Professional Documents
Culture Documents
UDOT Quaterly Report
UDOT Quaterly Report
UDOT Quaterly Report
On-Street Survey
First Quarter 2012
Compiled by
Brigham Young University
April 2012
Erik Westesen
Account Director
Thomas White
Account Executive
Natalie Sivertsen
Francesco Loli
Rebecca Lane
Account Coordinators
Rachel Cool
Table of Contents
Executive Summary........................................................................................2
Survey Instrument..........................................................................................4
Q1 2012 Survey Results - Demographic Responses.........................5
Q1 2012 Survey Results - Total..................................................................9
Question 1...............................................................................................10
Question 4...............................................................................................21
Area Specific Results...................................................................................23
Demographic Responses by Area.................................................24
Question 1 by area...............................................................................29
Question 4 by area..............................................................................45
Key Findings....................................................................................................53
Overall Results......................................................................................54
Detailed Results....................................................................................55
Executive Summary
This booklet contains the results of the man-on-the-street survey research carried out by
the Bradley Public Relations Agency at BYU in addition to phone survey research
conducted by Service Sampling International, for the first quarter of 2012.
Student volunteers and employees of the agency administered the surveys at retail and
grocery stores in each of the four areas established by UDOT: American Fork/Pleasant Grove,
Orem, Provo, and Spanish Fork/Springville (areas identified on the map on page 3). A total of
448 surveys were completed between March 24 - 31, 2012. Following collection, the data was
analyzed and compared to the three preceding quarters, as seen throughout this report.
Here, the results are broken down by question and by area. First, we have included the
demographic information of respondents included on the survey instrument (see page 4).
Next, we included graphs showing the overall results for questions 1 and 4 as compared
to Q2 2011 as well as Q3 and Q4 of 2011. Following this section we have provided the area
specific results for questions 1 and 4. Finally, we have summarized our key findings, with a
detailed look at overall trends.
For example, we observed an increase in the aggregate average score to 2.85 on a
five-point scale with 1.00 meaning the most negative and 5.00 meaning the most
positive. This was due in large part to a large increase in Spanish Fork/Springvilles
overall average score.
These results represent a collective opinion of those sampled. Their responses, as contained in this report, serve as a quick snapshot of current public opinion regarding the I-15
Core Corridor Expansion project. It is important to note that the results of this survey are
not statistically significant unless viewed as a whole; individual area samples are not substantial enough to stand alone.
Notes
Phone survey data is displayed separately from man-on-the-street data, and is not
included in the overall average scores.
Some graphical representations omit data labels (number above a graph bar indicating
value). This is due to the space required to show a whole years worth of data for certain
data sets. Specific values are available on the CD enclosed within this booklet. Scale
frequency has been increased to better compensate for this change.
Zone 4 - Springville
and Spanish Fork exits.
Surveys completed at
the Springville WalMart,
Maceys in Spanish Fork
and nearby locations.
Survey Instrument
Please answer the following questions based on your experience in the past month with
the I-15 CORE road construction project (on I-15 from Lehi Main Street to
Spanish Fork Main Street).
1. On a scale of one to five with one meaning completely disagree and five meaning completely agree,
please rate the project on the following:
Disagree
The detour routes are clear and easy to navigate (or drive).
Agree
Indifferent
4 p.m. to 7 p.m.
After 7 p.m.
4. Several methods are being used to help people stay informed about
construction activities. Of the following methods, which ones do
you use to stay informed about the I-15 construction project?
Choose all that apply:
Project e-mail updates
Project website updates
Electronic roadway signs
Door hangers/fliers
Radio messages
Television
0
to
n
O
re
ea
m
sa
nt
G
ro
ve
Pa
ys
on
Pr
ov
o
Sa
nt
Sa
a
ra
qu
to
in
ga
Sp
rin
Sp
gs
an
ish
Fo
rk
Sp
rin
gv
ille
Ot
he
Vi
r/
n
ey
No
ar
n-
d
Re
sp
on
se
Pl
do
le
ap
Lin
Le
hi
nd
ai
ills
10.00%
Other/Non-Response
Vineyard
Springville
50
Spanish Fork
Saratoga Springs
10
Santaquin
70
Provo
Payson
27
Pleasant Grove
90
Orem
12
Mapleton
la
gh
Hi
nt
ou
rk
ne
Fo
pi
r H
da
Ce
gle
Ea
Al
n
ica
er
Am
35.00%
Lindon
40
Lehi
20
Highland
Eagle Mountain
Cedar Hills
30
American Fork
10
Alpine
30.00%
25.00%
20.00%
15.00%
Q4 2011
Q1 2012
5.00%
0.00%
100
88
80
66
60
41
33
29
19
23
14
3. What time(s) of day do you drive on I-15 the most? Select all that apply.
40.00%
35.00%
30.00%
25.00%
Q2
Q3
20.00%
Q4
Q1
15.00%
10.00%
5.00%
0.00%
Before 6 am
40.00%
6-9am
9-4pm
4-7pm
a6er 7 pm
35.00%
29.58%
30.00%
Number of Respondents
25.00%
21.68%
20.00%
15.00%
9.24%
10.00%
5.00%
0.00%
3.36%
Before 6 am
6-9 am
9-4 pm
4-7 pm
a7er 7 pm
10
1, p1: I feel safe when driving through the construction zones. (Scale of 1-5
with 1 meaning completely disagree and 5 meaning completely agree):
40%
35%
32.6%
30.8%
30%
31.8%
30.2%
32.0%
31.6%
30.8%
26.8%
25%
Q2
2011
19.9%
20%
20.9%
Q3 2011
19.6%
Q4 2011
18.0%
Q1
2012
14.4%
15%
12.9%
13.5%
10.3%
10%
7.1%
6.3%
5.9%
4.6%
5%
0%
20.00%
11
35%
33.3%
30.0%
30%
29.1%
28.4%
27.9%
26.7%
25%
20.1%
20%
15%
19.2%
Q3 2011
17.6%
Q4
2011
Q1
2012
14.7%
12.4%
11.0%
10.9%
10.0%
8.8%
10%
5%
0%
40.00%
35.00%
30.00%
25.00%
Street
Surveys
Percentages
20.00%
Phone
percentages
15.00%
10.00%
5.00%
0.00%
12
1, p3: Dust is kept under control (Scale of 1-5 with 1 meaning completely disagree and 5 meaning completely agree):
40%
35%
37.6%
32.8%
32.8%
30.9%
30%
26.7%
25.5%
24.8%
25%
23.3%
Q2 2011
21.7%
21.3%
19.9%
20%
10%
Q4
2011
Q1
2012
16.5%
15.4%
14.6%
15%
Q3 2011
13.0%
9.9%
10.2%
9.6%
7.7%
6.1%
5%
0%
45.00%
40.00%
35.00%
30.00%
25.00%
20.00%
15.00%
10.00%
5.00%
0.00%
13
1, p4: Construction noise is kept under control. (Scale of 1-5 with 1 meaning
completely disagree and 5 meaning completely agree):
40%
34.6%
35%
35.9%
32.9%
31.2%
30.0%
30%
29.5%
27.5%
25.0%
25%
22.9%
Q2 2011
22.6%
20.5%
20%
Q3
2011
Q4
2011
Q1
2012
15.8%
15%
11.2%
10%
8.3%
7.6%
6.8%
10.8%
10.8%
9.7%
6.3%
5%
0%
45.00%
40.00%
35.00%
30.00%
25.00%
20.00%
15.00%
10.00%
5.00%
0.00%
14
1, p5: Lane markings are clear. (Scale of 1-5 with 1 meaning completely disagree and 5 meaning completely agree):
Clear
Lane
Markings
-
On
the
Street
45%
39.0%
40%
35%
38.1%
33.8%
28.9%
30%
29.1%
30.4%
Q3
2011
Q4
2011
25%
Q1 2012
20%
14.2%
15%
16.3%
15.3%
15.2%
11.7%
11.4%
10%
7.8%
5.1%
5%
0%
45.00%
3.6%
40.00%
35.00%
30.00%
25.00%
20.00%
15.00%
10.00%
5.00%
0.00%
15
1, p6: Construction signs are easy to read. (Scale of 1-5 with 1 meaning completely disagree and 5 meaning completely agree):
Clear
Lane
Markings
-
On
the
Street
45%
39.0%
40%
35%
38.1%
33.8%
28.9%
30%
29.1%
30.4%
Q3
2011
Q4
2011
25%
Q1 2012
20%
14.2%
15%
16.3%
15.3%
15.2%
11.7%
11.4%
10%
7.8%
5.1%
5%
0%
35.00%
3.6%
30.00%
25.00%
20.00%
Street
Surveys
Percentages
Phone
Percentages
15.00%
10.00%
5.00%
0.00%
16
1, p7: The detour routes are clear and easy to navigate (or drive). (Scale of 1-5
with 1 meaning completely disagree and 5 meaning completely agree):
40%
35%
30.9%
28.9%
30%
27.7%
26.0%
24.5%
25%
25.7%
25.8%
24.1%
Q2
2011
21.8%
20%
20.6%
Q3 2011
20.6%
Q4 2011
18.6%
17.8%
15.2%
15%
Q1 2012
14.5%
10%
7.4%
6.2%
4.6%
4.1%
5%
0%
40.00%
35.00%
30.00%
25.00%
Street
Surveys
Percentages
20.00%
Phone
Percentages
15.00%
10.00%
5.00%
0.00%
17
1, p8: Access to I-15 on- and off-ramps has been maintained. (Scale of 1-5 with
1 meaning completely disagree and 5 meaning completely agree):
Ramps
-
On
the
Street
30%
28.5%
28.0%
26.0%
25.2%
25%
24.7%
24.0%
23.4%
23.0%
23.2%
21.6%
20%
20.3%
19.3%
19.8%
18.1%
17.1%
Q2
2011
Q3
2011
15.6%
15%
Q4
2011
Q1
2012
11.0%
10.2%
10%
9.0%
8.6%
5%
0%
40.00%
35.00%
30.00%
25.00%
Street
Surveys
Percentages
20.00%
Phone
Percentages
15.00%
10.00%
5.00%
0.00%
18
1, p9: The construction crews are courteous. (Scale of 1-5 with 1 meaning completely disagree and 5 meaning completely agree):
Ramps
-
On
the
Street
30%
28.5%
28.0%
26.0%
25.2%
25%
24.7%
24.0%
23.4%
23.0%
23.2%
21.6%
20%
20.3%
19.3%
19.8%
18.1%
17.1%
Q2
2011
Q3
2011
15.6%
15%
Q4
2011
Q1
2012
11.0%
10.2%
10%
9.0%
8.6%
5%
0%
50.00%
45.00%
40.00%
35.00%
30.00%
Street
Surveys
Percentages
25.00%
Phone
Percentages
20.00%
15.00%
10.00%
5.00%
0.00%
19
1, p10: Construction does not increase my travel time. (Scale of 1-5 with 1
meaning completely disagree and 5 meaning completely agree):
60%
50.7%
50%
40%
47.1%
46.8%
40.7%
Q2
2011
Q3
2011
30%
Q4 2011
26.3%
Q1 2012
22.8%
22.7%
20.8%
20%
16.3%
12.6%
13.1%
10%
12.5%
11.2%
8.6%
9.5%
8.8%
7.4%
8.0%
8.6%
5.6%
0%
50.00%
45.00%
40.00%
35.00%
30.00%
Street
Surveys
Percentages
25.00%
Phone
Percentages
20.00%
15.00%
10.00%
5.00%
0.00%
20
35%
32.7%
32.3%
30.6%
30%
27.0%
26.3%
24.3%
25.0%
25%
21.4%
21.7%
Q2
2011
19.6%
20%
18.9%
16.5%
Q3 2011
18.5%
Q4 2011
16.3%
15.9%
Q1 2012
15%
12.6%
11.3%
10.8%
10.6%
10%
7.8%
5%
0%
40.00%
35.00%
30.00%
25.00%
Street
Surveys
Percentages
20.00%
Phone
Percentages
15.00%
10.00%
5.00%
0.00%
21
60%
50%
47.2%
41.5%
41.4%
42.2%
38.7%
36.9%
37.3%
40%
34.2%
Q3
2011
Q4
2011
30%
Q1 2012
20%
15.2%
10%
15.8%
12.0%
11.1%
7.7%
4.1%
0%
Q2 2011
Project
email
updates
Project
website
updates
7.1%
5.1%
7.3%
Radio messages
40%
35%
40.1%
34.9%
30.9%
30%
Q2
2011
25.8%
Q3 2011
25%
Q4
2011
20.6%
19.1%
20%
11.6%
12.4%
11.2%
10.4%
10.0%
10%
5%
0%
1.8%
Television
Socia media
Q1 2012
17.2%
16.9%
15%
18.4%
3.7% 2.7%
Mee<ngs
11.7%
3.5%
Newspaper
City newsleEer
22
64.0%
60%
50%
43.9%
40%
Q1
2012
30%
20%
14.8%
13.3%
10.7%
10%
0%
Project
email
updates
Project
website
updates
43.6%
40%
33.7%
35%
30%
25%
18.1%
20%
15%
8.2%
10%
6.9%
5%
0%
Television
Socia media
Mee<ngs
Newspaper
City newsleEer
Q1 2012
23
Area Specific
24
35
30
25
20
15
10
Q3 2011
Other/Non-Response
Vineyard
Springville
Spanish Fork
Saratoga Springs
Santaquin
Provo
Payson
Pleasant Grove
Orem
Mapleton
Lindon
Lehi
Highland
Eagle Mountain
Cedar Hills
American Fork
Alpine
Q4 2011
60
Q4
2011
50
47
Number of Respondents
44
40
32
30
20
17
14
10
Before 6 am
6-9am
9-4pm
4-7pm
a4er 7 pm
25
45
42
40
35
35
32
31
30
25
20
15
12
10
8
5
70
0 0
Other/Non-
Response
Vineyard
Springville
Spanish Fork
0 0
Saratoga
Springs
Santaquin
Provo
Pleasant
Grove
Orem
Mapleton
Lindon
Eagle
Mountain
Highland
0 0
Payson
Lehi
3 3
Cedar Hills
Alpine
3 3
American
Fork
5
0
Q4
2011
Q1
2012
63
63
60
51
50
Number
of
Respondents
13
45
40
43
37
35
30
23
20
12
10
2
0
Before 6 am
6-9am
9-4pm
4-7pm
a4er 7 pm
26
90
83
78
80
70
60
50
40
30
25
20
Springville
0 0
Other/Non-
Response
2 2
Vineyard
1 2
Spanish Fork
0 0
64
Q4
2011
Q1
2012
50
Number
of
Respondents
0 0
Saratoga
Springs
0 0
Santaquin
1 0
Provo
70
60
Payson
Eagle Mountain
0 0
Pleasant Grove
Cedar Hills
1 1
Orem
American Fork
1 2
Mapleton
0 0
Lindon
0 0
Lehi
1 0
Alpine
0 0
Highland
10
47
40
40
38
34
32
30
30
24
20
10
7
3
Before 6 am
6-9am
9-4pm
4-7pm
a5er 7 pm
27
80
72
70
65
60
50
40
30
Q4
2011
Q1
2012
Other/Non-Response
Saratoga Springs
0 0
Vineyard
0 0
Spanish Fork
Santaquin
55
51
46
40
Provo
Payson
0 0
10
50
Number of Respondents
Pleasant Grove
Lehi
60
0 1
4 3
Orem
0 0
Mapleton
0 0
Lindon
0 0
Highland
American Fork
0 0
Eagle Mountain
1 0
Cedar Hills
0 0
Alpine
10
0
14
12
Springville
20
48
36
30
30
25
21
20
11
10
Before 6 am
6-9am
9-4pm
4-7pm
a5er 7 pm
28
Phone Survey
100
88
90
80
70
66
60
50
41
33
29
27
23
19
Q1 2012
Spanish Fork
Santaquin
Provo
Payson
Pleasant Grove
Orem
Mapleton
Lindon
Lehi
Highland
Phone
Sample
Travel
Times
36.13%
35.00%
29.58%
30.00%
25.00%
Number
of
Respondents
21.68%
20.00%
15.00%
9.24%
10.00%
5.00%
0.00%
3.36%
Before 6 am
6-9 am
9-4 pm
4-7 pm
a7er 7 pm
Other/Non-Response
40.00%
9
4
Eagle Mountain
Alpine
American Fork
10
14
10
Saratoga Springs
12
Cedar Hills
20
Vineyard
30
Springville
40
29
Question 1 by area:
On a scale of one to five with one meaning completely disagree and five meaning
completely agree, please rate the project on the following:
30
Safe
Dust
Noise
Q3 2011
Ramps
Q4 2011
Crews
courteous
Q1 2012
Safe
roadway
Clear
lane
markings
Safe
roadway
Clear
lane
markings
Orem
Q2
2011
4
3.75
3.5
3.25
3
2.75
2.5
2.25
2
1.75
1.5
1.25
1
Safe
Dust
Noise
Q3 2011
Ramps
Q4 2011
Crews
courteous
Q1 2012
31
Provo
Q2
2011
5
4.75
4.5
4.25
4
3.75
3.5
3.25
3
2.75
2.5
2.25
2
1.75
1.5
1.25
1
Safe
Dust
Noise
Q3 2011
Ramps
Q4 2011
Crews
courteous
Q1 2012
Safe
roadway
Clear
lane
markings
Spanish
Fork
Q2
2011
Q3 2011
Q4 2011
Q1 2012
Ramps
Crews
courteous
No
delays
Reasonable
delays
5
4.5
4
3.5
3
2.5
2
1.5
1
Safe
Dust
Noise
Overall
response
Safe
roadway
Clear
lane
markings
32
Phone
Q1
2012
5
4.5
3.99
4
3.5
3.38
3.38
3.18
3.01
4.07
3.98
3.32
3.54
2.87
2.61
2.53
2.5
2
1.5
1
Safe
Dust
Noise
Clear
and
navigable
detours
Ramps
Crews
No
delays
Reasonable
Overall
courteous
delays
response
Safe
roadway
Clear
lane
markings
Q2 2011
Q3 2011
Q4 2011
Q1 2012
4.5
4
3.5
3
3.32
2.87
2.94
2.73
2.7
2.75
2.76
2.94
2.98 2.94
3.02
2.93
2.91
2.77
2.7
2.85
2.94
2.86
2.77
2.85
2.5
2.5
2
1.5
1
American Fork
Orem
Provo
Spanish Fork
All
Phone
1.25
1.5
1.75
2.25
2.5
2.75
3.25
3.5
3.75
4.25
4.5
4.75
Safe
2.34
Dust
3.54
Noise
3.51
Easy
to
read
signs
2.72
Clear
and
navigable
detours
2.39
Q2 2011
Ramps
2.95
Q3 2011
Crews
courteous
3.66
Q4 2011
2.10
No delays
Q1 2012
Reasonable
delays
2.93
3.09
2.11
2.94
33
34
I feel safe when driving through the construction zones (average response on a
1 to 5 scale):
5
4.5
4
3.5
Q2
2011
3.01
Q3 2011
2.47
2.5
2.6
2.42
2.48
2.28
Q4 2011
2.47 2.39
2.51
2.38
2.37
2.37
2.19
2.12
2.07
Q1 2012
2.2
1.97
2
1.5
1
American Fork
Orem
Provo
Spanish Fork
Phone
Provo
-
"Safe"
45
39
40
35
30
51
38
50
38
43
32
30
40
28
25
25
30
23
24
20
33
25
23
19
15
18
16
15
10
4
1
1
20
18
18
16
14
13
31
35
33
31
30
20
20
21
35
28
28
27
24
22
23
10
10
8
6
18
16
15
13
35
20
15
5
32
25
19
37
30
22
40
40
25
Orem - "Safe"
36
32
45
41
35
7
6
42
40
24
22
30
27
10
45
28
21
20
9
29
28
14
10
5
0
10
10
8
11
4
35
3.54
3.5
3.23
3.05
2.97
2.95
3.19
3.14 3.09
2.85
2.57
2.5
2
Q3
2011
Q4
2011
1.5
Q1 2012
1
0.5
0
American Fork
Orem
Provo
Spanish Fork
32
33
33
33
21
21
33
30
24
12
10
10
7
15
15
15
14
12
11
13
10
6
33
20
25
17
13
12
10
10
20
15
10
30
24
25
19
35
34
30
15
39
35
27
18
10
40
40
32
28
25
45
33
31
30
23
21
20
20
14
14
14
33
27
25
16
15
40
35
26
20
41
40
30
25
Phone
19
18
15
14
12
9
10
10
10
5
0
36
4.5
3.99
3.75
3.66
3.5
3.44
3.54
3.5
3.55
3.5
3.44 3.49
3.29
3.25
3.11
3.24
Q2 2011
Q3
2011
Q4
2011
2.5
Q1 2012
2
1.5
1
American Fork
Orem
Provo
Spanish Fork
Phone
Provo - "Dust"
40
36
35
35
32
31
30
28
26
19
19
17
13
16
14
13
11
19
18
14
13
11
8
9
6
36
40
34
23
21
15
13
8
25
21
15
14
10
10
23
22
21
19
18
16
17
15
14
9
5
30
29
20
20
29
29
25
34
33
32
33
32
30
37
35
50
10
7
Orem
-
"Dust"
57
22
24
20
40
60
30
28
27
26
25
29
20
10
10
30
15
11
20
36
34
25
20
10
38
35
25
15
40
40
37
4.5
3.98
4
3.4
3.5
3.59
3.52
3.46
3.38
3.49
3.7 3.71
3.6
3.59
3.45
3.31
3.31
3.38
3.65
3.21
Q2 2011
Q3
2011
Q4
2011
2.5
Q1 2012
2
1.5
1
American Fork
Orem
Provo
Spanish Fork
Phone
Provo
-
"Noise"
45
38
37
36
35
40
36
32
30
35
29
27
25
24
20
17
15
12
10
5
0
16
14
10
5
27
22
20
17
13
12
11
8
5
45
45
45
40
40
37
35
40
22
21
20
11
13
13
12
11
10
27
25
28
26
27
20
16
15
12
12
13
30
28
23
20
10
34
32
30
29
23
12
36
35
29
25
40
40
35
30
50
50
10
Orem - "Noise"
15
19
19
30
28
30
29
25
36
33
30
15
13
10
41
40
10
38
2.5
2.5
2.33
2.24
2.14
2.15
2.05
2.07
2.04
1.99 1.96
2.61
2.48 2.49
1.5
Q3
2011
Q4
2011
Q1
2012
0.5
American Fork
Orem
Provo
Spanish Fork
60
47
45
50
40
40
49
37
30
25
27
14
10
13
14
11
19
12
11
50
45
50
37
38
48
37
35
40
31
30
25
30
24
19
31
22
24
16
10
10
5
2
15
11
4
3
2
16
16
13
14
10
28
20
15
15
34
39
20
12
40
19
3
2
19
13
10
11
28
26
15
15
36
33
20
20
37
35
39
39
30
45
Phone
6
4
39
4.5
4
3.5
3
2.69
2.66
2.63
2.5
Q2 2011
2.92
2.91
Q3 2011
2.77
2.68
2.63
2.53
2.42
3.18
3.12
3.04
2.44
2.63
2.52
Q4
2011
Q1
2012
2.29
2
1.5
1
American Fork
Orem
Provo
Spanish Fork
45
45
40
40
40
35
31
30
25
24
25
21
21
22
19
17
18
10
8
7
25
20
20
24
16
8
7
26
19
20
12
5
3
25
13
15
8
6
10
5
0
26
27
21
24
19
20
15
29
29
25
19
10
32
30
24
15
37
35
25
23
40
30
24
20
45
35
25
15
14
14
10
33
25
24
23
19
50
40
30
21
17
30
29
25
31
30
25
15
15
10
33
30
25 25
27
15
25
35
35
30
28
20
35
Phone
19
17
16
18
16
16
12
11
10
40
The detour routes are clear and easy to navigate (or drive) [average response
on a 1 to 5 scale]:
5
4.5
4
3.5
Q2
2011
2.87
2.94
3
2.64
2.47
2.45
2.41
2.5
2.77
2.73
2.56
2.58
2.49
Q3 2011
2.65
Q4 2011
2.39
2.35
2.32
Q1 2012
2.21
2.14
2
1.5
1
American Fork
Orem
Provo
Spanish Fork
Phone
Provo
-
"Detours"
50
45
50
40
35
30
25
25
32
32
32
30
40
32
35
29
29
25
23
22
21
20
20
15
25
26
26
29
25
22
20
19
17
16
6
3
1
17
12
10
10
9
8
3
Orem - "Detours"
50
38
46
46
45
35
32
30
40
32
29
27
26
26
22
24
15
8
8
7
5
4
5
3
24
22
21
21
20
17
19
15
10
10
26
25
20
36
30
23
19
40
35
29
23
20
28
26
20
19
18
25
31
30
10
40
48
16
17
14
13
10
10
7
5
0
41
Access to I-15 on- and off-ramps has been maintained (average response on a 1
to 5 scale):
5
4.5
4
3.38
3.5
2.93
2.79 2.76
2.72
2.55
2.5
2.96
2.91
2.79
2.89
3.09
2.92 2.9
Q2 2011
Q3 2011
2.72
Q4 2011
2.5
Q1 2012
2.22
2
1.5
1
American Fork
Orem
Provo
Spanish Fork
Phone
Provo
-
"Ramps"
45
40
35
30
27
26
26
26
26
18
18
20
15
15
10
21
20
18
17
14
13
13
10
Orem
-
"Ramps"
40
40
35
35
32
30
32
29
27
26
17
15
22
21
21
20
30
28
24
23
23
21
20
17
15
15
14
13
11
10
29
27
26
25
25
20
34
30
29
25
20
14
23
21
25
26
22
10
8
7
29
27
26
25
20
15
32
30
25
24
19
39
35
28
28
25
20
40
34
32
19
18
17
26
18
16
14
13
12
10
11
5
2
42
4.5
4.07
3.96
4
3.58
3.57
3.66
3.67
3.59
3.85
3.54
3.5
3.65
3.85
3.74
3.6
3.67
3.56
3.42
3.14
Q2 2011
Q3
2011
Q4
2011
2.5
Q1 2012
2
1.5
1
American Fork
Orem
Provo
Spanish Fork
Phone
Provo - "Crews"
50
45
50
41
40
37
35
35
30
25
33
30
25
24
23
20
32
30
30
28
28
27
25
28
24
20
15
10
5
10
9
8
5
2
5
5
3
Orem - "Crews"
50
47
46
45
50
50
40
47
36
35
33
31
30
33
23
20
23
20
19
19
15
10
5
5
2
31
30
33
30
23
20
35
30
10
8
6
39
40
29
26
25
43
41
40
40
34
32
30
50
20
7
2
20
9
7
5
3
43
4.5
4
3.5
Q2
2011
Q3
2011
Q4 2011
2.53
2.46
2.5
2.29
2.21
2.05
2.34
2.12
2.03
1.95
2.32
2.28
1.98
2.06
1.85
1.76
Q1 2012
2.23
1.88
1.5
1
American Fork
Orem
Provo
57
55
53
80
70
50
46
50
30
31
30
40
22
20
21
10
7
5
4
6
4
27
22
16
10
14
9
10
15
14
11
10
10
6
9
5
70
61
60
59
50
48
45
42
44
40
38
30
30
29
28
25
20
18
10
0
33
28
40
35
20
13
11
10
9
46
42
30
18
10
50
67
60
40
Phone
60
60
Spanish Fork
15
11
10
10
6
15
13
10
0
21
18
16
12
19
20
19
16
14
27
12
11
6
44
4.5
4
3.38
3.5
3.27
3.09
2.8
2.77
2.61
2.71
3.12 3.09
Q3 2011
2.82
2.7
Q4
2011
2.53
2.46
2.5
Q2 2011
3.15
3.02
2.95
3.17
Q1 2012
2
1.5
1
American Fork
Orem
Provo
Spanish Fork
Provo - "Reasonable"
40
35
35
34
33
31
30
25
21
18
15
16
15
15
11
9
8
6
10
5
0
14
12
10
5
1
30
32
31
31
28
20
42
38
30
26
23
20
25
22
20
18
16
15
12
35
26
25
40
35
12
14
14
10
5
0
17
16
Orem - "Reasonable"
37
30
27
14
45
40
10
28
26
19
15
29
22
21
19
38
21
20
18
15
29
25
25
24
20
38
30
25
24
21
32
31
27
Phone
20
26
20
21
18
15
10
27
27
26
26
24
23
15
14
14
11
10
10
10
45
Question 4 by area:
Several methods are being used to help people stay informed about construction activities.
Of the following methods, which ones do you use to stay informed about the I-15
construction project? Choose all that apply:
Metric is actual number of responses out of ~100 respondent sample. Because each
sample is out of ~100, this is essentially interchangeable with a percentage.
46
American
Fork
65
60
55
50
45
40
35
30
25
20
15
10
5
0
Website
Electronic
Roadway
Signs
Door
Hangers
Radio
TV
Local
Events
Social
Media
Newspapers
City
Website
TV
Local
Events
Social
Media
Newspapers
City
Website
Orem
65
60
55
50
45
40
35
30
25
20
15
10
5
0
Website
Electronic
Roadway
Signs
Door
Hangers
Radio
47
Provo
60
55
50
45
40
35
30
25
20
15
10
5
0
Website
Radio
TV
Spanish
Fork
55
50
45
40
35
30
25
20
15
10
5
0
Website
Electronic
Roadway
Signs
Door
Hangers
Radio
TV
Local
Events
Social
Media
Newspapers
City
Website
48
Orem:
Spanish Fork:
Working on all the major side roads and frontage roads as well as the free way makes it difficult and
frustrating.
Provo:
I wish the signs were easier to notice (i.e. Provo Center Street, exit). They blend in with the orange all
around The removal of old lane lines, addition of temp lines, cones, and varying asphalt colors make it
hard to navigate and understand traffic pattern. I do appreciate the work being done and understand the
necessity but the everywhere-ness of it is tiresome and very inconvenient. If it were clearer and if I had
done more to be informed, it would be better. The lanes are rough to understand.
The main thing they could improve is road signs and lane markings. Sometimes you cant tell what your
lane is, creating increased danger. Lack of advanced warning, in particular lane reduction, seem to be the
biggest cause of traffic jams. Drivers dont have enough warning to change lanes, leading to backing up
when they try to change at the last moment.
49
Orem:
On various road sides, there are signs that say so many minutes that way and so many minutes this way.
I cant say that impacts the drivers decision. I dont think that it is helpful one way or another. Its a big
waste of money. UDOT is doing a good job, though.
I am grateful and feel wonderful that they have done this, but I feel anxious when I am riding on the road.
They are changing the channels that we are going through, and it fills me with so much anxiety. I really
need to focus and be attentive because the lines are very obvious that it is filled. Overall, UDOT has done a
very good job, and it is a challenging job. The electronic signs are good. The crews were courteous. Its a
good thing that there are no accidents that have happened.
They need more patrolmen because we used to travel on that road.
Theyve got to accommodate commuter traffic at high traffic times. They cannot arbitrarily close major
thoroughfares without proper advanced warning, like University parkways.
Sometimes, the lane markings are hard to determine at night.
By using orange paint in remarking construction lanes, there is greater visibility that would result for the
drivers.
Signs are clearly done in roads. In Spanish Fork, I do not feel safe in that area.
The entrance to Provo is too slow in the I-15. There is traffic congestion.
The only concern I have is on the center street in Orem. The lights there and on the 12th West are not
coordinated well, so there is a huge backup.
Its about widening the road to have three to six lanes. It should only take two months, and thats the
most.
We think they have a very good job in traffic control considering that it is a complex project. They have
done it very well.
My only concern is that there is that one section on the 15th south near 1600 north on ramps wherein
lines are not clear. I do not know where my lane is clearly going.
50
What bothers me the most is the narrow lanes. It is very challenging and dangerous when passing through
big trucks. Secondly, there are no emergency lanes. The third one is theres a lot of debris, which is kind of
dangerous.
I would like to see more information on the stops, what they are going to make as well as where and when.
I hope they will have more advertisements about the construction.
Provo:
Its the Provo Center Street. The design of the freeway they made was confusing. Some parts are
dangerous. If I am driving from the East to West, I have to turn left. Theres a crowded and dangerous
part.
The lanes are too narrow.
Last night around 7 PM, we entered the 8-North Entrance Freeway in Orem and the green light was on. My
husband thinks the green light slows things down.
Weve been calling from someone in UDOT about the ramp on 1600 road that was closed. It causes traffic.
The wait time is way too long.
It is about where they do the lane split. They have to put more signs ahead or make it clearer. There
should be clearer warning for what is to come.
Spanish Fork:
I want to have them make sure that the lanes in Spanish Fork off-ramp are not horrible. My car has to tip
sideways slightly, which is dangerous. They should level the asphalt better and make it concrete.
Aside from not being able to see the markings on the lanes, they are doing a pretty good job. There is
an unevenness of the road and the paving of the asphalt from old to new, but considering the size of the
project, they are doing a good job.
They are doing wonderfully except for the uneven surfaces in Springville and Orem, which are a lot.
There was so much of the debris that was torn up and all of those were unsafe.
It would be the rock trucks. They accidentally threw over the road and hit my car and windshield.
51
52
53
Key Findings
Summary of results
54
Overall Results
The average of all Q1 2012 responses gathered in the four man-on-the-street surveys was
2.94 on a five-point scale. This shows an increase from the last quarter, which yielded an
overall average of 2.85.
The most negative geographic area in Q1 2012 was American Fork/Lehi receiving a 2.76.
Although American Fork also experienced the most negative in overall score it is
improving. The area of Provo yielded the most significant decrease in overall score going
from 3.02 to 2.77, whereas in Q4 2011 it scored as the most positive geographical area.
Scores decreased in the following questions: Maintain safe roadways, Noise, Lane
markings clear, Easy to read, Detours, Travel delays, and Reasonable.
The most positive geographic area in Q1 2012 was Orem with a score of 2.94 on a fivepoint scale. There was an increase on every question except for Lane markings clear and
Travel delays.
Five categories in Question 1 increased in average score from Q1 2012. The four categories
that yielded a decrease in score from Q1 2012 were Noise, Detours, Reasonable delays,
and Clear lane markings. Dust and No delays were the two categories that maintained
their scores from Q4 2011.
Construction crews are courteous received the highest average response with a score of
3.66 on a five-point scale. No delays was the weakest point once again in Q1 2012 with
an average of 2.1 on a five-point scale.
We saw a general increasing trend in all the communication method categories except
Project email updates and Project website updates. Electronic roadway signs emerged as
the communication method most used again at 47.2%. Television emerged second place at
40.1% and Radio at third place with 37.3%. The most significant increase in preferred communication method was Newspapers which increased from 17.2% in Q4 2011 to 25.8% in Q1 2012.
55
Detailed Results
An Increase in Overall Average
The largest contributing factor for an increase in overall average score was the significant
increase in score in Orem.
Orem was the area with the most positive growth receiving
a 2.94 on a five-point scale, up from 2.7 in Q4 2011.
American Fork experienced increases in overall scores.
Five out of 11 categories in Question 1 increased in score from Q4 2011.
If Provo had not experienced such a drastic decrease in score, the project would have
achieved a greater overall average.
The most positive geographic area in Q1 2012 was Orem with a score of 2.94
on a five-point scale, increasing on all but two questions.
American Fork experienced growth in their average overall response score
from 2.75 in Q4 2011 to 2.76 on a five-point scale.
Most Improvement
The Question 1 category that experienced the most positive growth in Q1 2012 as
compared to Q4 2011 was Ramps.
In American Fork Ramps increased to 2.93, from 2.72 Q4 in 2011.
In Orem Ramps increase to 2.96, from 2.76 in Q4 2011.
Provo and Springville remained about the same.
Most Decline
When asked to agree or disagree with the statement The detour routes are clear and easy
to navigate, people responded more negatively to this statement than Q4 2011.
American Fork received 2.41, down from 2.32 in Q4 2011, based on a five-
point scale
Springville received 2.39, down from 2.58 in Q4 2011, based on a five-point
scale.
Provo received 2.35, down from 2.58 in Q4 2011, based on a five-point scale.
Orem recieved 2.49, up from 2.21 in Q4 2011, based on a five-point scale.
56
Communication
In Q1 2012, respondents generally still look to electronic roadway signs and traditional
media sources like television and radio more than non-traditional media sources; however,
Newspaper experienced the most positive growth. The most significant decline in the
percentage points was seen in Project website updates. Social media the category that
showed the largest decrease in category Q4 2011 showed significant increase in Q1 2012.
Television experienced positive growth of 1.8%. Television
experienced growth in percentage points in all four areas except Provo.
Electronic roadway signs was reported as the most used method of
communication in Provo, American Fork and Spanish Fork.
The most used method of non-traditional communication was Social media at
16.9%.
Local meetings/public events experienced an overall increase of 0.8%, with
increases in all areas except for Springville.
Project email updates experienced a 1% decline, much of it coming from
American Fork and Orem.
Door hangers/fliers experienced a 2.2% increase. The most significant de
cline came from American Fork.
Radio messages experienced a 0.4% increase, with increase in America Fork
and decrease in Springville.
Newspapers experienced a 8.6% increase, with the most significant
increases in Orem and Springville.
57
Recommendations
Something Accomplishable
The following are recommendations that may help UDOT increase the publics perception
about the project. The following areas are reasonable and accomplishable.
Improvements in Provo
Provo received the largest decrease in overall ratings. The most significant decreases were
in the categories of Clear lane markings, No delays, Noise, Easy to read signs, and
Clear and navegable detours. The following comments highlight the general feeling in
Provo, and the need for a focus on improvement in the area.
I wish the signs were easier to notice (i.e. Provo Center Street, exit). They blend in with
the orange all around The removal of old lane lines, addition of temp lines, cones, and
varying asphalt colors make it hard to navigate and understand traffic pattern. The
lanes are rough to understand.
The main thing they could improve are road signs and lane markings. Sometimes you
cant tell what your lane is, creating increased danger. Lack of advanced warning, in
particular lane reduction, seem to be the biggest cause of traffic jams. Drivers dont
have enough warning to change lanes, leading to backing up when they try to change at
the last moment.
Communication Campaign
A significant number of complaints were expressed in the Free Response section of the
survey regarding delays. Although the delays cannot be eliminated until the project is
done, the reason for the delays can be better communicated.
This may be done through the most effective methods of preferred communication shown
in the Preferred Communication charts. Radios messages, Television, and Electronic
Roadway Signs, have highest percentages of preference in receiving notifications
regarding the I-15 construction areas.
With a recent increase in the Newspaper category, now might be the best time to utilize
newspapers in helping drivers understand the need for construction and why it causes
traffic delays.