or professional appointment will in most cases also apply to the recourse
available to the beneficiary under the associated collateral warranty. It is not, therefore, possible to properly
assess the value of a collateral warranty without reviewing that underlying contract.
A copyright licence allowing the beneficiary to copy and use drawings, specifications, bills of quantities
and other project documents in relation to the project and the completed project. A copyright licence might be
required for a wide variety of reasons such as to allow a tenant to integrate its fits out into shell and core works,
to allow the employer/client to market the property for sale or lease or to allow a purchaser to maintain the health
and safety file for the property.
An undertaking to maintain professional indemnity insurance for a specified amount and time, where the
granter has some element of professional responsibility in relation to design or other professional services.
Although professional indemnity insurance is designed primarily to protect the insured party, purchasers, tenants
and funders will want to have certainty that insurance is in place, particularly in the context of professional
consultants whose only assets might be a lease and their office equipment.
The right to assign the benefit of the collateral warranty. It is almost always the case that warranties are
only granted to first funders, first purchasers and first tenants so provision is made for the collateral warranty to
be assigned to second purchasers, their funders and to tenants. It is fairly standard for collateral warranties to be
assignable on two occasions without consent. Prior to the credit crunch, given the speed at which property
changed hands, it was often the case that all the assignations had been used up before the expiry of the
collateral warranty.
Step in rights for employers and funders to allow them to "take over" the contract to which the collateral
warranty relates. In the case of an employer, if the main contractor it has engaged becomes insolvent or simply
fails to perform, the employer might want to "step into" the contracts with the key sub-contractors in order to finish
the works. In the case of a project funder, if the developer disappears, the funder might want to have the ability
to step in and complete the project to protect the value of its security. Step in rights are optional and it may be
that the beneficiary chooses not to complete the project because the cost of paying all outstanding liabilities
outweighs the return that can be made. However, in one case earlier this year (The Royal Bank of Scotland Plc v
Chandra [2010] EWHC 105 (Ch)), the Bank, in fact, obliged itself to step in to the building contract. This is
extremely unusual but arose from the fact that the contractor was concerned about the ability of the developer to
meet its obligations. The contractor, the developer and the bank therefore agreed that the contractor would have
the benefit of mandatory step in rights to give the contractor security in the event of developer default or
insolvency.
Consultants, contractors and sub-contractors granting collateral warranties will wish to make sure that the
collateral warranties they grant:
are clear that they have the protection of any caps on, or exclusions of, liability in the building contract or
contribution" / "fair share" clause that apportions liability for a fault on the assumption that all other parties at fault
have paid their share of the beneficiary's loss. Funders will generally not accept such clauses but they are
sometimes a feature of tenant collateral warranties;
have a time limit on liability;
include the right to rely on the same defences to claims under the collateral warranty that they would have
against their client/employer; and
incorporate an ability to maintain a lower level of professional indemnity insurance should the cost of
however this can only provide a benefit to one party and might not be appropriate where the employer/client has
ongoing obligations to purchaser or tenants to procure that defects are made good during the defects liability
period or to the contractor to release the retention following completion of making good defects. Assignments or
assignations are also not generally favoured because the assignee can acquire no better rights than the assignor
has, and so any settlements reached with the construction team could defeat the assignee's claim. In many
cases the assignee will be completely unaware of the terms of any settlement between the assignor and the
construction team and therefore the impact on the rights that are being assigned.
Third party rights: Whilst there is legislation in England which allows parties to a contract to agree to
benefit third parties who are not party to the contract (e.g. funders, purchasers and tenants) and a third party
rights principle in Scotland called the jus quaesitium tertio, for a variety of reasons third party rights have tended
not to be used nearly as much as collateral warranties. Nevertheless, the suite of standard form construction
contracts published by the Joint Contracts Tribunal for use in England and Wales and their Scottish equivalents
produced by the Scottish Building Contracts Committee does include a third party rights option.
Latent defects policy: A latent defects policy is an insurance product that will respond to certain latent
defects in buildings. Although these policies do provide insurance based protection, they are not generally seen
as a replacement for collateral warranties because any claims made are subject to a deductible or excess;
liability is capped at the sum insured, is subject to the exclusions in the cover provided (often excluding
consequential losses and mechanical and electrical elements of the building) and is dependent on the general
issues surrounding insurance contracts including disclosures made at the time the policy was obtained. In the
case of a party who is purchasing a property who wishes to rely on the transfer of an existing insurance policy
(e.g. by endorsement or assignment/assignation of rights), it will not have made those disclosures and may not
have access to the facts or documentation to allow it to assess whether there is any issue with the disclosures
made for the purposes of obtaining the policy. Latent defects insurance policies will also not provide the other
benefits of collateral warranties noted above, e.g. step in rights and a copyright licence.
Conclusion
The possible alternative comfort options outlined above have not succeeded in replacing the need for collateral
warranties, which will remain a key feature of construction and engineering projects for the foreseeable future.
Although there are common provisions in collateral warranties, each style is different and should be carefully
reviewed, together with the underlying construction contract, to make sure that it provides sufficient comfort for
the beneficiary, or that it does not go too far from the granter's perspective.