Professional Documents
Culture Documents
Assessment of Energy Storage For Transmission-Constrained Wind
Assessment of Energy Storage For Transmission-Constrained Wind
Applied Energy
journal homepage: www.elsevier.com/locate/apenergy
h i g h l i g h t s
We assess the potential for energy storage to economically decrease wind curtailment or decrease system costs.
We assume that the wind is under contract via a power purchase agreement.
Maximum viable energy storage costs were $780/kW with ten hours of storage capacity.
Sizing the energy storage to reduce a small portion of curtailment supports higher unit cost batteries.
Signicant curtailment persists even with high capacity energy storage.
a r t i c l e
i n f o
Article history:
Received 17 June 2013
Received in revised form 31 January 2014
Accepted 2 March 2014
Available online 11 April 2014
Keywords:
Wind
Curtailment
Energy storage
Transmission
Power purchase agreement
a b s t r a c t
Grid-scale energy storage is one option to reduce curtailment and increase deliverability of transmissionconstrained wind. This study examines four hypothetical wind and transmission projects in the United
States to quantify the reduction in curtailment under various energy storage congurations and
determine the cost targets that energy storage must achieve to become a viable solution for use with
remote wind. The delivered cost of wind is determined using a power purchase agreement approach
and six AC transmission voltage classes are considered. The ndings show that curtailment reduction
can be achieved with energy storage costs as high as $780/kW with ten hours of storage capacity, a value
that is 5085% lower than current cost estimates for redox and sodium sulfur batteries. Batteries with
higher power ratings result in greater curtailment reduction, but also lower maximum viable costs. Sizing
the battery to reduce a small portion of curtailment allows for higher utilization of the storage and
supports higher cost batteries. Using energy storage to increase wind installed capacity can also be
economically viable, but at costs lower than those for curtailment reduction. The results were most
sensitive to the elimination of wind subsidies, the installed cost of transmission, battery efciency
degradation, and battery cycle life. The study did not show economic viability for the use of energy
storage to reduce transmission voltage class.
2014 Elsevier Ltd. All rights reserved.
1. Introduction
The highest quality onshore wind resources are often located far
from load centers and a signicant amount of new transmission
will be needed to support high penetrations of wind energy [1].
Minimizing the cost to deliver remote wind is essential for this
technology to continue to compete with other renewables and
with traditional generation. Energy storage co-located with the
wind resource can reduce curtailment, increase transmission line
utilization, allow for lower voltage lines to be used, and, poten-
378
379
Fig. 1. Map of four scenarios. Wind map adapted from the National Renewable
Energy Laboratory.
t0
tax
where
tax
where
380
Table 1
Wind Assumptions.
Cost assumptionsa
Overnight capital cost ($/kW)
Fixed O&M ($/kW-yr)
Variable O&M ($/MW h)
Allowance for funds during construction
Site A
Site B
Site C
Site D
2099
27.2
3%
2099
27.2
3%
2300
29.8
3%
2521
32.7
3%
5.0%
35.0%
38.3%
1.0%
1.0%
14.0%
30.0%
6.0%
20
6.8%
Ination assumptiond
Ination (%/yr)
2.0%
Depreciation assumptionse
5-Year MACRS (% of installed cost)
20-YrMACRS (% of installed cost)
No MACRS (% of installed cost)
Bonus deprecitation (% of installed cost)
45.0%
2.5%
2.5%
50.0%
0.022
30%
95%
50%
a
Installed cost assumptions are based on Wind Technologies Market Report,
selected for each region [4]. All O&M costs are treated as xed costs (i.e., independent of generation levels) and escalate at the rate of ination. O&M costs do not
include property tax or insurance, which are included separately. Allowance for
funds used during construction is consistent with construction nancing costs in
Tegan et al. [18].
b
Tax and insurance rates are estimated. Property tax and insurance costs escalate
at the rate of ination.
c
The debt to equity ratio was estimated based on the amount of secured debt for
4000 MW of wind [4]. Debt rates under 6% are noted in the same reference.
d
Estimate.
e
Bonus depreciation was extended in American Taxpayer Relief Act of 2012.
Accelerated (MACRS) depreciation is allowed under 26 USC 48(a)(3)(A). The share
of installed cost that is eligible for 5-year depreciation (after bonus depreciation) is
based on Bolinger et al. [19].
f
Wind projects are eligible for either the federal production tax credit (PTC) or
the investment tax credit (ITC). The PTC and ITC were renewed in January 2013
under the American Taxpayer Relief Act of 2012. The share of installed costs that
qualify for the ITC is from Bolinger et al. [19]. The Internal Revenue Service allows
half of the value of the ITC to be depreciable.
Loss %
Q rd
V2
RRwind RRTX
Q t h X t 1 Lt
where RRwind and RRTX are the annual revenue requirements for
wind and transmission in $, Q is wind production (MW), h is time
(hours), X is the energy lost to curtailment (MWh), and L represents
the transmission loss rate (%), summed over all time intervals t for
the year (there is 52,560 ten-minute time intervals in a non-leap
year). The minimized delivered energy cost is bounded by the maximum installed wind capacity and solved using the site-specic line
distance and wind shape, coupled with cost assumptions provided
in Tables 1 and 2. Delivered costs are calculated for each of the
six voltage classes. The minimized cost determines the lowest cost
combination of wind capacity and voltage class and represents the
target value of a signed PPA with a load serving entity. The effective
introduction of energy storage to the wind-transmission system
should result in lower delivered costs or more wind delivered at
the same cost.
2.3. Determining the breakeven cost for energy storage integration
into wind-transmission system
For each scenario, we assessed the opportunity to introduce energy storage into the wind-transmission system for three applications: (1) mitigation of curtailment, (2) reduction of transmission
voltage class, and (3) increasing the wind installed capacity. For
381
Cost assumptions
Line ($000/mile)a
Station ($M)b
Less than 300 miles
300480 miles
More than 480 miles
Allowance for funds during construction and overheadc
Fixed O&M (% of installed cost)d
115 kV
230 kV
345 kV
345 kV 2 circuit
500 kV
765 kV
483
927
1298
2077
1854
3060
2.7
2.7
2.7
17.5%
3%
12
14
15
17.5%
3%
32
38
42
17.5%
3%
61
71
79
17.5%
3%
65
79
90
17.5%
3%
148
175
200
17.5%
3%
a
Costs for 115 kV project based on project proposal estimates. Transmission line costs for 230 kV, 345 kV, and 500 kV are based on Black & Veatch analysis [20]. Costs for
765 kV are based on selected projects detailed in Mills et al. and escalated to current dollars [21].
b
Station costs are based on the same references in footnote a, following the approach employed by Newcomer and Apt [22].
c
Based on NREL review [18].
d
Estimate.
Table 3
Transmission loadability and loss assumptions voltage class.
SILa
Resistanceb
MW per unit
ohm/mi
115 kV
230 kV
345 kV
500 kV
765 kV
35
0.24
140
0.07
420
0.048
1000
0.024
2280
0.012
a
The surge impedance loading for each voltage class is representative of typical
assumptions for 60-Hz overhead lines [25].
b
Line resistance can vary greatly within a voltage class. The assumed values are
consistent with the weighted averages for U.S. transmission lines by voltage class,
as published in Kappenman (2010) [26].
where Pcharge,t is the charge rate for the battery at time t in MW, Qt is
the wind output in MW, CAPTX is the transmission line loadability in
MW, Pbatt,t is the batterys rated power in MW at time t, SOCt is the
batterys state of charge as a percentage of the total storage
capacity.
382
C deliv ered
52;560
X
t1
10
3. Results
3.1. Determining the power purchase agreement price
The shape of the wind duration curves, as shown in Fig. 2, determine the amount of wind curtailed for given transmission loadabilities. Fig. 3 shows the relationship between wind curtailment and
the ratio of wind installed capacity and transmission loadability.
While the differences between the scenarios may appear modest,
small differences in curtailment can greatly affect the viability of
wind projects. Case B (Minnesota wind) has a atter generation
383
Fig. 4. Minimized cost of delivered wind for (a and b) Site A Iowa wind; (c and d) Site B Minnesota wind; (e and f) Site C New York wind; and (g and h) Site D Maine
wind. Left side graphs = all voltage classes; right side graphs = only the optimal voltage class for transmission.
384
For three of the scenarios (A, B, and D), dropping to the next
lower voltage class while maintaining wind installed capacity
would represent a major increase in the delivered cost of wind,
as much as 100% over the optimized cost. These large increases
in installed costs are driven primarily by reduced line loadability,
resulting in signicant increases curtailment and reductions in
the amount of delivered electricity. For Site C (NY), dropping from
500 kV to 345 kV transmission, before introducing energy storage,
increases the delivered cost of wind by 21%. This smaller increase is
because the cost minimized system with the 500 kV line had signicant excess transmission capacity and dropping to the lower
voltage line would cause a more modest amount of curtailment.
Therefore, Site C was examined to test the viability of introducing
energy storage to reduce voltage class.
Even for very large batteries (289 MW with 2890 MW h of storage capacity), the ability of the battery to atten the wind shape
was insufcient to decrease the delivered cost of wind on the
345 kV system below the costs found using 500 kV line. This suggests that, for the scenarios examined, batteries at no cost would
still not be benecial for use to decrease voltage class. These scenarios do not paint a comprehensive picture given that more transmission design alternatives could be examined, but suggest that
using batteries for this purpose may only be appropriate in very
specic situations. In addition, building transmission with lower
loadability reduces the potential for greater use in the future.
Fig. 5. Annual reduction in wind curtailment with batteries of varying power and storage capacity for (a) Site A Iowa wind (where 100% of battery power equals 129 MW
and 100% of curtailment equals 235,000 MW h) and (b) Site D Maine wind (where 100% of battery power equals 30 MW and 100% of curtailment equals 26,500 MW h).
385
Fig. 6. Maximum installed battery cost for Site A Iowa wind (a) per power rating and (b) per energy storage capacity (where 100% of battery power equals 129 MW); and for
Site D Maine wind (c) per power rating and (d) per energy storage capacity (where 100% of battery power equals 30 MW).
386
Fig. 7. Maximum installed battery cost for increased wind capacity at Site A Iowa wind with one hour of storage (a and b); ten hours of storage (c and d); at Site B with ten
hours of storage (e and f); at Site D with one hour of storage (g and h); ten hours of storage (i and j).
Fig. 8. Results of sensitivity analysis for Site A (Iowa wind) with 10 MW battery and
100 MW h of energy storage capacity. When low and high sensitivities are tested,
the results of the rst assumption listed are shown in blue (decrease in maximum
costs), while the results from the second assumption are shown in gray (increase in
maximum costs). (For interpretation of the references to colors in this gure legend,
the reader is referred to the web version of this paper.)
A PPA with on-peak and off-peak pricing was examined for Site
A. Due to its point of delivery, the on-peak to off-peak energy price
difference was based on the hourly locational marginal price for
the ComEd zone in PJM [30]. Based on 2012 data, average on-peak
prices were $9.69/MW h higher than average off-peak prices. A PPA
for Site A that reects this difference would offer $122.89/MW h
for delivered on-peak wind and $113.20/MW h for off-peak wind
in order to meet the revenue requirements for the wind and
transmission. Given a round trip battery efciency of 75%, this
difference is insufcient to justify time of day arbitrage (i.e., time
shifting to on-peak hours). Because the annual wind resource is
nearly evenly divided between on-peak and off-peak generation,
and the battery discharge is divided between on-peak and off-peak
hours, the introduction of a time of day PPA has minimal impact on
the maximum battery price. A discharge strategy in which a
battery maximizes revenues by optimally delaying the discharge
of some energy to on-peak hours, assuming perfect wind forecast,
results in a trivial (0.1%) increase in revenues. This suggests that
the need to incorporate wind forecasting errors is unnecessary
for this analysis.
4. Discussion
This analysis found that energy storage can be used to improve
the deliverability of transmission-constrained wind if ambitious
cost targets for energy storage are met. In instances where the
optimal wind-transmission system results in some wind curtailment, it was found that energy storage could be incorporated to reduce curtailment at costs as high as $780/kW. Not surprisingly,
higher delivered costs can support more expensive energy storage.
Energy storage can also be introduced to facilitate the incorporation
of additional wind, beyond the optimized installed capacity, but often with lower energy storage cost targets. As the overbuild of wind
increases, it becomes more difcult to cost effectively incorporate
energy storage. The results were most sensitive to the elimination
of wind subsidies, the installed cost of transmission, battery efciency degradation, and battery cycle life. In the cases examined,
energy storage was not a viable option to decrease transmission
voltage class (and thus decrease transmission installed costs).
Researchers at Pacic Northwest National Labs summarized
current capital costs for battery options [7]. Converting their results to a system with ten hours of energy storage capacity, the
range of costs in 2011 is $2600$4900/kW for sodium sulfur
batteries, $880$1170/kW for CAES, and $2700$3900/kW for redox ow batteries. The studys potential costs in 2020 would drop
these values to $1800$3300/kW, $530$1170/kW, and $1500
387
388
%
$
$
%
$/MW
%
$/MW
$/MW h
%
$/MW-yr
$/MW-yr
$/MW-yr
%
rWACC
RRwind
Cwind
rdebt
Bdebt
requity
Bequity
PTC
CF
Income
Int
Dep
rincome tax
$/MW-yr
$/MW-yr
$/MW-yr
Taxproperty
Ins
FOM
MW
$/MW
%
CAPwind
Covernight
AFUDC
%
%
%
%
adebt
aequity
MW per
unit
Ohm/mile
%
MW
Miles
kV
$/MW h
$/MW h
$/MW h
$/MW h
SIL
$/MW h
LMPon
RRTX
MW h
MW
MW
MW
%
MW
%
$/kW
$/MW-h
X
Pcharge
CAPTX
Pbatt
SOC
Pdischarge
ITC
bITC
r
L
Q
d
V
Cdelivered
Cdel,off
Cdel,on
LMPoff
g
Cbattery,power
Cbattery,storage
References
[1] U.S. Department of Energy, 20% Wind Energy by 2030: Increasing Wind
Energys Contribution to U.S. Electricity Supply, 2008.
[2] American Wind Energy Association, AWEA U.S. Wind Industry Fourth Quarter
2012 Market Report, Washington, DC, 2012.
[3] Global Wind Energy Council, Global Wind Report: Annual Market, Update
2012, Brussels, 2013.
[4] Wiser R, Bolinger M. Wind Technologies Market Report, 2012, Lawrence
Berkeley National Laboratory, 2011.
[5] Denholm P. Energy Storage to Reduce Renewable Energy Curtailment, 2012
IEEE Power and Energy Society General Meeting, 2012.
[6] Electric Power Research Institute, Electricity Energy Storage Technology
options: A White Paper Primer on Applications, Costs, and Benets
(1020676), Palo Alto, CA, 2010.
[7] Kintner-Meyer M, et al., National Assessment of Energy Storage for Grid
Balancing and Arbitrage: Phase 1, WECC, Pacic Northwest National Lab
oratory: Richland, WA, 2012.
[8] Eyer J, Corey G. Energy Storage for the Electricity Grid: Benets and Market
Potential Assessment Guide, Sandia National Laboratories: Albuquerque, NM,
2010.
[9] Denholm P, Sioshansi R. The value of compressed air energy storage with wind
in transmission-constrained electric power systems. Energy Policy
2009;37(8):314958.
[10] Denholm P, Hand M. Grid exibility and storage required to achieve very high
penetration of variable renewable electricity. Energy Policy 2011;39(3):
181730.
[11] Fertig E, Apt J. Economics of compressed air energy storage to integrate wind
power: a case study in ERCOT. Energy Policy 2011;39(5):233042.
[12] Greenblatt JB et al. Baseload wind energy: modeling the competition between
gas turbines and compressed air energy storage for supplemental generation.
Energy Policy 2007;35(3):147492.
[13] DeCarolis JF, Keith DW. The economics of large-scale wind power in a carbon
constrained world. Energy Policy 2006;34(4):395410.
[14] Succar S, Denkenberger DC, Williams RH. Optimization of specic rating for
wind turbine arrays coupled to compressed air energy storage. Appl Energy
2012;96:22234.
[15] Madlener R, Latz J. Economics of centralized and decentralized compressed air
energy storage for enhanced grid integration of wind power. Appl Energy
2013;101:299309.
[16] National Renewable Energy Laboratory. Eastern Wind Dataset. 2013 [cited
2013 January 15]. http://www.nrel.gov/electricity/transmission/eastern_
wind_methodology.html.
[17] Congressional Budget Ofce, The Methodology Behind the Levelized Cost
Analysis: Supplemental Material for Nuclear Powers Role in Generating
Electricity, Washington, DC, 2008.
[18] Tegen S, et al. Cost of Wind Energy Review, 2012, National Renewable Energy
Laboratory, 2010.
[19] Bolinger M, Wiser R. PTC, ITC, or Cash Grant? An Analysis of the Choice Facing
Renewable Power Projects in the United States, Lawrence Berkeley National
Laboratory, 2009.
[20] Mason T, Curry T, Wilson D. Capital costs for transmission and susbstations:
recommendations for WECC Transmission Expansion Planning, Black &
Veatch, 2012.
[21] Mills A, Wiser R, Porter K. The cost of transmission for wind energy in the
United States: a review of transmission planning studies. Renew Sust Energy
Rev 2012;16(1):119.
[22] Newcomer A, Apt J. Implications of generator siting for CO2 pipeline
infrastructure. Energy Policy 2008;36(5):177687.
[23] Clair HP St. Practical concepts in capability and performance of transmission
lines. A.I.E.E. Transactions Part III. Power Ap Syst 1953;72(2):11527.
[24] Dunlop RD, Gutman R, Marchenko PP. Analytical development of loadability
characteristics for EHV and UHV transmission-lines. IEEE Trans Power Ap Syst
1979;98(2):60617.
[25] Glover JD, Sarma MS, Overbye T. Power system analysis and design. 5th
ed. Stamford, CT: Cengage Learning; 2012.
[26] Kappenman J. Geomagnetic storms and their impacts on the U.S. Power Grid,
Oak Ridge National Laboratory, 2010.
[27] Eckroad S. EPRI-DOE Handbook of Energy Storage for Transmission &
Distribution Applications: Washington, DC, 2003.
[28] Weber AZ et al. Redox ow batteries: a review. J Appl Electrochem
2011;41(10):113764.
[29] Krieger EM, Cannarella J, Arnold CB. A comparison of lead-acid and lithiumbased battery behavior and capacity fade in off-grid renewable charging
applications. Energy 2013;60:492500.
[30] PJM. PJM Day-Ahead LMP Data. [cited 2013 October, 10]. http://
www.pjm.com/markets-and-operations/energy/day-ahead/lmpda.aspx.
[31] Hittinger E, Whitacre JF, Apt J. What properties of grid energy storage are most
valuable? J Power Sources 2012;206:43649.