Professional Documents
Culture Documents
Technical Aspects of Site Investigation Volume 2
Technical Aspects of Site Investigation Volume 2
Research Contractor:
WS Atkins
Publishing Organisation
Environment Agency, Rio House, Waterside Drive, Aztec West, Almondsbury,
BRISTOL, BS32 4UD.
Tel: 01454 624400
Fax: 01454 624409
Website: www.environment-agency.gov.uk
All rights reserved. No part of this document may be reproduced, stored in a retrieval system,
or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording
or otherwise without the prior permission of the Environment Agency.
The views expressed in this document are not necessarily those of the Environment Agency.
Its officers, servants or agents accept no liability whatsoever for any loss or damage arising
from the interpretation or use of the information, or reliance upon views contained herein.
Dissemination Status
Internal:
Released to Regions
External:
Released to Public Domain
Statement of Use
This document provides guidance to Environment Agency staff, research contractors and
external agencies, on technical issues relating to site investigation, in relation to land
contamination.
Research Contractor
This document was produced under the Land Quality Function R&D Project P5-065/TR by:
WS Atkins, Woodcote Grove, Ashley Road, Epsom, Surrey, KT18 5BW
CONTENTS
1.
INTRODUCTION
2.
10
11
11
2.10 - Audit trails and record keeping - issues on which confidence may be required
12
13
3.
19
20
21
4.
22
23
82
87
90
91
94
5.
95
SAMPLING
5.1 - Checklist of major issues to be considered in preparation for and when sampling
96
98
5.3 - Type and amount of samples (Table A5 from Environment Agency R&D
Technical Report Number P5-066/TR Secondary Model Procedure for the
Development of Appropriate Soil Sampling Strategies (in preparation))
99
5.4 - Field techniques used in soil sampling (Table A7 from Environment Agency
R&D Technical Report Number P5-066/TR Secondary Model Procedure for the
Development of Appropriate Soil Sampling Strategies (in preparation))
100
101
102
6.
ON-SITE MEASUREMENTS
104
105
6.2 - Groundwater field sampling installations commonly used for site investigations
108
6.3 - Groundwater sample extraction methods commonly used for site investigations
109
6.4 - Soil gas sampling equipment commonly used for site investigations
110
111
7.
112
CROSS-CONTAMINATION
7.1 - Some ways in which cross-contamination can occur during a site investigation
113
115
116
117
118
8.
119
ANALYTICAL STRATEGIES
120
121
122
9.
123
TOPOGRAPHIC SURVEYS
124
125
9.3 - An illustration of the value of assimilating topographic survey data with historic
maps
126
126
127
128
10.
129
10.1 - Diagrammatic presentation of Section 6 of the Party Wall etc. Act 1996
Adjacent Excavation and Construction
130
131
11.
132
133
135
136
137
11.5 British Drilling Association site colour coded site characterisation system
138
139
140
141
142
12.
144
ENVIRONMENTAL PROTECTION
12.1 - Fauna species that are protected together with their resting place.
145
146
147
13.
150
151
1.
Introduction
1.1
Background
1.2
1.3
1.4
1.5
Report structure
2.
2.1
Introduction
2.2
Site location
2.3
Site description
2.4
2.5
Archaeological information
3.
3.1
Introduction
3.2
Geology
3.3
Hydrogeology
3.4
Hydrology
4.
Site history
4.1
Introduction
4.2
History
4.3
4.4
4.5
5.
5.1
Introduction
5.2
6.
6.1
6.2
Methodology
6.3
Analytical suites
7.
Factual results
7.1
Introduction
7.2
7.3
7.4
7.5
7.6
10
7.7
10
7.8
10
7.9
10
8.
11
FOREWORD
This document is one of a range of guidance documents published (and in preparation) by the
Environment Agency. Some of these are specific to the new contaminated land regime under
Part IIA of the Environmental Protection Act 1990 (EPA 1990), and others are of a more
generic nature and intended as guidance in a range of contexts. This document is the generic
type and should cover any occasion where guidance on technical issues relating to site
investigation is needed in relation to land contamination. It is a supporting technical
guidance document within the framework of guidance being produced for land
contamination (see below and Figure 1). An outline of where the document fits within this
hierarchy is provided below and in Figure 1.
The Model Procedures for the Management of Contaminated Land (2000 in preparation) have
been developed for the Department of the Environment, Transport and the Regions, and the
Environment Agency. These incorporate existing good technical practice, including the use
of risk assessment and risk management techniques, into a systematic process for making
decisions about and taking appropriate action to deal with contamination. The approach
contained in the Model Procedures is consistent with UK policy and legislative requirements.
Therefore the model procedures set out a recommended good practice approach to managing
land where contamination is, or may be, an issue.
The model procedures are part of a hierarchy of documents that provides a systematic
approach to managing ground and groundwater contamination. The guidance within the
documents increases in complexity and technical detail within each tier of the hierarchy. The
four main tiers are:
1
the process for managing ground and groundwater contamination describing the
overall approach and decision-making process within the UK legislative and policy
frameworks;
primary model procedures that describe the procedural approach for the main
technical activities involved in managing land contamination, namely:
risk assessment;
secondary model procedures that describe the procedural approach for specific
activities that support, or are part of, the three main technical activities covered by the
primary procedures;
4.
supporting technical guidance that describe technical aspects for specific activities
(or sets of activities) that are part of the activities covered by the primary and
secondary procedures.
This document is supporting technical guidance that is expected to be relevant to all parties
involved in the assessment and management of contaminated sites, and in a variety of
contexts. Users should establish a clear understanding of the purpose, context and
requirements of any site investigation before using this guidance.
ii
Figure 1 - Where this document fits in the overall scope of guidance on land contamination
Activity
Desk Study
Preliminary
risk
assessment
Site
investigation
Phase 1B
Hazard assessment
Phase 2
Risk estimation
evaluation
and
Risk
assessment
Remediation
Volume MP2
Evaluation
and
selection of remedial
measures
Volume MP3
Implementation of risk
management measures
Specific technical
guidance areas
Industry profiles
DETR Contaminated Land Report (CLR) Series, Reports CLR 710, dealing with the programme of development of toxicological
data and guideline values for substances in soils (in preparation).
Technical aspects of site investigation Environment Agency
R&D Publication P5-065/TR(this document)
Code of practice: The investigation of potentially contaminated
sites British Standards Institute,BS10175, 2001
Sampling strategies for contaminated land DETR - CLR 4
(1994)
Secondary Model Procedure for the Development of Appropriate
Soil Sampling Strategies for Land Contamination Environment
Agency R&D Technical Report P5-066/TR
Selection of tools for risk assessment of land Environment
Agency R&D Technical ReportP260 (in preparation)
Guidance on the protection of housing on contaminated land Environment Agency R&D Publication 66 (2000)
Communicating understanding of contaminated land risks
SNIFFER Publication SR97(11)F (1999)
Risk assessment:
Human health
Controlled waters
Ecology
Buildings
Engineering options
Methane
Part IIA inspection strategies
Petroleum industry
Methane
Treatment options
Monitoring and verification
Methane
1.
INTRODUCTION
1.1
purchase/sale of land.
1.2
Target audience
those who fall under the regulatory regime and need to understand the Environment
Agencys approach and requirements in relation to the investigation of contaminated
sites; and
The document is intended, primarily, to provide the target audience with the specialist
technical information required when acting in a project management capacity dealing with
investigation of contaminated sites. The variation in the level of existing expertise of the
target audience has been recognised.
The document should also assist in the development of a nationally consistent approach to site
investigation projects in which the Environment Agency is involved by setting out what the
Environment Agency believes to be the key issues relating to good site investigation practice.
In particular, the report serves as a supplement to, and should be used in conjunction with,
other key guidance documents including:
Methodology for the derivation of remedial targets for soil and groundwater to protect
water resources. Environment Agency R&D Publication 20;
1.3
1.4
The information is arranged and presented so that it can easily be drawn upon when using
other relevant guidance. It is split into two volumes:
Volume I
Volume II
Volume I begins with an overview of good practice and further sections describe key issues in
relation to the principal site investigation activities. The different chapters cross-refer to
others within the technical guidance document where relevant. The format adopted aims to
assist the reader in the practical use of the technical information by the strong links between
the text in Volume I and the supplementary material in Volume II.
2.
Tick
Chapter 2
Chapter 4
Chapter 11
Chapter 12
Chapter 11
Chapter 5
Analytical requirements
Chapter 8
Chapters 2&8
Chapter 10
Chapter 4
Costs/budget available?
Not covered
Chapter 4
Site ownership?
Not covered
Consents/permits required?
Chapter 13
Not covered
Chapter 10
Presence of obstructions?
Chapter 9
Chapter 13
Tick
Chapter 12
Ecology
Chapter 12
Archaeology
Chapter 12
Chapter 9
Chapter 2
Not covered
Tick
Exploratory investigations
number
type (boreholes, trial pits, groundwater wells etc.)
dimensions
locations
methods
Sample collection
media type (soils, liquids, gases)
numbers
size and type
locations
depths
storage and handling
In situ and on-site testing
media type
determinand/property
numbers
locations
duration
Laboratory testing
media type
sample preparation
determinand/property
analytical method
Health and Safety
procedures
protective equipment
Environmental protection
air quality
groundwater and surface waters
waste disposal
operating procedures/management systems
Comments
Site records (e.g. drawings, process descriptions, construction records, incident records);
local historical information (e.g. published histories, museums, local history societies);
services drawing (e.g. for gas, electricity, water, telephone, cable, oil pipelines, sewers);
regulatory authorities (e.g. Environment Agency, SEPA, Local Authority, Petroleum Officer);
borehole records;
meteorological information;
tide tables.
Examples
Site location
Address, location plan (with scale and orientation) and OS grid reference
Design/construction modifications
Nature/quantities
handled on site
of
materials
Physical features
Previous history
Geology/hydrogeology/hydrology
Ecological/geological status
Archaeological status
Tick
Comments
Site owner:
Site size (ha)
Grid ref.:
Job reference
Operational/disused/derelict
Visit by:
Position (s):
Visit accompanied by (include position):
Subject
Information obtained
by (date)
10
when completed
operation of a comprehensive health and safety management system and a demonstrable track record;
availability of adequate Professional Indemnity Insurance, Public Liability Insurance and other
insurances.
Scientist / Engineer
Technician
11
2.10 - Audit trails and record keeping - issues on which confidence may be required
Issues
Possible requirement
12
Department of the Environment (1991) Policy Appraisal and the Environment: A Guide for Government
Departments. HMSO.
Department of the Environment (1994) CLR 1. A framework for assessing the impact of contaminated land
on groundwater and surface water. Volumes 1 and 2.
Department of the Environment (1994) CLR 2. Guidance on preliminary site inspection of contaminated
land. Report by Applied Environmental Research Centre Ltd. Volumes 1 and 2.
Department of the Environment (1994) CLR 3. Documentary research on industrial sites. Report by RPS
Group.
Department of the Environment (1994) CLR 4. Sampling strategies for contaminated land. Report by The
Centre for Research into the Built Environment, The Nottingham Trent University.
Department of the Environment (1994) CLR 5. Information systems for land contamination. Report by
Meta Generics Ltd.
13
Department of the Environment (1995) CLR 6. Prioritisation and categorisation procedure for sites which
may be contaminated. Report by M J Carter Associates.
Department of the Environment, Transport and the Regions. CLR 11. Handbook of Model Procedures for the
Management of Contaminated Land. Contaminated Land Research Report (in preparation).
Department of the Environment (1997) CLR 12. A quality approach for contaminated land consultancy.
Report by the Environmental Industries Commission in association with the Laboratory of the Government
Chemist.
Department of the Environment (1994)
(PPG23).
Department of the Environment (1995) Workshop 1. Professional standards, April 1994 (superseded by CLR
12 see below).
Department of the Environment (1995) Guide to Risk Assessment and Risk Management for Environmental
Protection.
Department of the Environment, Transport and the Regions (1998) CLR Research Report. Research into the
Impact of Contaminated Land on the Water Environment. Prepared by Sir William Halcrow & Partners
Ltd.
Department of the Environment, Transport and the Regions (1998) CLR Research Report. Modelling the
Impact of Contaminated Land on Water Quality using the MIKE SHE model. Prepared by WS Atkins
Consultants Ltd.
Department of the Environment, Transport and the Regions (1998) CLR Research Report. International
review of the state of the art in Contaminated Land Treatment Technology Research and a Framework
for Treatment Process Technology Research in the UK. Prepared by The Centre for Research into the Built
Environment, The Nottingham Trent University.
Department of the Environment, Transport and the Regions (1998) CLR Research Report. Active
Containment: Combined Treatment and Containment Systems. Prepared by Golder Associates (UK) Ltd.
Department of the Environment (1995) Workshop 3. Risk assessment and the use of guidelines, July 1994.
Department of the Environment (1996) Industry profile. Profile of miscellaneous industries, incorporating
charcoal works, dry-cleaners, fibreglass resins, glass, photographic processing, printing and bookbinding
works.
Department of the Environment (1996) Industry profile. Waste recycling, treatment and disposal sites:
solvent recovery works.
Department of the Environment (1996) Industry profile. Waste recycling, treatment and disposal sites:
landfills and other waste treatment or waste disposal sites.
Department of the Environment (1996) Industry profile. Waste recycling, treatment and disposal sites:
hazardous waste treatment plants.
Department of the Environment (1996) Industry profile. Waste recycling, treatment and disposal sites: drum
and tank cleaning and recycling plants.
Department of the Environment (1995) Industry profile. Timber products manufacturing works.
14
Department of the Environment (1996) Industry profile. Textile works and dye works.
Department of the Environment (1996) Industry profile. Road vehicle fuelling, service and repair: transport
and haulage centres.
Department of the Environment (1996) Industry profile. Road vehicle fuelling, service and repair: garages
and filling stations.
Department of the Environment (1996) Industry profile. Pulp and paper manufacturing works.
Department of the Environment (1995) Industry profile. Oil refineries and bulk storage of crude oil and
petroleum products.
Department of the Environment (1996) Industry profile. Metal manufacturing, refining and finishing works:
non-ferrous metal works (excluding lead works).
Department of the Environment (1995) Industry profile. Engineering works: vehicle manufacturing works.
Department of the Environment (1996) Industry profile. Engineering works: electrical and electronic
equipment manufacturing works (including works manufacturing equipment containing PCBs).
Department of the Environment (1995) Industry profile. Engineering works: aircraft manufacturing works.
Department of the Environment (1995) Industry profile. Dockyards and dockland.
Department of the Environment (1995) Industry profile. Timber products manufacturing works.
Department of the Environment (1996) Industry profile. Chemical works: mastics, sealants, adhesives and
roofing felt manufacturing works.
Department of the Environment (1995) Industry profile. Chemical works: linoleum, vinyl and bitumenbased floor covering manufacturing works.
Department of the Environment (1996) Industry profile.
manufacturing works.
Chemical works:
inorganic chemicals
Department of the Environment (1996) Industry profile. Chemical works: fertiliser manufacturing works.
Department of the Environment (1995) Industry profile. Chemical works: disinfectants manufacturing
works.
Department of the Environment (1995) Industry profile.
manufacturing works.
Chemical works:
Department of the Environment (1995) Industry profile. Chemical works: coatings (paints and printing inks)
manufacturing works.
Department of the Environment (1996) Industry profile.
works.
15
Department of the Environment (1995) Industry profile. Sewage works and sewage farms.
Department of the Environment (1995) Industry profile. Power stations (excluding nuclear power stations).
Department of the Environment (1995) Industry profile. Metal manufacturing, refining and finishing works:
iron and steelworks.
Department of the Environment (1995) Industry profile. Metal manufacturing, refining and finishing works:
precious metal recovery works.
Department of the Environment (1995) Industry profile. Metal manufacturing, refining and finishing works:
electroplating and other metal finishing works.
Department of the Environment (1995) Industry profile. Engineering works:
shipbreaking (including naval shipyards).
Department of the Environment (1995) Industry profile.
manufacturing works.
Chemical works:
Department of the Environment (1995) Industry profile. Chemical works: organic chemicals manufacturing
works.
Department of the Environment (1995) Industry profile. Chemical works: pesticides manufacturing works.
Department of the Environment (1995) Industry profile. Engineering works: railway engineering works.
Department of the Environment (1995) Industry profile. Railway land.
Department of the Environment (1995) Industry profile. Animal and animal products processing works.
Department of the Environment (1995) Industry profile.
pyrotechnics.
Chemical works:
Department of the Environment (1995) Industry profile. Chemical works: pharmaceuticals manufacturing
works.
Department of the Environment (1995) Industry profile. Chemical works: fine chemicals manufacturing
works.
Department of the Environment (1995) Industry profile. Chemical works:
(including works manufacturing tyres or other rubber products).
Department of the Environment (1995) Industry profile. Engineering works: mechanical engineering and
ordnance works.
Department of the Environment (1995) Industry profile. Gas works, coke works and other coal carbonisation
plants.
Department of the Environment (1995) Industry profile. Asbestos manufacturing works.
Department of the Environment (1995) Industry profile. Metal manufacturing, refining and finishing works:
lead works.
Department of the Environment (1995) Industry profile. Waste recycling, treatment and disposal sites: metal
R&D Technical Report P5-065/TR
16
recycling sites.
Department of the Environment, Transport and the Regions. Potential Contaminants for the Assessment of
Land. Report by Consultants in Environmental Science (in preparation).
Department of the Environment, Transport and the Regions SP99. Guidance on the sale and transfer of land
which may be affected by contamination. Report by Parkman Environment, Andrew Bryce and Co. and
Clifford Chance (in preparation).
Department of the Environment, Transport and the Regions/Environment Agency/NHBC. Guidance for the
Development of Housing on Land affected by Contamination. R&D Publication 66 2000.
Department of the Environment.
Sustainable use of soil. HMSO.
Environment Agency (2000 in preparation) Model Procedures for the Management of Contaminated Land.
Environment Agency. Methodology for the derivation of remedial targets for soil and groundwater to
protect water resources. Environment Agency R&D Publication 20;
Environment Agency. National Sampling Procedures Manual Quality Management System for
Environmental Sampling (internal Environment Agency guidance);
Garston, CRC (1998) Contaminated Land: a review of research at BRE. BRE Report reference number
BR346. Published only on the CD-ROM BRE Reports on CD, number 10 (1998).
Harris, M.R. and Herbert, S.M. (1994) Contaminated land: investigation, assessment and remediation. ICE
Design Guide, Thomas Telford (London).
Health and Safety Executive (1991) Protection of workers and the general public during development of
contaminated land. HS(G)66.
ICRCL 59.83. Guidance on the assessment and redevelopment of contaminated land. 2nd Edition, July
1987.
ISO FDIS 10381-1 Soil quality Part 1 Guidance on the design of sampling programmes.
ISO FDIS 10381-2 Soil quality Part 2 Guidance on sampling techniques.
ISO FDIS 10381-3 Soil quality Part 3 Guidance on safety.
ISO FDIS 10381-4 Soil quality Part 5 Guidance on the procedure for the investigation of soil contamination
of urban and industrial sites.
Paul, V. (1995) Bibliography of Case Studies on Contaminated Land: investigation, remediation and
redevelopment. BRE Report BR291.
British Standard Institution, BS 10175:2001. Code of Practice for the Investigation of Potentially
Contaminated Sites.
Risks of Contaminated Land to Buildings, Building Materials and Services a literature review. Report by
BRE for the Environment Agency, R&D Technical Report P331, 2000.
Scottish Enterprise. How to investigate contaminated land. SE (Glasgow), revised.
17
Uff J F and Clayton C R I. Role and responsibility in site investigation. Special Publication 73. CIRIA, 1991
Warren Spring Laboratory (1994)
remediation. Report LR 1003.
18
3.
19
Site owner:
Contract details
Grid ref.:
Consultant:
Job reference
Principal contractor and sub-contractor(s):
Recorded by:
Position:
Weather:
Time
Activity
Additional comments
by (date)
20
when completed
21
4.
22
trial pits (trial holes, trial trenches, test pits and test holes - hand dug and
mechanically excavated)
rotary coring
down the hole hammer drilling (DTH, DTHH and rotary percussive)
window sampling
In preparing the summary sheets for intrusive methods, the contribution of Chris Jeffries of
Environmental Sampling Ltd is gratefully acknowledged.
Non-intrusive methods
seismic
gravity
electrical
electromagnetic
magnetic
In preparing the summary sheets for non-intrusive methods, the contribution of John Arthur of
Top-hole Site Studies Ltd is gratefully acknowledged.
23
Sequence of events:
an appropriate location (clear of underground services etc) for the trial pit is chosen and a before
photograph may be taken. It may be necessary to protect the ground surface from contaminated arisings
using plastic sheeting, wooden boards etc. and to use sand-bags or other methods to contain water as the pit
is dug;
the excavator driver manoeuvres the excavator into a suitable position for the trial pit location, taking into
account factors such as the position of the sun/other bright lights (good visibility is essential) and wind
direction (in relation to vehicle exhaust fumes, ground gases, odours etc). Any surface concrete/other hard
cover is broken out to a suitable size and the excavator changes from breaker to bucket. As the trial pit is
dug, the scientist/engineer directs the speed/depth of excavation and also maintains a constant look out for
anything that may affect safety of the trial pitting exercise. Under no circumstances should anyone enter a
trial pit;
as the trial pit progresses, the spoil is segregated in such a way that it can be used to backfill the pit in
roughly the same order that it was removed. Photographs, depth measurements and samples are taken as
required (during this time the excavator stands still with the bucket on the ground i.e. hydraulics at rest).
Anyone approaching a trial pit should do so on the short side opposite the excavator and all the time with an
awareness of the pits stability and the surrounding ground conditions. (see section below on practical safety
and environmental protection measures about safe distances for placement of excavated spoil, safe working
near trial pits etc.).
once the desired depth or limit of the machine is reached, final measurements and photographs are taken (the
driver should not be asked to hold the photograph identification board). The trial pit is then backfilled using
the original spoil which is emplaced in roughly the same order to the original (alternatively, clean sand/gravel
may be used). A gas monitoring standpipe may be installed in the trial pit. When backfilling is completed, an
after photograph may be taken;
re-instatement works that are needed are carried out (arrangements for this should be made before starting
the investigation). Irrespective of whether formal re-instatement works are to be carried out, it is important
that the backfilled trial pit and surrounding affected area are left in a safe condition. Open trial pits should
NEVER be left unattended unless securely fenced off (safety issues are covered below).
24
Limitations
Ground instability can cause pit walls to collapse repeatedly so that the excavator ends up merely digging this
material out rather than deepening the pit. This occurs frequently with soil types such as ashy granular made
ground and loose sands/gravels. Groundwater flowing rapidly into the pit through the sides of the pit can
exacerbate unstable conditions.
Compacted or hard layers can be difficult to dig through and it may be necessary for a breaker unit to be used
intermittently.
All trial pits cause considerable ground disturbance and it can be difficult to restore the surface completely.
Depending on the make-up of the groundmass, a slight mounding or dip in the surface will remain. On many
derelict or redevelopment sites this will not matter but on operational sites this may be unacceptable and formal
re-instatement works may be required. These can be expensive and may require the general area to be fenced off
for the surface to settle first. In some parts of operational sites, the disturbance caused by trial pits is wholly
unacceptable e.g. access roads, inside buildings, airport runways, close to rail lines, close to pipe/cable runs.
surface cover conditions the hourly hire rate is greater for an excavator with a breaker unit than for one
without and breaking through concrete is a time consuming activity;
re-instatement requirements;
sampling rate;
need for additional Health & Safety measures and working methods to address hazardous contaminants.
Personnel requirements
Trial pitting should be carried out only by an experienced scientist/engineer, working in partnership with an
experienced excavator operator. On average, around five trial pits to 5 m per day (no surface concrete) should be
achieved per trial pitting team although the precise number will vary according to the factors listed in the section
key cost factors.
Excavators with skilled operators are widely available but the experience of the driver needs to be assured prior to
hire to ensure the success of the trial pitting exercise.
Access to the site and within the site (for a backhoe loader allow 2.7 m width for access through gates and
more for larger machines check with the plant hire company);
overhead clearance (allow 6.5 m for a backhoe loader and more for larger machines);
available working area (allow an area of minimum 15 m X 15 m for a backhoe loader and more for larger
machines);
availability of washdown facilities, with power and freshwater supply, for the excavator bucket that can be
accessed by the excavator;
ability of ground to support weight of plant (a backhoe loader weighs around 9 tonnes while larger machines
can weigh 45 tonnes).
25
26
*temperature and conductivity to examine changes in the groundwater composition with depth and to
identify flow horizons;
calliper (to determine the borehole diameter and the identify presence of fractures);
resistivity (to measure the resistance of the groundwater and the rock);
*natural gamma radiation (to determine the radioactive properties of the rock);
*neutron (to measure the porosity of the rock and the properties of the groundwater);
*gamma gamma radiation (to determine the bulk density of the rock).
If down-hole logging is required, the specific technical requirements of the method (e.g. borehole diameter,
casings etc) should be checked with a geophysics specialist before drilling work is commissioned.
27
Sequence of events:
an appropriate location for the borehole is chosen and a before photograph may be taken. Any surface
concrete is broken or cored through. It may be necessary to protect the ground surface from contaminated
arisings using plastic sheeting, wooden boards etc. and to use sand-bags or other methods to contain water as
the borehole is drilled and arisings extracted;
the general requirements for drilling, sampling, in situ tests and the design of the groundwater/gas monitoring
installation (if needed) etc. are confirmed before the borehole is started. It is usually desirable, however for
some flexibility to be maintained as the borehole is drilled and the conditions emerge;
the rig is positioned over the borehole location by the Drill Supervisor and the appropriate type of lead auger
is fitted and the borehole is started. As the hole deepens and the auger spirals into the ground, the material
being conveyed up the auger helix emerges at the ground surface and is moved clear of the top auger.
Depending on the specific requirements of the project and whether CFA or HSA is the method used, samples
of this conveyed material may be taken although this only permits an approximate depth to be ascribed to the
sample. Alternatively (and only applicable to HSA), a sampler may be inserted down through the hollow stem
to retrieve a soil sample from a specific depth;
as the borehole develops the scientist/engineer liaises with the drilling crew on precise sampling and
groundwater measurement requirements, but stands a safe distance back from and avoids obstructing the
actual drilling process. Anyone approaching the rig, aside from the drilling crew, should do so only after
indicating to the Drilling Supervisor of this intention as it may be necessary to stop the drilling mechanism.
When approaching the rig, this must be done with an awareness of the safety of the rig itself, the equipment
in the vicinity and the condition of the ground surface. All personnel maintain a look out for anything that
may affect the safety of the drilling exercise;
where there is need to construct the borehole in such a way as to protect, for example, an underlying aquifer
the precise design is refined to reflect the emerging conditions;
as the borehole progresses, any retrieved spoil that is not required for samples is either stockpiled temporarily
close to the borehole or placed directly into bags. Whichever method is chosen, the arisings are stored in
such a way that any that are suitable can be used as backfill material at the appropriate time, while those that
are not may be disposed of appropriately;
once the desired depth is reached, final measurements of the depth of the hole and groundwater level are
taken. If a groundwater/gas monitoring installation is required, this is constructed carefully by the drilling
crew and the top of the borehole fitted with an appropriate cover;
Re-instatement works that are needed are carried out (arrangements for this should be made before starting
the investigation). Irrespective of whether formal re-instatement works are to be carried out, it is important
that the borehole and surrounding area are left in a safe condition. Open boreholes and drilling equipment
should not be left unattended unless securely roped, coned or fenced off (safety issues are covered below).
Limitations
It can be time-consuming to re-locate boreholes that have hit shallow obstructions.
Water may need to be added to the borehole to assist in the withdrawal of the lead auger when boring is complete.
this is particularly the case in sandy conditions as sand can lodge and prevent the lead auger being withdrawn.
If samples of conveyed soil are taken from the top of the auger flights, it is difficult to be sure of which depth this
has come from and considerable reliance has to be placed on the skill of the Drill Supervisor. Similarly it is not
always possible to be precise about the intersection between different geological strata.
28
spoil storage/disposal.
Personnel requirements
There are a small number of specialist environmental drilling companies that have developed HSA/CFA rigs for use
in ground contamination investigation.
On average, around 30 m to 50 m per day (no surface concrete) should be achieved by CFA per drilling rig/crew
although the precise meterage will vary according to the factors listed in the section key cost factors. On
average, around 15 m to 20 m per day (no surface concrete) should be achieved by HSA per drilling rig/crew and,
again, the precise meterage will vary according to the key cost factors.
access to and within the site many of these rigs have been specifically designed for environmental
investigation and are much smaller than most other types of rig. Consequently, these are able to be used in
areas that may be inaccessible for other drilling methods (allow 2 m width and 5 m length);
overhead clearance similarly, the mast height tends to be less than for many other rig types (allow 3.5 m for
a rig when the mast is at full height;
available working area (allow an area of minimum 2 m X 6 m for the rig and working area around). Take into
account the fact that the rig may be noisy and generate diesel fumes which may be a problem in areas
confined between buildings, near public walkways etc.;
availability of washdown facilities, with power and freshwater supply, for washing of the augers etc. that can
be accessed by the towing vehicle.
29
30
*temperature and conductivity to examine changes in the groundwater composition with depth and to
identify flow horizons;
calliper (to determine the borehole diameter and the identify presence of fractures);
resistivity (to measure the resistance of the groundwater and the rock);
*natural gamma radiation (to determine the radioactive properties of the rock);
*neutron (to measure the porosity of the rock and the properties of the groundwater);
*gamma gamma radiation (to determine the bulk density of the rock).
If down-hole logging is required, the specific technical requirements of the method (e.g. borehole diameter,
casings etc) should be checked with a geophysics specialist before drilling work is commissioned.
31
Sequence of events:
an appropriate location for the borehole is chosen and a before photograph may be taken. It may be
necessary to protect the ground surface from contaminated arisings using plastic sheeting, wooden boards
etc. and to use sand-bags or other methods to contain water as the borehole is drilled and arisings extracted;
any surface concrete is broken or cored through and a hand-dug starter pit may be required (e.g. to check
that there are no pipes/cables etc at the drilling location). The Drill Supervisor or Second Man manoeuvres
the drilling rig into position and the legs of the mast are locked into position using cross-bars at above head
height. The general requirements for drilling, sampling, in situ tests and the design of the groundwater/gas
monitoring installation (if needed) etc. are confirmed before the borehole is started. It is usually desirable,
however for some flexibility to be maintained as the borehole is drilled and the conditions emerge;
a suitable boring tool is used to cut the start of the borehole and, at a suitable depth (usually less than 1 m),
the first length of casing is established to which others are attached and progressively advanced as the
borehole deepens;
as the borehole develops the scientist/engineer liaises with the drilling crew on precise sampling and
groundwater measurement requirements and any in situ tests that are needed, but stands a safe distance
back from and avoids obstructing the actual drilling process. Anyone approaching the rig, aside from the
drilling crew, should do so only when the cable tools are at rest on the ground and all the time with an
awareness of the safety of the rig itself, the equipment in the vicinity and the condition of the ground surface.
All personnel should maintain a look out for anything that may affect the safety of the drilling exercise;
where there is need to construct the borehole in such a way as to protect, for example, an underlying aquifer
the precise design is refined to reflect the emerging conditions;
as the borehole progresses, any retrieved spoil that is not required for samples is either stockpiled temporarily
close to the borehole or placed directly into bags. Whichever method is chosen, the arisings are stored in
such a way that any that are suitable can be used as backfill material at the appropriate time, while those that
are not, are stored temporarily in a skip on the site and then disposed of appropriately;
once the desired depth is reached, final measurements of the depth of the hole and groundwater level are
taken. If a groundwater/gas monitoring installation is required, this is constructed carefully by the drilling
crew under instruction from the scientist/engineer and the top of the borehole fitted with an appropriate
cover. Re-instatement works that are needed are carried out (arrangements for this should be made before
starting the investigation);
irrespective of whether formal re-instatement works are to be carried out, it is important that the borehole
and surrounding area are left in a safe condition. Open boreholes and drilling equipment should not be left
unattended unless securely roped, coned or fenced off (safety issues are covered below).
Limitations
Not suitable for very small or confined sites.
Considerable quantities of water may need to be added to the borehole during drilling to enable collection of sands
and gravels.
Hard layers can be difficult and take long periods of time to chisel through.
The sections of casing may be of different lengths and these need to be checked as they are inserted if a record of
the depth of casing used (a costed item) is to be kept independently of the Drill Supervisor.
Cable percussive boring can cause a significant amount of mess if the containment of arisings (both solid and
liquid) is not planned for carefully. These can slow down the drilling operations slightly.
32
a wide range of unexpected situations can cause drilling to halt and drillers to go on standing time;
need for additional Health & Safety measures and working methods to address hazardous contaminants.
NB cable percussive drilling is usually charged by the metre with additional costs applied to sampling, in situ
testing, standing time etc. Many cable percussive drillers prefer straightforward drilling into clean ground with
minimal sampling, testing etc. as it is that which gives the greatest financial return. It may be necessary,
sometimes, to slow down the rate of drilling to maintain control over the quality of sampling, measurements
taken etc.
Personnel requirements
Supervision of a cable percussive drilling contractor should be carried out only by an experienced
scientist/engineer that is familiar with this method of drilling and the way cable percussive drilling crews operate.
One such scientist/engineer should be allocated to each rig and should be prepared to carry out or supervise
closely, the majority of the hands on sampling of soils.
A drilling crew should be used that is BDA (British Drilling Association) accredited for cable percussive work, has
experience of working on a wide range of contaminated sites and is prepared to be flexible in terms of responding
to the emerging conditions, sampling requirements, borehole design etc. Many cable percussive drilling crews
prefer clean geotechnical work and it is essential that the nature of the ground conditions and the approach to
safe working is clearly specified at the time of the initial enquiry about availability for hire. There may be a need
to re-state the need for particular personal protective equipment, safe working practices etc. throughout the
duration of an investigation of a contaminated site, particularly where drillers are more familiar with
uncontaminated conditions.
It is important that the supervising scientist/engineer double checks each measurement of borehole depth, gravel
pack, bentonite seals etc.
On average, around 15 m to 20 m per day (no surface concrete) should be achieved per cable percussive drilling
rig/crew although the precise meterage will vary according to the factors listed in the section key cost factors.
Access within the site (for a towed drilling rig allow 2 m width and 12 m length;
available working area (allow an area of minimum 2.5 m X 6 m for the rig and the towing vehicle (usually a
large four-wheel drive vehicle) will also need to have access. A general working area around the rig of is also
desirable). Take into account the fact that the rig will be noisy and generate diesel fumes which may be a
problem in areas confined between buildings, near public walkways etc.;
availability of washdown facilities, with power and freshwater supply, for washing of the casing, boring tools
etc. that can be accessed by the towing vehicle;
33
34
*temperature and conductivity to examine changes in the groundwater composition with depth and to
identify flow horizons;
calliper (to determine the borehole diameter and the identify presence of fractures);
resistivity (to measure the resistance of the groundwater and the rock);
*natural gamma radiation (to determine the radioactive properties of the rock);
*neutron (to measure the porosity of the rock and the properties of the groundwater);
*gamma gamma radiation (to determine the bulk density of the rock).
If down-hole logging is required, the specific technical requirements of the method (e.g. borehole diameter,
casings etc) should be checked with a geophysics specialist before drilling work is commissioned.
35
Sequence of events:
an appropriate location for the borehole is chosen and a before photograph may be taken. Any surface
concrete is broken or cored through. It is virtually impossible to protect the ground surface completely from
contaminated arisings due to the volume of flush water/formation water and arisings that are ejected from the
borehole intermittently (see limitations below). Nevertheless, the use of plastic sheeting, wooden boards
sand-bags or other methods to contain these may reduce the extent of the area that is affected.
if a different drilling method, e.g. cable percussive, is to be used to drill the upper part of the borehole to
avoid causing cross-contamination into an aquifer (see above), this is completed and the rig removed. The
Drill Supervisor or Second Man then manoeuvres the rotary coring rig into position and progresses the
borehole. If only rotary coring is to be used for the whole borehole, the rig is similarly set up from the outset;
the general requirements for drilling, sampling, in situ tests and the design of the groundwater/gas monitoring
installation (if needed) etc. are confirmed before the borehole is started. It is usually desirable, however for
some flexibility to be maintained as the borehole is drilled and the conditions emerge;
drilling commences and, at a suitable depth (usually less than 1 m), the first length of casing is established to
which others are attached and progressively advanced as the borehole deepens;
as the borehole develops the scientist/engineer liaises with the drilling crew on precise sampling and
groundwater measurement requirements and any in situ tests that are needed, but stands a safe distance
back from and avoids obstructing the actual drilling process. Anyone approaching the rig, aside from the
drilling crew, should do so only after indicating to the Drill Supervisor of this intention as it may be necessary
to stop the drilling mechanism. At certain times e.g. when running in/out the drill rods, the Drill Supervisor
will not permit non-drilling personnel to approach. When approaching the rig, this must be done with an
awareness of the safety of the rig itself, the equipment in the vicinity and the condition of the ground surface.
All personnel maintain a look out for anything that may affect the safety of the drilling exercise;
where there is need to construct the borehole in such a way as to protect, for example, an underlying aquifer
the precise design is refined to reflect the emerging conditions;
as the borehole progresses, the core samples will be placed in special core boxes for recording of the depths
that the run came from, logging on site or to be sent for analysis/storage. The fragments of drilled
formation that are flushed out of the deepening borehole gradually form a carpet around the top of the hole.
Any unwanted arisings are disposed of appropriately but the total volume of these arisings is usually relatively
small;
once the desired depth is reached, final measurements of the depth of the hole and groundwater level are
taken. If a groundwater/gas monitoring installation is required, this is constructed carefully by the drilling
crew and the top of the borehole fitted with an appropriate cover;
re-instatement works that are needed are carried out (arrangements for this should be made before starting
the investigation). Irrespective of whether formal re-instatement works are to be carried out, it is important
that the borehole and surrounding area are left in a safe condition. Open boreholes and drilling equipment
should not be left unattended unless securely roped, coned or fenced off (safety issues are covered below).
Limitations
It can be time-consuming to re-locate boreholes that have hit shallow obstructions. However, this drilling method
will probably be capable of drilling through most shallow obstructions.
Flush medium and water may need to be added to the borehole.
Some rotary coring rigs are too big for flexible use on small and/or operational sites.
Rotary coring can generate a great deal of flushed water and arisings when working below the groundwater level
and this is a considerable disadvantage of this drilling method. Even where this is uncontaminated water/slurry,
the general mess that can result, even with use of sandbags, plastic sheeting etc can be unacceptable on many
(e.g. operational) sites. In contaminated conditions, the potential for spreading contaminated water/arisings on
the ground surface may preclude the use of this method.
36
the possible need for an alternative drilling method to be used for the upper section of the borehole and
establish a seal and protect an underlying aquifer;
well design;
need for additional Health & Safety measures and working methods to address hazardous contaminants.
NB rotary coring usually proves to be one of the most expensive drilling methods as rates tend to be higher than
for most other methods, but offers the best recovery of consolidated rock of all systems.
Personnel requirements
Supervision of a rotary core drilling contractor should be carried out only by an experienced scientist/engineer that
is familiar with this method of drilling. One such scientist/engineer should be allocated to each rig.
A drilling crew should be used that has experience of working on a wide range of contaminated sites and is
prepared to be flexible in terms of responding to the emerging conditions, sampling requirements, borehole design
etc. Most rotary coring contractors do exploration or geotechnical work and it is essential that the nature of the
ground conditions and the approach to safe working is clearly specified at the time of the initial enquiry about
availability for hire.
On average, around 15 m to 20 m per day (no surface concrete) should be achieved per rotary core drilling
rig/crew although the precise meterage will vary according to the factors listed in the section key cost factors.
37
Great care needs to be taken when manoeuvring rigs near overhead services, site structures etc and when
excavating in the vicinity of services, near walls, fences, buildings, archaeological remains etc. to avoid damage.
If structures are close by, this can occur some time later if settlement occurs.
Similarly, care needs to be taken to avoid damage to flora and fauna, especially protected species by careful siting
of the borehole, rig and arisings. When working under trees, consider mast height and avoid damaging the
canopy. Considerable harm can be done to trees if knocked by this type of rig, even if damage is not readily
visible at the time.
If unmanageable materials (e.g. unexpected friable asbestos) or unexpected conditions (e.g. gases/strong odours)
are encountered, drilling should be halted, the hole covered with a sheet, board or otherwise and method of
investigation and health and safety arrangements re-appraised.
Once the borehole is completed, the general area must be left safe e.g. disturbed ground should be made good,
any exposed contaminated material covered with clean and surplus arisings need to be properly managed.
38
39
Down-hole geophysical logging can be used to examine the subsurface properties of both the groundwater and the
rock, extending a few or tens of centimetres into the rock matrix. A sonde (instrumental probe) is lowered into
the borehole at a known velocity to produce a log. The following are the down-hole logging techniques most
usually carried out. Some of these (marked with an asterisk) can be used in an installed borehole while others will
be most successful in a clean hole where the formation is unobstructed:
*temperature and conductivity to examine changes in the groundwater composition with depth and to
identify flow horizons;
calliper (to determine the borehole diameter and the identify presence of fractures);
resistivity (to measure the resistance of the groundwater and the rock);
*natural gamma radiation (to determine the radioactive properties of the rock);
*neutron (to measure the porosity of the rock and the properties of the groundwater);
*gamma gamma radiation (to determine the bulk density of the rock).
If down-hole logging is required, the specific technical requirements of the method (e.g. borehole diameter,
casings etc) should be checked with a geophysics specialist before drilling work is commissioned.
Sequence of events
an appropriate location for the borehole is chosen and a before photograph may be taken. Any surface
concrete is broken or cored through. It is virtually impossible to protect the ground surface completely from
contaminated arisings due to the volume of flush water/formation water and arisings that are ejected from the
borehole intermittently. Nevertheless, the use of plastic sheeting, wooden boards sand-bags or other
methods to contain these may reduce the extent of the area that is affected.
if a different drilling method, e.g. cable percussive, is to be used to drill the upper part of the borehole to
avoid causing cross-contamination into an aquifer (see above), this is completed and the rig removed. The
drill team then manoeuvres the rotary coring rig into position and progresses the borehole. If only rotary
coring is to be used for the whole borehole, the rig is similarly set up from the outset;
the general requirements for drilling, sampling, in situ tests and the design of the groundwater/gas monitoring
installation (if needed) etc. are confirmed before the borehole is started. It is usually desirable, however for
some flexibility to be maintained as the borehole is drilled and the conditions emerge;
drilling commences and at a suitable depth it is usual to install a short length of temporary casing to keep the
borehole straight, to prevent collapse, prevent wash-out of material in the upper surface and in the case of
water/mud flush, to help channel the flow for recirculation.
as the borehole deepens, the scientist/engineer liaises with the drilling crew on precise sampling and
groundwater measurement requirements and any in situ tests that are needed, but stands a safe distance
back from and avoids obstructing the actual drilling process. Anyone approaching the rig, aside from the
drilling crew, should do so only after indicating to the Drill Supervisor of this intention as it may be necessary
to stop the drilling mechanism. At certain times e.g. when drilled arisings are being flushed out, the Drill
Supervisor will not permit non-drilling personnel to approach. When approaching the rig, this must be done
with an awareness of the safety of the rig itself, the equipment in the vicinity and the condition of the ground
surface. All personnel maintain a look out for anything that may affect the safety of the drilling exercise;
where there is need to construct the borehole in such a way as to protect, for example, an underlying aquifer
the precise design is refined to reflect the emerging conditions;
as the borehole progresses, the samples will be bagged for inspection on site or to be sent to the laboratory.
The fragments of drilled formation that are flushed out of the deepening borehole gradually form a carpet
around the top of the borehole. Any unwanted arisings are disposed of appropriately;
once the desired depth is reached, final measurements of the depth of the hole and groundwater level are
taken. If a groundwater/gas monitoring installation is required, this is constructed carefully by the drilling
crew and the top of the borehole fitted with an appropriate cover;
re-instatement works that are needed are carried out (arrangements for this should be made before starting the
investigation). Irrespective of whether formal re-instatement works are to be carried out, it is important that the
borehole and surrounding area are left in a safe condition. Open boreholes and drilling equipment should not be
left unattended unless securely roped, coned or fenced off (safety issues are covered below).
40
Limitations
Where the flush returns are constant; samples can be taken from precise depths, however, in all cases the quality
of sample for environmental project is poor. This limits the suitability of this method of drilling when soil sampling
is an objective.
It can be time-consuming to re-locate boreholes that have hit shallow obstructions.
Considerable quantities of flush medium will need to be added to the borehole.
Some rig assemblies may be too big for flexible use on small operational sites.
Rotary drilling can generate a great deal of flushed water and arisings when working below the groundwater level
and this is a considerable disadvantage of this drilling method. Even where this is uncontaminated water/slurry,
the general mess that can result, even with use of sandbags, plastic sheeting etc can be unacceptable on many
(e.g. operational) sites. In contaminated conditions, the potential for spreading contaminated water/arisings on
the ground surface may preclude the use of this method.
the possible need for an alternative drilling method to be used for the upper section of the borehole and
establish a seal and protect an underlying aquifer;
need for additional Health & Safety measures and working methods to address hazardous contaminants.
Personnel requirements
Supervision of a rotary drilling contractor should be carried out only by an experienced scientist/engineer that is
familiar with this method of drilling. One such scientist/engineer should be allocated to each rig.
A drilling crew should be used that has experience of working on a wide range of contaminated sites and is
prepared to be flexible in terms of responding to the emerging conditions, sampling requirements, borehole design
etc. Most contractors do mainly exploratory or geotechnical work and it is essential that the nature of the ground
conditions and the approach to safe working is clearly specified at the time of the initial enquiry about availability
for hire.
The meterage achievable will vary widely (15 m to 100 m per day) according to the factors listed in the section
key cost factors above.
41
42
none. The acronym DTTH or partial acronym DTH are frequently used.
43
Down-hole geophysical logging can be used to examine the subsurface properties of both the groundwater and the
rock, extending a few or tens of centimetres into the rock matrix. A sonde (instrumental probe) is lowered into
the borehole at a known velocity to produce a log. The following are the down-hole logging techniques most
usually carried out. Some of these (marked with an asterisk) can be used in an installed borehole while others will
be most successful in a clean hole where the formation is unobstructed:
*temperature and conductivity to examine changes in the groundwater composition with depth and to
identify flow horizons;
calliper (to determine the borehole diameter and the identify presence of fractures);
resistivity (to measure the resistance of the groundwater and the rock);
*natural gamma radiation (to determine the radioactive properties of the rock);
*neutron (to measure the porosity of the rock and the properties of the groundwater);
*gamma gamma radiation (to determine the bulk density of the rock).
If down-hole logging is required, the specific technical requirements of the method (e.g. borehole diameter,
casings etc) should be checked with a geophysics specialist before drilling work is commissioned.
Sequence of events:
an appropriate location for the borehole is chosen and a before photograph may be taken. Any surface
concrete is broken or cored through. It may be necessary to protect the ground surface from contaminated
arisings using plastic sheeting, wooden boards etc. and to use sand-bags or other methods to contain water as
the borehole is drilled and arisings extracted. Property in the vicinity may also need protecting from the dust
and chippings generated;
the general requirements for drilling, sampling, in situ tests and the design of the groundwater/gas monitoring
installation (if needed) etc. are confirmed before the borehole is started. It is usually desirable, however for
some flexibility to be maintained as the borehole is drilled and the conditions emerge;
the drill team then manoeuvres the auger rig into position, the appropriate type of bit is fitted and the
borehole is started. In uncohesive conditions, a simultaneous casing system will be used;
as the borehole develops the scientist/engineer liaises with the drilling crew on precise sampling and
groundwater measurement requirements and any in situ tests that are needed, but stands a safe distance
back from and avoids obstructing the actual drilling process. Anyone approaching the rig, aside from the
drilling crew, should do so only after indicating to the Drill Supervisor of this intention as it may be necessary
to stop the drilling mechanism. At certain times e.g. when drilled arisings are being flushed out, the Drilling
Supervisor will not permit non-drilling personnel to approach. When approaching the rig, this must be done
with an awareness of the safety of the rig itself, the equipment in the vicinity and the condition of the ground
surface. All personnel maintain a look out for anything that may affect the safety of the drilling exercise;
where there is need to construct the borehole in such a way as to protect, for example, an underlying aquifer
the precise design is refined to reflect the emerging conditions;
as the borehole progresses, the samples will be bagged for inspection on site or to be sent to a laboratory.
The fragments of drilled formation that are flushed out of the deepening borehole gradually form a carpet
around the top of the hole. Any unwanted arisings are disposed of appropriately;
once the desired depth is reached, final measurements of the depth of the hole and groundwater level are
taken. If a groundwater/gas monitoring installation is required, this is constructed carefully by the drilling
crew and the top of the borehole fitted with an appropriate cover;
re-instatement works that are needed are carried out (arrangements for this should be made before starting
the investigation). Irrespective of whether formal re-instatement works are to be carried out, it is important
that the borehole and surrounding area are left in a safe condition. Open boreholes and drilling equipment
should not be left unattended unless securely roped, coned or fenced off (safety issues are covered below).
44
Limitations
DTH is not recommended for ground contamination investigations unless there is no better alternative because soil
samples are of poor quality, it can be difficult to log the horizons and internal lubrication by means of in-line
additives is needed.
DTH is inefficient at drilling through superficial deposits and other unconsolidated formations, unless a
simultaneous casing is used.
Performs poorly in sticky formations (e.g. soft clays) where returns can be poor and clogging can occur.
Requires a large amount of fuel and a powerful compressor.
Requires oils to be used for lubrication.
DTH can drill through most conditions but fill with metal, rubber and paper can be problematic.
DTH can cause a significant amount of mess, particularly air-borne dust in unsaturated rock zones. On many
derelict or redevelopment sites this will not matter but on operational sites this may be unacceptable and
containment measures will needs to be planned carefully. These can slow down the drilling operations slightly.
The compressor needed is powerful and can be particularly noisy. In some situations, vibration can be sufficient to
damage nearby pipes, foundations etc.
need for additional Health & Safety measures and working methods to address hazardous contaminants.
Personnel requirements
The DTH and simultaneous casing system should be commonly available. Rigs tend to be relatively large (see
below) but small rigs may also offer this drilling method.
For ground contamination investigations, daily meterage in the order of 20 m to 80 m would be expected,
depending on the drilling conditions (for exploratory purposes, greater meterage can be achieved).
45
46
none
Sequence of events:
an appropriate location for the window sampler borehole (the borehole) is chosen and a before photograph
may be taken. Any surface concrete is broken or cored through. It is usually unnecessary to protect the
ground surface as the method generates hardly any mess. However, if needed, samplers can be placed on
plastic sheeting during sampling to protect particularly sensitive ground surfaces.
the general requirements for drilling, sampling, in situ tests and the design of the groundwater/gas monitoring
installation (if needed) etc. are confirmed before the borehole is started. It is usually desirable, however for
some flexibility to be maintained as the borehole is drilled and the conditions emerge;
47
the first, and widest, sampler is driven fully into the ground and withdrawn. The next narrower one is pushed
through the open hole to its base and then driven, in turn, into the soil at the bottom. This sequence is
repeated using progressively smaller diameter samplers down to the required depth or limit of the technique
in the particular ground conditions encountered;
as the borehole develops the scientist/engineer liaises with the drilling crew on precise sampling and
groundwater measurement requirements, but avoids obstructing the actual drilling and jacking out processes.
All personnel maintain a look out for anything that may affect the safety of the drilling exercise;
if there is spoil in excess of that needed for sampling/backfilling purposes, this is placed directly into bags and
stored in such a way that they may be disposed of appropriately once the investigation has finished;
once the desired depth is reached, a groundwater/gas monitoring installation is constructed carefully by the
drilling crew (if required) and the top of the borehole fitted with an appropriate cover. If an installation is not
needed, the hole is backfilled with clean suitable material. This can be any spoil in excess of that required for
sampling (if suitable), clean sand/gravel (if appropriate) or bentonite to prevent future downward migration of
contaminants through the hole;
On many sites it is unlikely that any re-instatement works will be needed. If they are (e.g. concrete/tarmac
repair), these are carried out (arrangements for this should be made before starting the investigation). The
borehole and surrounding area must be left in a safe condition. Drilling equipment should not be left
unattended, not least due to its portability (safety issues are covered below).
Limitations
Compacted/hard layers and buried concrete can be difficult to progress through.
The method does not work well in some fill materials that includes large quantities of paper, rubber, wood and
metal.
While some contractors will claim that depths to 20 m can be achieved, this method should really be viewed as one
most successful in shallow depths. In practice, depths of around 5 m are typical with depths of around 8 m to
10 m achievable in only very favourable conditions. At greater depths, the diameter of the samplers will be much
reduced and consequently only small soil samples can be retrieved.
Dense gravels can grip onto the samplers and make extraction difficult.
The method is not suitable in spark-risk situations.
48
distance between sampling locations (equipment can easily be carried but, if the distance between location
exceeds more than about 200 m, it may prove quicker to use a vehicle;
presence of fences/walls/steep inclines/dense vegetation etc. that may inhibit transport of equipment between
locations by hand;
Personnel requirements
There are an increasing number of specialist environmental drilling companies that offer window sampling for
ground contamination investigations.
On average, around 20 m to 30 m per day (no surface concrete) should be achieved (no installations constructed
i.e. all drilled boreholes backfilled). If all boreholes are installed, around 20 m to 25 m per day (no surface
concrete) should be achieved. In both cases, the precise meterage will vary according to the key cost factors.
access to and within the site window sampling is a method that is particularly suited to sites where access is
very constrained and inaccessible for other drilling methods. Essentially, a window sampler borehole can be
drilled if there is space for two people and equipment the size of a small suitcase held initially just above head
height. In exceptionally small spaces, the equipment can be operated by one person but this is not ideal;
overhead clearance - similarly, the overall height of the equipment tends to be less than for many other
drilling methods (allow 2.5 m);
available working area -see notes above (while a borehole can be drilled very small spaces, if possible, allow a
working area of around 2 m by 3 m to accommodate the drilling operations, the samplers on the ground and
ancillary equipment). The hammer unit will generate noise similar to that of lawnmower and this should be
considered when working in locations close to members of the general public;
availability of washdown facilities, with power and freshwater supply, for washing of the samplers etc. (can be
accessed on foot);
knowledge of the location of buried services is essential for the safety of the drilling crew.
49
Care needs to be taken to avoid damage to flora and fauna, especially protected species by careful siting of the
borehole and operational area where samplers etc. are placed. When working under trees, consider the height of
the hammer unit when drilling and avoid damaging the canopy.
If unexpected and unmanageable materials (e.g. friable asbestos) are encountered, drilling should be halted, the
hole covered with a sheet, board or otherwise and method of investigation and health and safety arrangements reappraised.
Once the borehole is completed, the general area must be left safe e.g. the small area of disturbed ground should
be made good.
50
Sequence of events:
an appropriate location for the probehole is chosen and a before photograph may be taken. Any surface
concrete is broken or cored through. It is usually unnecessary to protect the ground surface as the method
generates little mess. However, if needed, samplers and other tools can be placed on plastic sheeting during
sampling to protect particularly sensitive ground surfaces.
the general requirements for drilling, sampling, in situ tests and the design of the groundwater/gas monitoring
installation (if needed) etc. are confirmed before the borehole is started. It is usually desirable, however for
some flexibility to be maintained as work progresses and the conditions emerge;
the vehicle driver manoeuvres the vehicle over the location and unfolds the hammer sampling mast;
as the probehole develops the scientist/engineer liaises with the drilling crew on precise sampling and other
requirements. All personnel maintain a look out for anything that may affect the safety of the drilling
exercise;
if there is spoil in excess of that needed for sampling purposes, this is placed directly into bags and stored in
such a way that it may be disposed of appropriately once the investigation has finished;
once sampling is finished, a groundwater/gas monitoring installation is constructed carefully by the drilling
crew (if required) and the top of the borehole fitted with an appropriate cover. If an installation is not needed,
the hole is backfilled with clean suitable material. This can be any spoil in excess of that required for sampling
(if suitable), clean sand/gravel (if appropriate) or bentonite to prevent future downward migration of
contaminants through the hole;
51
On many sites it is unlikely that any re-instatement works will be needed. If they are (e.g. concrete/tarmac
repair), these are carried out (arrangements for this should be made before starting the investigation). The
borehole and surrounding area must be left in a safe condition. Equipment should not be left unattended
(safety issues are covered below).
Limitations
Compacted/hard layers can be difficult to progress through.
The method does not work well in some fill materials that includes large quantities of paper, rubber, wood and
metal.
While some contractors will claim that depths to 30 m can be achieved, this method should really be viewed as one
most successful in shallow depths. In practice, depths of around 5 m are typical with depths of around 8 m to
10 m achievable in only very favourable conditions.
Dense gravels can grip onto the rods make extraction difficult.
Personnel requirements
There are an increasing number of specialist companies that offer this technique for ground contamination
investigations.
On average, around 7 probe holes to around 6 m per day (no surface concrete and continuous sampling) should be
achieved (no installations constructed i.e. all drilled boreholes backfilled). If all boreholes are installed, around 5
per day (no surface concrete) should be achieved. In both cases, the precise meterage will vary according to the
key cost factors.
access to and within the site this equipment is vehicle-deployed and access requirements will depend on the
size of the vehicle. Generally, allow 2 m width and 5 m length;
overhead clearance - similarly, this will depend on the vehicle deploying the technique. Generally, allow 3 m
the mast at full height;
available working area (allow an area of minimum 2 m X 6 m for the vehicle and a working area around).
Take into account the fact that the equipment may generate fumes which may be a problem in areas confined
between buildings, near public walkways etc;
availability of washdown facilities, with power and freshwater supply, for washing of the equipment that can
be accessed by the vehicle.
52
53
none.
54
Sequence of events:
an appropriate location for the borehole is chosen and a before photograph may be taken. Any surface
concrete is broken or cored through. It is usually unnecessary to protect the ground surface as these methods
generates hardly any mess. However, if needed, samplers can be placed on plastic sheeting during sampling
to protect particularly sensitive ground surfaces. If using a piston sampler to sample sediments in a river,
lagoon etc, an appropriate boat, raft or otherwise will be needed that can be stabilised at the appropriate
location;
the general requirements for drilling, sampling, and the design of any (necessarily shallow) groundwater/gas
monitoring installation needed etc. are confirmed before the borehole is started. It is usually desirable,
however for some flexibility to be maintained as the borehole is drilled and the conditions emerge;
as the borehole develops the scientist/engineer liaises with the drilling crew on precise sampling and
groundwater measurement requirements, but avoids obstructing the actual processes. All personnel maintain
a look out for anything that may affect the safety of the drilling exercise;
it is rare for there to be spoil in excess of that needed for sampling/backfilling purposes but any that is spare
is placed directly into bags and stored in such a way that they may be disposed of appropriately once the
investigation has finished;
once the desired depth is reached, the hole is either backfilled with bentonite/spoil or, in some circumstances,
left to collapse in. Leaving the hole open will only be acceptable if (i) the site conditions are appropriate and
(ii) very small diameter augers have been used. Where a shallow groundwater/gas monitoring installation is
required, this is constructed carefully by the drilling crew and the top of the borehole fitted with an
appropriate cover. It is most unlikely that any spoil in excess of that needed for sampling backfilling will
remain but, if any does, this is bagged and disposed of appropriately;
On many sites, it is unlikely that any re-instatement works will be needed. If they are (e.g. concrete/tarmac
repair), these are carried out (arrangements for this should be made before starting the investigation). The
borehole and surrounding area must be left in a safe condition. Drilling equipment should not be left
unattended, not least due to its portability (safety issues are covered below).
55
Limitations
The method is not suitable for collapsing conditions or coarse gravels.
Many of the hand held tools can be used to only very shallow depths (generally around 1.25 m). The exceptions
are the Piston Sampler (5 m), the Spiral Auger (varies greatly in UK conditions and rarely used) and the Post Hole
Borer (possibly up to 10 m if used in conjunction with a tripod).
With most of the most commonly used hand augers, the diameter of the equipment means that only small
quantities of soil samples can be obtained.
Compacted or hard layers can be difficult to progress through.
Dense gravels can grip onto the equipment in the ground and make extraction difficult.
distance between sampling locations (equipment can easily be carried but, if the distance between location
exceeds more than about 200 m, it may prove quicker to use a vehicle;
presence of fences/walls/steep inclines/dense vegetation etc. that may inhibit transport of equipment between
locations by hand;
sampling requirements.
Personnel requirements
Many contractors offer a range of these hand-operated methods alongside other drilling methods.
The daily meterage that can be achieved with hand augers varies markedly with the ground conditions and
operating context. Between around 20 m to 100 m per day (no surface concrete) could be achieved (no
installations constructed i.e. all drilled boreholes backfilled). If all boreholes are installed, around 10 m m to 30 m
per day (no surface concrete) should be achieved. In both cases, the precise meterage will vary according to the
key cost factors.
access to and within the site these methods are particularly suited to sites where access is very constrained
and inaccessible for other drilling methods. Essentially, a small borehole can be drilled if there is space for
one person and equipment that takes up the space of one other. General access for the vehicle bringing the
equipment to site/general drilling location will also be needed;
overhead clearance similarly overhead clearance is rarely an issue with these methods as equipment is not
generally used above head height);
available working area -see notes above (while a borehole can be drilled in very small spaces, if possible allow
a working area of around 2 m by 3 m to accommodate the drilling operations, the samplers on the ground and
ancillary equipment);
availability of washdown facilities, with power and freshwater supply, for washing of the augers and ancillary
equipment etc. (can be accessed on foot).
56
If unexpected and unmanageable materials (e.g. friable asbestos) are encountered, drilling should be halted, the
hole covered with a sheet, board or otherwise and method of investigation and health and safety arrangements reappraised.
Once the borehole is completed, the general area must be left safe e.g. the small area of disturbed ground should
be made good.
57
Sequence of events
A modelling exercise is ideally carried out offsite as a preliminary stage to determine whether the suspected
feature is theoretically discernible. This enables the limit of detectability to be calculated for a given site.
Models may be simple two dimensional along a profile across the site or a three-dimensional model plotted as
a map of expected gravitational change over an area.
If the modelling exercise indicates that a survey could be successful, a field team is mobilised to conduct a
series of acquisition procedures to ensure that accuracy is achieved in both gravity and topographic
observations over a grid of points (or along a profile or series of profiles). This can be accomplished in an
urban environment, inside or outside buildings, as well as in a brownfield or greenfield site.
The equipment is light and easily transported in a car or van. However if the site is away from levelled tracks
or roads an off-road vehicle should be provided to enable access to the survey area. In remote areas, if data
are to be processed simultaneously with acquisition, a local site hut may be desirable.
It is usual for the Contractor to carry out field work supported by a dedicated assistant working in the local
office carrying out data reduction. Field plots (station location and non-terrain corrected Bouguer anomaly
contour maps and profiles) are produced and are often available for inspection on a daily basis.
Unless existing ground levels are already available to an accuracy of +/-0.01 m, it will be necessary for the
survey team (usually two persons) not only to mark out on the ground (by pegs or biodegradable paint) but
also to undertake a levelling exercise to an accuracy of 0.01 m to obtain corrected heights for each gravity
station. The modelling exercise will have determined what spacing of stations is required; 1 m to 2.5 m grids
are appropriate for environmental type investigations. Approximately 60-80 stations (which includes base
readings and repeats) is achievable each day depending on grid size and accessibility.
58
A model D LaCoste & Romberg Land Gravity Microgal meter has a high precision with readings that can be
repeated to 0.005 mGal (milligal) = 5 Gal. An automated levelling/recording system, the Scintrex CG-3 is
also available. Contractor should demonstrate that gravity meters have been calibrated within the last three
months. Otherwise a calibration will need to be carried out along approved BGS, or an equivalent, calibration
range prior to commencement of survey. Prior to the surveying exercise, the instruments will usually require
a settling period of 24 hours.
For a large area of survey a local gravity base net will be established and tied to National Gravity Reference
Net. Local base stations should not be located within the sphere of cultural effects, these being any manmade object capable of generating and transmitting vibrations to the ground, e.g. dwellings, roads, pylons and
their associated effects. For both base station and field readings it may be necessary to stipulate more than
one reading be taken until repeatability is achieved. Modern instruments can sample tens to 100s of readings
per station to provide a standard deviation within acceptable limits.
All gravity measurements require to be corrected for tidal effects and meter drift. This is accomplished by
making repeat readings throughout the overall period of field observations at a local sub-base station that is
allocated for each day's operations. Readings are made at the local base station before and after each day's
operation and at the sub-base station at 2 hourly intervals throughout the surveying.
Depending on the timing criticality of the survey two meters of the same make may need to be provided to
ensure no break in survey due to meter malfunction. Duplicate readings with both meters should be taken at
the first and last station point to determine comparability of operational meter and spare.
Daily production may be displayed on a simple Bouguer anomaly plot and elevation plot. Together with the
field readings these can be used to identify specific station readings that may be in error or indicate a local
anomaly, although this can prove costly. These readings should be repeated the following day together with
adjacent stations to ensure data will fit in with the set.
Terrain corrections" need to be estimated because the gravity values are also affected by lateral changes in
mass (e.g. local humps and/or hollows). Very local changes should be recorded by the instrument observer.
A digital terrain model based on estimates of mean elevations, with the degree of sensitivity decreasing with
distance, can be used for more distant effects.
Data should be supplied digitally. The data would include station ID, positional information, Bouguer density,
observed gravity value, free air anomaly, terrain correction, the Bouguer gravity anomaly latitude correction,
regional gravity gradient.
Having acquired the data it is necessary to undertake an evaluation of the results in order for example, to
reveal hitherto unknown voids or suspected underground tanks. This work element could be accomplished by
the acquisition contractor or by an alternative specialist. This may be qualitative or quantitative and should
always be followed by careful intrusive investigation to establish ground truth. If such investigation is not
feasible then further modelling exercises may be initiated on each of the perceived discrete anomalies to
estimate the depth to the causative body (or cavity).
59
Limitations
Measurement of such small variations requires a very sensitive instrument. This is therefore sensitive to
microseisms and man-made vibrations that may occur on an active industrial site. If severe these may preclude
measurements being obtainable.
To be effective there needs to be a density contrast between the desired target and host rock/soil or variations in
density within the geological structure within which the target is expected; absence of density contrast means no
gravity anomaly will exist.
If strong local topographic variations are present it may be impracticable to assess the terrain corrections required
to fully correct gravity observations.
ambient vibration - prevalence of microseisms and/or machinery, vehicles, pedestrians, livestock close by.
Personnel requirements
Design, fieldwork and at least initial interpretations are usually best undertaken by a specialist geophysical
contractor/consultant.
A typical geophysics team carrying out a gravity survey will comprise between one and three experienced
personnel carrying out the following activities:
service design -
field measurements -
data processing -
geophysical interpretation -
environmental assessment -
It is not usually necessary for the survey team to be accompanied full time by the commissioning organisation. It
will, however, be necessary for a technical representative from the commissioning organisation, familiar with the
overall aims of the investigation, to be present on the first day and then to maintain contact thereafter.
the presence of unstable ground, such as potential shallow old workings, mine shafts or marshy environment.
the existence of farm stock, which potentially could be hostile or consume/remove pegs.
site may extend across busy highways and railway lines or rivers; adequate precautions should be made to
ensure safety of personnel.
all physical survey markers to be removed on completion of survey (to avoid ingestion by stock).
60
Reynolds, J. M. An Introduction to
Applied
and
Environmental
Geophysics. Wiley
Applied
Geophysics
Code
of
Practice, Ministere de l'Industrie
(SQUALPI) with BRGM, CGG,CGGF
and LCPC, France
61
Sequence of events
Whilst pre-survey modelling exercises can be carried out off-site for the refraction to determine whether the
particular feature is theoretically discernible, it is more usual to undertake an initial trial. This enables the
operating parameters to be established for a given site and provides positive proof of the efficacy, or
otherwise, of the method. Where specific details of the subsurface are known, a simple two dimensional
model along a profile across the site can provide an early view of the potential value of the approach.
It is particularly important that the objectives of the survey are discussed and agreed with the contractor
during the modelling or trial stage. If the modelling exercise or trial indicates that a survey could be successful,
then a full field team may be mobilised to lay out geophones along a profile or series of profiles. Whilst the
method can be utilised in an urban environment, the higher ambient noise levels mean that disused sites are
more likely to produce more noisy data than on greenfield sites.
The recording equipment is light and easily transported in a van. However if the site is away from levelled
tracks or roads an off-road vehicle should be provided to enable access to the survey area. In remote areas, if
data are to be processed simultaneously with acquisition, a local site hut plus computing facilities in airconditioned accommodation would be needed and for ground contamination investigations, post-processing in
an office is normal.
It is usual for the Contractor to carry out field work supported by a dedicated assistant working in the local
office carrying out data reduction for refraction surveys. Reflection data requires a processing unit and, whilst
this can be provided in the field, it is more usual to process data at a processing centre.
62
For a survey of large size it will be necessary to arrange access, wayleaves and permitting in advance to
ensure no hold up to the survey crew. The laying out of geophone spreads, particularly where these are
alongside roads, and the use of seismic sources that are audible to the general public (and which in some cases
can cause ground damage), may require compensation to be paid.
Prior to the geophysical acquisition it will be necessary for the survey team (which may be independent of the
seismic crew), to mark out on the ground (by pegs or biodegradable paint) the positions of the geophones and
seismic source points. Unless existing ground levels are already available, a levelling exercise to obtain
corrected heights for each position will also be required. Permanent reference stations should be established
off the area that may be disturbed during remediation or construction.
Geophone spacing will depend on the specific targets and detail required. 1 m to 5 m separations are
appropriate for shallow environmental type investigations for refraction and spreads usually contain 12 or 24
detectors. Shot positions depend on source strength, likely depth to refractor and ground resolution required.
Shots will be undertaken at both ends of spread and maybe also be within and/or at spread-length distances off
the end of the spread. Approximately 4 to 6 spreads might be achievable each day depending on station
spacing and accessibility.
Contractor should bring to site a range of source types. Shallow refraction targets can be addressed by short
spreads and a sledgehammer. Deeper targets may require a weight drop (which may by accelerated) or a land
airgun. In open country, especially for longer spreads, it may be appropriate to use detonators, a proprietary
shot gun or small explosive charges set in shallow augered holes.
The most appropriate surface energy source should be selected having in mind the objectives of the survey,
access to the survey site, the proximity of dwellings, services, potential sources of noise and safety issues.
Previous examples demonstrating the suitability of the proposed source should be provided.
Reflection spreads are usually longer and may contain up to 120 channels. Geophones may be placed as close
as 1m with receiving positions being selected at the recording unit to avoid or diminish unwanted shot noise or
refracted arrivals at far range.
Where it has been decided to utilise energy sources placed in shot holes it may be necessary to employ a
drilling rig if ground conditions are too hard for hand auger drilling. It is inevitable that some ground
disturbance will be experienced and the air blast may be offensive (and potentially dangerous) to local
residents. Adequate arrangements, approved by the police if necessary, must be made prior to arrival on site
for the supply and storage of explosives and detonators.
Reflection seismic surveys require sufficient experienced personnel to carry out the works in a timely and
efficient manner. Where geophone spreads are left on line overnight security along the line, particularly with
regard to pre-loaded holes, must be maintained and line guards should be provided for this purpose.
A micro-processor based field office processing system using industry standard software may be an efficient
way to keep up with seismic reflection data acquisition for a large survey. An experienced operator familiar
with the basic principles of data processing and use of the system and software will be required. Two tapedrives, fully compatible with the field format to enable copying of field tapes and an electrostatic plotter capable
of quality are integral parts of the system for large high-volume surveys.
The field processing system can be used for producing analytical displays and print-outs, filtered displays of
field records to facilitate rapid assessment of the relationship between shot depth and record quality and
preliminary displays (brute stacks). It may be used not only for assessing the quality of acquired data, but
producing a final record. It can also be used to make copies of field tapes before despatch to main processing
contractor.
Land survey data should be supplied digitally. The data would include station ID, positional information,
geophone and shot location elevations to an agreed datum. Field seismic reflection data will be retained in shot
record form and passed to the field or office based processing centre in digital form. These data will be
reassembled into Constant Mid-Point form through a processing sequence.
Having acquired the data it is necessary to undertake an evaluation of the results in order for example, to
determine the nature of the geology along each 2D section or to build a 3D image. This work element could be
accomplished by the acquisition or processing contractors or more usually by a specialist in seismic
interpretation. This interpretation may be qualitative but more usually is quantitative and should provided
depths to specific horizons of interest to the environmentalist. It should be followed by careful intrusive
investigation to establish ground truth and relate specific sub-surface horizons to events on the seismic record.
63
Limitations
Measurement of acoustic signals requires a quiet environment. The methods are sensitive to microseisms and
man-made vibrations that may occur on an active industrial site. If severe these may preclude measurements
being obtainable.
To be effective there needs to be a contrast in acoustic impedance between the desired target and host rock/soil,
or variations in impedance within the geological structure within which the target is expected. Absence of
impedance contrast means no surface will be detected.
For refraction the soil/rock seismic velocity must increase with depth for a refractor to be identified.
If strong local bedding dips are present it may be impracticable to image the structure.
ambient vibration prevalence of microseisms and/or machinery operating close by, pedestrians, traffic, fast
flowing rivers, surf noise on beaches, trees etc.
64
Personnel requirements
Design, fieldwork and at least initial interpretations are usually best undertaken by a specialist geophysical
contractor/consultant.
A typical geophysics team carrying out a seismic survey will comprise between two (for refraction) and up to four
(for reflection) experienced personnel plus helpers carrying out the following activities:
service design -
one geophysical advisor and, for refraction, access to computing facilities and
modelling software.
field measurements -
one geophysicist (party chief), one instrument operator, one surveyor, one
licensed blaster/source operator, plus a number of geophone installers/
surveying assistants.
data processing -
geophysical interpretation -
environmental assessment -
It is usual for reflection seismic survey teams to be accompanied full time by a technical representative from the
commissioning organisation. He should be familiar with the overall aims of the investigation, present at the
contractor briefing and available on the crew when it mobilises and thereafter. There may also be the need to
supervise the data processing especially if the company is not familiar with environmental/engineering type data.
the presence of unstable ground, such as potential shallow old workings, mine shafts or marshy environment.
the existence of farm stock, which potentially could be hostile or consume/remove pegs.
site may extend across busy highways and railway lines or rivers; adequate precautions should be made to
ensure safety of personnel.
all physical survey markers to be removed on completion of survey (to avoid ingestion by stock);
Reynolds, J. M. An Introduction to
Applied
and
Environmental
Geophysics. Wiley
Applied
Geophysics
Code
of
Practice, Ministere de l'Industrie
(SQUALPI) with BRGM, CGG,CGGF
and LCPC, France
65
Sequence of events
A modelling exercise is optionally carried out offsite as a preliminary stage to determine whether the
suspected feature/s is/are theoretically discernible and which geometrical configuration will be most suitable.
It is also necessary to evaluate the resistivity contrasts. Models may be simple one dimensional at a point or
two dimensional along a profile. In the absence of modelling a field trial is usually undertaken.
If the conditions appear to be satisfactory for using this approach a field team is mobilised to conduct a series
of acquisition procedures at either selected sounding positions, along a profile or series of profiles or over a
grid of points (with base current electrodes in place).
The equipment is light and easily transported in a car or van. However if the site is away from levelled tracks
or roads an off-road vehicle should be provided to enable access to the survey area. In remote areas, if data
is to be processed simultaneously with acquisition, a local site hut may be desirable.
It is usual for the Contractor to carry out field work supported by a dedicated assistant working in the local
office carrying out data reduction. Field plots (station location and non-terrain corrected anomaly contour
maps and profiles) may be produced and are often available for inspection on a daily basis.
Unless existing ground levels are already available, it may be necessary for the survey team (usually a
minimum of two persons) not only to mark out on the ground (by pegs or biodegradable paint) but also to
undertake a levelling exercise to obtain corrected heights for each station.
66
Electrodes can be in the form of steel rods, steel plates with bentonite, tin or aluminium foil or, less
frequently, porous pots. Plates or foil are used when sufficient penetration of a steel rod cannot be achieved
and/or when high contact resistances are experienced. The foil is placed in a hole filled with water or copper
sulphate solution and covered with soil soaked with copper sulphate solution. The current electrodes are
generally but not always placed on the outside of the potential electrodes, although the opposite layout is
theoretically equivalent. NB Galvanic versus capacitative electrode systems.
The most common electrode set-up is the Wenner arrangement. Each potential electrode is separated from
the adjacent current electrode by a distance a which is one-third the separation of the current electrodes. For
depth exploration using the Wenner spread the electrodes are expanded about a fixed centre, increasing the
spacing a in steps. For mapping the spacing remains constant and all four electrodes are moved along the
line. The apparent resistivity for each array position is then plotted using the centre of the spread.
In the Schlumberger configuration, the linear electrode spacing is expanded by increasing the distance
between current electrodes a or that between potential electrodes b, but only one at a time, during the course
of a measurement. The potential electrodes are assumed to be an infinitesimal distance apart, and observed
values of potential are adjusted by extrapolation to fit this assumption. In depth probing the potential
electrodes remain fixed while the current electrode spacing is expanded symmetrically about the centre of the
spread.
Resistivity mapping may be conducted by using a very large fixed separation of the current electrodes (100s
of metres) and the potential pair moved between them, also with a fixed spacing. Apparent resistivity is
plotted at the mid-point of the potential electrodes.
Dipole-dipole arrays are the most expensive of the arrays to run, since all four electrodes are moving along
the line, but have several advantages. The foremost of these is that all four electrodes are in the local area of
the station measured and therefore spurious effects that relate to a distant electrode placement are absent.
The current electrodes are usually well separated from the potential electrodes. Usually the separations a and
b are equal and the distance between the respective pairs is r.
Where deep soundings or widely spaced current electrodes are required (and especially in arid conditions) it
will be necessary to utilise a generator to provide adequate power for the transmitter. In these surveys a
separate receiver may be employed. Smaller surveys in the moist European environment usually use a single
unit.
For traversing, apparent resistivity may be displayed on a lap-top computer to identify lateral changes in the
subsurface for given potential electrode spacings (not necessarily the same depth due to lateral changes in
conductivity). For soundings a curve of increasing apparent resistivity with depth is produced. Where data
show single anomalous values in relation to adjacent readings these may have to be rejected or the particular
reading for that position (any one of the four electrode may have a poor contact) repeated before the data
accepted.
Field data should be supplied digitally. The data would include station ID, positional information, electrode
configuration and apparent resistivity. This data requires processing and analysis in order to assess the true
ground conditions. This work element could be accomplished by the acquisition contractor, but preferably by
an alternative specialist.
Resistivity sounding curves may be interpreted by computer curve matching (there may be more than one
solution). Computer inversion has been developed to enable inversion of Sub-Surface Imaging apparent
resistivity pseudo-sections is now standard.
Evaluation should always be followed by careful intrusive investigation to establish ground truth. If such
investigation is not feasible then further modelling exercises may be initiated on each of the perceived discrete
anomalies to estimate depth and nature of the variations established in the sub-surface or a particular
causative body.
67
Limitations
To be effective there needs to be a resistivity contrast between the desired target and host rock/soil and variations
in resistivity within the geological structure within which the target is expected; absence of contrast means no
detectable anomaly will exist.
Analysis generally assumes a horizontally layered host medium. Extreme lateral variation in ground surface or
subsurface may preclude meaningful soundings being obtainable.
If strong local topographic variations are present current paths may be so complex that the sub-surface structure
may not be resolvable by Sub-Surface Imaging.
Natural or artificial electrical sources may cause interference.
High voltage cables or other buried cables, water mains or metal pipes may locally preclude valid observations.
openness of site (especially for towed arrays) and foot access to areas to be surveyed.
topographic variation and/or density of vegetation.
degree of man-made obstructions present
size of area/number of profiles to be surveyed.
station spacing to achieve useable/interpretable data set and depth penetration.
ambient weather heavy rain or standing water can affect ability to make readings.
degree of analysis and post modelling required.
Personnel requirements
Design, fieldwork and at least initial interpretations are usually best undertaken by a specialist geophysical
contractor/consultant.
A typical geophysics team carrying out a resistivity survey will comprise between one and three experienced
personnel plus helpers carrying out the following activities:
service design -
field measurements -
data processing -
geophysical interpretation -
environmental assessment -
Depending on changes to the field configurations resulting from the initial results that may be required it may be
necessary for the survey team to be accompanied full time by a representative of the commissioning organisation.
In all cases, it is recommended that a technical representative from the commissioning organisation, familiar with
the overall aims of the investigation, is present on the first day and then to maintain contact thereafter.
68
the presence of unstable ground, such as potential shallow old workings, mine shafts or marshy environment.
the existence of farm stock, which potentially could be hostile, consume/remove pegs or be harmed by
contact with live electrodes.
site may extend across busy highways and railway lines or rivers; adequate precautions should be made to
ensure safety of personnel.
the use of a generator for powering a transmitter may mean that there is a danger of electrocution. Caution
is required when working with high power electrical equipment.
Reynolds, J. M. An Introduction to
Applied
and
Environmental
Geophysics. Wiley
Applied
Geophysics
Code
of
Practice, Ministere de l'Industrie
(SQUALPI) with BRGM, CGG,CGGF
and LCPC, France
69
Sequence of events
A modelling exercise may be carried out off-site as a preliminary stage to determine whether the suspected
feature with a particular magnetic susceptibility is theoretically discernible. This enables the limit of
detectability to be calculated for a given site. Models may be simple two dimensional along a profile across
the site or a three-dimensional model plotted as a map of expected magnetic change over an area.
If the modelling exercise indicates that a survey could be successful, a field team is mobilised to acquire over
a grid of points (or along a profile or series of profiles). This can be accomplished in an urban environment, as
well as in a brownfield or greenfield site.
The equipment is light and easily transported in a car or van. However if the site is away from levelled tracks
or roads an off-road vehicle should be provided to enable access to the survey area.
It is usual for the Contractor to carry out field work supported by a dedicated assistant working in the local
office carrying out data reduction. Field plots (station location and non-terrain corrected anomaly contour
maps and profiles) are produced and are often available for inspection on a daily basis.
It is not usually necessary for the survey team to undertake a levelling exercise as the surveys are generally
only concerned with the position of subsurface features. If an automatic positioning system is being used
there may also be no need to mark out stations on the ground (by non-magnetic pegs or biodegradable paint)
although some form of visual location will be required. Survey observations may be as close as 0.25 m on
lines at 1m interval and 40,000 readings can be accomplished in a day for such archaeological survey
coverage with an auto-recording system depending on grid size and accessibility. 1 m to 2.5 m grids are
appropriate for environmental type investigations.
Various types of magnetometer are available, the earlier Fluxgate and Caesium vapour (10 readings/sec)
being most usual for environmental and archaeological work. For detail surveys it is usual to use two units,
one above the other, to measure the vertical gradient. In this case no base readings are required as the
gradient is independent of diurnal variation.
70
For a large area of survey where total field is being recorded a local base station should be established. This
should be located away from magnetic targets or magnetic noise (e.g. pylons) and where the local field
gradient is relatively flat. As the survey progresses the base station is re-occupied every 30 or 45 minutes to
compile a diurnal curve for later correction of field readings against time of observation. Alternatively a
separate continuous recording unit may be installed on the base station.
Daily production may be displayed on a simple anomaly plot and used to identify specific station readings
which may be in error or indicate a local anomaly. These readings should be repeated the following day
together with adjacent stations to check that data will fit in with the set.
Terrain corrections" may need to be estimated when the ground over which the survey is conducted is both
magnetically and topographically rough. If the rough terrain is made up largely of low-susceptibility
sedimentary rocks there will be little or no distortion of the earths magnetic field.
Field data should be supplied digitally. The data would include station ID, positional information, total
magnetic field for each given sensor and magnetic gradient. Data may require processing in order to remove
high frequency noise and remove diurnal variation.
Results should be evaluated to identify features of potential concern. This could either be accomplished by the
acquisition contractor or, preferably, by an alternative specialist. This may be qualitative or quantitative and
should always be followed by careful intrusive investigation to establish ground truth. If such investigation is not
feasible then further modelling exercises may be initiated on each of the perceived discrete anomalies to estimate
the depth to the causative body. The intensity and direction of any permanent (natural remanent) magnetisation
will affect the validity of the model which is produced.
Limitations
Measurements are not possible during periods of intense sunspot activity when magnetic storms occur.
Due to the sensitivity to all ferro-metallic objects, on brownfield sites it will be necessary to set the sensor at a
suitable height above ground to limit sensitivity to likely noise.
High voltage cables, fences, armouring or proximity to metal framed buildings with their attendant magnetic fields
may preclude meaningful measurements being obtainable.
To be effective there needs to be a magnetic susceptibility contrast between the desired target and host rock/soil
or variations within the geological structure within which the target is expected.
Absence of magnetic
susceptibility contrast may mean no anomaly will exist unless a specific target has its own remnant magnetism.
If strong local topographic variations are present and sub-surface is highly magnetic it may be impracticable to
assess the terrain corrections required to fully correct the observations.
71
Personnel Requirements
Design, fieldwork and at least initial interpretations are usually best undertaken by a specialist geophysical
contractor/consultant.
A typical geophysics team carrying out a magnetic survey will comprise between one and three experienced
personnel carrying out the following activities:
service design -
field measurements -
data processing -
geophysical interpretation -
environmental assessment -
It is not usually necessary for the survey team to be accompanied full time by the commissioning organisation. It
will, however, be necessary for a technical representative from the commissioning organisation, familiar with the
overall aims of the investigation, to be present on the first day and then to maintain contact thereafter.
the presence of unstable ground, such as potential shallow old workings, mine shafts or marshy environment.
the existence of farm stock, which potentially could be hostile or consume/remove pegs.
site may extend across busy highways and railway lines or rivers; adequate precautions should be made to
ensure safety of personnel.
all physical survey markers to be removed on completion of survey (to avoid ingestion by stock).
tale care to avoid high sensor rods from touching overhead cables.
72
Reynolds, J. M. An Introduction to
Applied
and
Environmental
Geophysics. Wiley
Applied
Geophysics
Code
of
Practice, Ministere de l'Industrie
(SQUALPI) with BRGM, CGG,CGGF
and LCPC, France
73
Sequence of events
There are many manufacturers of radar equipment addressing different technical situations. Likewise there
has been a growth in companies offering ground radar surveys. The technology is advanced but because the
equipment can be hired easily and operated with only minimal training/understanding of the technique, the
quality of the results may not be high. To obtain appropriate results and for a full understanding of
constraints in the use of the technology it is wise to check the experience of the operator before engaging a
companys services.
Whilst modelling is not undertaken as a preliminary stage it is necessary to consider whether the site and
targets are amenable to investigation/location by GPR. In particular, if clay is present to any degree or if the
groundwater is likely to be conductive and at a shallow level then the chance of reasonable penetration is
slight. A small trial in selected parts of the site is recommended before the main acquisition commences.
If the trial indicates that a survey could be successful, a field team is mobilised to conduct a series of profiles.
This can be accomplished in an urban environment, inside or outside buildings, as well as in a brownfield or
greenfield site. An early decision is required as to which frequency of transmitter is to be used. This will
determine not only likely penetration but also degree of resolution.
The equipment is light and easily transported in a car or van. However if the site is away from levelled tracks
or roads an off-road vehicle should be provided to enable access to the survey area. In remote areas, if data
is to be processed simultaneously with acquisition, a local site hut may be desirable.
74
Aside from field work, it is usual for the Contractor to provide draft data presentation (without elevations).
Processing of data will be required post-acquisition to improve the data quality, insert the elevation data and
produce a useable section.
Unless existing ground levels are already available, it will be necessary for the survey team, not only to mark
out way points on the ground (by pegs or biodegradable paint), but also to undertake a levelling exercise to
obtain corrected heights along each traverse. This will enable the data to be height corrected to remove the
ground variation distortion on final records.
For a large area of survey several units may be operated simultaneously. In these circumstances, although
the data may be recorded digitally enabling subsequent playback at modified outputs, it is recommended that
a uniform presentation style be adopted enabling field records to be directly compared and interpreted.
Signal transmission can usually be triggered at set distance or at regular time intervals Whilst the latter is
acceptable for reconnaissance in open, smooth sites, the former is preferred as the horizontal scale of printed
records is then uniform. The antennae are usually dragged or wheeled along a survey line with reference
marks being inserted by the operator, if necessary, for future correlation with site features. Record length is
set to encompass the depth to which reflections are achievable and the detail required.
Whilst units which combine transmitter and receiver antennae are preferable for profiling work there are also
systems which operate with separate units. These provide the opportunity to undertake wide angle reflection
and refraction (WARR) measurements that can be used in areas of flat lying reflectors to measure the velocity
of the electromagnetic wave. This information is needed to convert the time section to depth and should be
obtained at discrete points within a survey where changes in sub-structure have been observed.
Problems may be experienced in transmitting the signal into the ground in local parts of the site. A decision
will have to be made as to whether a change in antenna or acquisition parameters will improve this or whether
the survey will have to be abandoned. Where a change is dictated then readings should be repeated over the
original section for comparison and subsequent analysis.
Where data quality is good and reasonable penetration is obtainable, it is possible to operate ground radar in a
Common Mid-Point mode using multiple channels, as with reflection seismic. This should only be attempted
by a skilled geophysical team, as the geometry needs to be fully understood. The methodology has now been
extended to acquire three-dimensional data sets for full site assessment.
Data should be supplied digitally. The data would ideally include station ID, positional information and the
radar data. Data can be processed using specialist GPR processing software or using standard seismic
reflection processing software.
Having acquired the data it is necessary to undertake an evaluation of the results in order for example, to
reveal hitherto unknown voids or suspected underground contamination. This work element could be
accomplished by the acquisition contractor or by an alternative specialist. This may be qualitative or
quantitative and should always be followed by careful intrusive investigation to establish ground truth.
75
Limitations
The presence of clay or any other electrically conducting medium will severely preclude the recovery of useful
data. Metallic screen at ground level or close re-bars in concrete may prevent penetration, depending on antennae
frequencies.
Transmitters and receivers have limited directivity and therefore signals that are recovered out of the plane of the
intended section (overhead gantries, adjacent walls) may cause severe interference and subsequent problems in
interpretation. In constricted areas, shielded antennae should be used.
Multiple reflections between subsurface layers and interaction between the antennae and the immediate above
surface environment may produce ringing or an overlong pulse which obscures the required detail.
To be effective there needs to be a permitivity contrast between the desired target and host rock/soil or variations
in permittivity within the geological structure in which the target is expected. Absence of contrast means the
structure will not be resolved.
If strong local topographic variations are present along the survey line it may essential to input the elevations
before any attempt is made to interpret the data.
Personnel requirements
Design, fieldwork and at least initial interpretations are usually best undertaken by a specialist geophysical
contractor/consultant.
A typical geophysics team carrying out a GPR survey will comprise between one and three experienced personnel
carrying out the following activities:
service design -
field measurements -
data processing -
geophysical interpretation -
environmental assessment -
simultaneously
It may not be necessary for the survey team to be accompanied full time by the commissioning organisation. It
will, however, be necessary for a technical representative from the commissioning organisation, familiar with the
overall aims of the investigation, to be present at the trial and on the first day of full survey and then to maintain
contact and view records regularly thereafter.
76
the presence of unstable ground, such as potential shallow old workings, mine shafts or marshy environment.
the existence of farm stock, which potentially could be hostile or consume/remove pegs.
when working within buildings the stability of the structure should be assessed.
site may extend across busy highways and railway lines or rivers; adequate precautions should be made to
ensure safety of personnel.
all physical survey markers to be removed on completion of survey (to avoid ingestion by stock).
Reynolds, J. M. An Introduction to
Applied
and
Environmental
Geophysics. Wiley
Applied
Geophysics
Code
of
Practice, Ministere de l'Industrie
(SQUALPI) with BRGM, CGG,CGGF
and LCPC, France
77
Sequence of events:
For certain of the methods a modelling exercise may be optionally carried out offsite as a preliminary stage to
determine whether the suspected feature is theoretically discernible. This enables the limit of detectability to
be calculated for a given feature at a particular site. Models may be simple two dimensional along a profile
across the site or a three dimensional model plotted as a map of expected values over an area.
If the modelling exercise indicates that a survey could be successful, a field team is mobilised to conduct a
series of acquisition procedures as indicated below using one or a number of differing approaches to ensure
that sufficient data is acquired over a grid of points, along profiles or at a sounding location. In certain
circumstances this can be accomplished in an urban environment, as well as in a brownfield or greenfield site.
The equipment is light and easily transported in a car or van. However if the site is away from levelled tracks
or roads an off-road vehicle should be provided to enable access to the survey area. In remote areas, if data
is to be processed simultaneously with acquisition, a local site hut may be desirable.
It is usual for the Contractor to carry out field work supported by a dedicated assistant working in the local
office carrying out data reduction. Computations for some of the sounding methods are complex and require
considerable computer time to produce an acceptable depth (inversion) result.
It will not usually be necessary for the survey team to undertake a levelling exercise although it should be
noted that VLF measurements can be adversely affected by topography. However the survey grid will need to
be marked out on the ground (by non-magnetic pegs or biodegradable paint). Specific requirements will
depend on the method adopted.
78
For a time-domain sounding a large direct current is passed through a large ungrounded loop transmitter for a
period of 20 to 40 milliseconds. The applied current is then terminated and the presence of any surface currents
induced in the ground recorded by the transient voltage in the same or a separate loop at discrete time
intervals. As the surface currents dissipate a decreasing magnetic field is experienced and the resulting
decaying voltage is recorded. This is repeated many times at a given location with all the data being logged
automatically. Various types of time-decay plots are used to characterise the resulting sounding data for
environmental purposes using PC software. Up to 50 soundings of 25 50 m depth with high vertical resolution
can be achieved per day for environmental purposes.
Profiling surveys are accomplished with the time-domain approach by establishing a large ungrounded
transmitter loop with the long axis parallel to any geological strike. A small receiver coil is moved along
transects perpendicular to the long axis of the transmitter to obtain profiles of the measured parameters as a
function of distance. Data can be plotted as profiles or a grid developed utilising a loop size appropriate to the
depth being investigated.
The use of Very Low Frequency (VLF) military transmitters around the world for the reconnaissance of near
surface effects has been established for many years. The transmitters propagate powerful horizontal plane EM
waves which are modified by local conducting ground conditions that can therefore be specially mapped. Survey
profiles are conducted along the line of the magnetic vector for a given transmitter (of which there are currently
eleven); two orthogonal electric and magnetic sensors are used to measure the electrical (R) and magnetic (EM)
components which relate to the near-sub-surface site conditions (approximately 2 5 m).
The magneto-telluric (MT) method uses measurements of both the electric and magnetic components of the
natural time-variant fields generated as a consequence of the presence and fluctuation of the earths
magnetosphere. Natural-source MT method uses 0.001 to 19Hz frequencies, audio-frequency systems (AMT)
operate within 10Hz to 10kHz. A controlled-source system (CSAMT) operating from 0.1 to 10kHz has recently
been developed for geotechnical and environmental investigations. A loop or grounded dipole is used as a
transmitter off site with two orthogonal electric and three orthogonal magnetic sensors to measure the
horizontal electrical and total magnetic components and build sounding curves to depths of the order of 300 m.
Depending on the requirements of the survey it may be necessary to use two differing EM units. These will
need calibrating against each other to ensure that data can be merged from both units. Duplicate readings with
both should be taken on selected stations to determine comparability of systems at the same coil spacing.
Data should be supplied digitally. The data would include station ID, positional information, observed values
and topography (if recorded).
Having acquired the data it is necessary to undertake an evaluation of the results. This work element could be
accomplished by the acquisition contractor or by an alternative specialist.
This may be qualitative or
quantitative and should always be followed by careful intrusive investigation to establish ground truth. If such
investigation is not feasible then further modelling exercises may be initiated on each of the perceived discrete
anomalies to estimate the depth to the causative body (or cavity).
79
Limitations
Ambient electrical noise from AC power cables and VLF transmitters
Live electrical cables that produce a signal at a specific frequency that may be removable.
Static cultural noise from pipes (if these are not the target), metal fences or other utilities.
Existence of metal structures above, around or beneath the ground (other than target)
In open environments wind may cause motion of magnetic field sensors within earths magnetic field.
Natural geomagnetic signals may cause interference at low frequencies (less than 1Hz); distant lightning discharges
produce sferics which interfere in the 6-10Hz band.
To be effective there needs to be a conductivity contrast between the desired target and host rock/soil or variations
in density within the geological structure within which the target is expected; absence of conductivity contrast
means no anomaly will exist.
If strong local topographic variations exist or the host sub-surface geology is not near horizontal, it may be
impossible to assess the effect or model the sounding to produce a reasonable interpretation.
ambient weather excessive rain can affect ability to make readings as many instruments are not weatherproof.
Personnel requirements
Design, fieldwork and at least initial interpretations are usually best undertaken by a specialist geophysical
contractor/consultant.
A typical geophysics team carrying out an electromagnetic survey will comprise between one and three experienced
personnel plus helpers carrying out the following activities:
service design -
field measurements -
data processing -
geophysical interpretation -
environmental assessment -
Depending on changes which may be required to the field configurations resulting from the initial results it may be
necessary for the survey team to be accompanied full time by the commissioning organisation. In all cases it is
recommended that a technical representative from the commissioning organisation, familiar with the overall aims of
the investigation, is present on the first day and then to maintain contact thereafter.
80
the presence of unstable ground, such as potential shallow old workings, mine shafts or marshy environment.
the existence of farm stock, which potentially could be hostile or consume/remove pegs.
when working within buildings the stability of the structure should be assessed.
site may extend across busy highways and railway lines or rivers; adequate precautions should be made to
ensure safety of personnel.
all physical survey markers to be removed on completion of survey (to avoid ingestion by stock).
the use of a generator for powering a transmitter may mean that there is a danger of electrocution. caution is
required when working with high power electrical equipment.
Reynolds, J. M. An Introduction to
Applied
and
Environmental
Geophysics. Wiley
Applied
Geophysics
Code
of
Practice, Ministere de l'Industrie
(SQUALPI) with BRGM, CGG,CGGF
and LCPC, France
81
trial pits
Plate 1 - trial pits can be hand dug, but the usual method is to use hired
mechanical plant with a skilled operator. Plate 1 shows a backactor excavator
with an extendable arm capable of digging to around 5 m.
Plate 2 shows a slew boom excavator capable of greater depth, power and
manoeuvrability.
Note The utmost care should be taken by personnel working alongside trial pits as the forces operating on the sides of a
gradually deepening pit as spoil is piled above are immense and collapse can be sudden and catastrophic. In both of the cases
shown in Plates 1 and 2, the surface concrete and ground conditions were such that it was safe to approach the trial pit sides.
82
Plate 3
Plates 3 and 4 show cable
percussive (shell and auger) rigs
with casings and associated
materials.
Plate 4
83
drilling techniques
Plates 5 and 6 show large rigs
employing rotary coring
together with associated plant
needed for their operation.
These rigs can usually also
offer rotary drilling and down
the hole hammer techniques.
They can also sometimes offer
auger drilling techniques,
depending on their precise
design.
Plate 5
Plate 6
84
Plate 7 shows a small rig using a combination of hollow stem auger (HSA) and
continuous flight auger (CFA) techniques. Both CFA and HSA augers lie on the
ground nearby (CFA in operation).
Plate 8 shows CFA in operation and Plate 9 shows HSA in operation. These
small rigs can sometimes also offer rotary coring, rotary drilling and down the
hole hammer techniques, depending on their precise design.
85
drilling techniques
86
Intrusive methods
Rotary coring
Rotary drilling
CFA
HSA
Window sampling
Probing
Unconsolidated gravels
Medium sedimentary
Unconsolidated sands
87
Cable percussive
boreholes
Trial pits
Soil/Rock conditions
instructions for using this table (see also Text Supplement 4.4 Worked example)
1 identify the site specific soil/rock conditions and the most appropriate intrusive methods;
2 identify any site specific special situations and the most appropriate intrusive methods;
3 identify any site specific operational issues and the most appropriate intrusive methods;
4 discuss your specific requirements with your chosen drilling contractor(s);
5 if no suitable methods remain, consider using non-intrusive methods (see Chapter 4 of Volume I) or modify the
investigation design (e.g. avoid penetrating through an aquiclude or move boreholes away from areas where overhead
clearance is restricted).
Intrusive methods
Rotary coring
Rotary drilling
CFA
HSA
Window sampling
Probing
Archaeological features
Special situations
Site
specific
note that it may be necessary to use two drilling techniques in combination and also to use robust bentonite seals between horizons.
88
Cable percussive
boreholes
Trial pits
instructions for using this table (see also Text Supplement 4.4 Worked example)
1 identify the site specific soil/rock conditions and the most appropriate intrusive methods;
2 identify any site specific special situations and the most appropriate intrusive methods;
3 identify any site specific operational issues and the most appropriate intrusive methods;
4 discuss your specific requirements with your chosen drilling contractor(s);
5 if no suitable methods remain, consider using non-intrusive methods (see Chapter 4 of Volume I) or modify the
investigation design (e.g. avoid penetrating through an aquiclude or move boreholes away from areas where overhead
clearance is restricted).
Intrusive methods
Cable percussive
boreholes
Rotary coring
Rotary drilling
CFA
HSA
Window sampling
Probing
89
Trial pits
Identify the site specific soil/rock conditions and the most appropriate intrusive methods;
Made ground = reworked clay and PFA. Natural ground = sandy clay overlying clay bedrock. The most
suitable methods = Trial Pits, Cable Percussive, HSA, Window Sampling and Probing. Unsuitable methods =
Rotary Drilling and Down the Hole Hammer.
Identify any site specific special situations and the most appropriate intrusive methods;
Drilling into ground containing asbestos. A number of methods may have been suitable, depending on the
working methods adopted. Trial Pitting was identified as an unsuitable method.
Identify any site specific operational issues and the most appropriate intrusive methods;
Access constraints (buildings, tanks), locations next to buildings, members of the general public in the vicinity of
investigation locations and vehicles needing to pass over the finished installations. The most suitable methods =
window sampling and hand auger/associated methods.
The project manager discussed the site context, ground conditions and technical objectives of the site
investigation with a drilling contractor, who suggested that, of his two suggested methods (window sampling
and hand augering) hand-deployed window sampling be used. The contractor advised that hand auger methods
would not achieve the required depth.
The contractor estimated that it would take one long day to complete the seven installations, together with
breaking out of concrete at nearly all of these which was scheduled to be completed first (using hand-held
equipment), before workers arrived at the industrial unit in the morning. In addition, as the method was quick,
it was planned that the two boreholes close to offices would be completed during the workers lunch break. As
the diameter of the largest samplers was only 50 mm, the amount of surface concrete broken out was minimal
and stop-cock type covers with neat concrete repair established flush with ground level were chosen as these
would not obstruct vehicle movements.
The detailed method statement included for safe investigation in those areas where small amounts of asbestos
insulation were expected in the fill.
90
Have the permitted site working hours been agreed with the site?
Can a key to the site gate be held by site investigation personnel and
if so, who will be responsible for this and its safe return?
Will the site contact need/wish there to be an inaugural site meeting
and what will be the impact on the intended organisation of the parties
involved?
Can the site provide a secure and suitable office and storage area for
use by site investigation personnel and can a refrigerator be used
temporarily in this for the storage of samples (if needed)?
Can the site provide an appropriate washdown area for equipment
together with nearby power and clean water supplies?
Are site skips appropriate for waste arisings from the site
investigation and if not, where can site investigation skips be stored?
Will the client and/or site contact need a set of borehole keys?
Will the client and/or site contact wish to inspect the site investigation
locations and condition of the working areas after the work has
finished?
What needs to be done to comply with the requirements of CDM,
COSHH and other Health and Safety legislation?
Who needs copies of contact names and telephone numbers etc for
parties involved in the investigation?
91
Comments
92
Comments
What special storage facilities are needed for samples to maintain the
correct temperature, security etc)?
Will any cover/reinstatement materials (e.g. gravel, sand, scalpings
etc) be needed, when should they arrive on site and where should they
be stored?
Will any ropes, cones, barriers, warning signs be needed?
Will any couriers that are needed to collect samples for delivery to the
lab need to be booked provisionally?
What referencing system will be used for the investigation locations
and samples?
Will any photographs need to be taken during the investigation (e.g.
general ones of the site, before and after ones at investigation
locations etc)?
If the site is near to surface water features, will the level of these need
to be recorded?
What other on-site measurements will be needed?
What arrangements will need to be made for
skips/portacabins/equipment etc to be collected after the site
investigation is finished?
93
Comments
Rapid
Driscol, F. G. (1986) Groundwater and Wells. Second Edition. Johnston Division, Minnesota.
Environment Agency R&D Project P2-178. Review of Non-intrusive Groundwater Investigation Techniques
for Groundwater Pollution Studies (in preparation).
Environment Agency R&D Project record P5-044. Guidance on Monitoring the Operational and Postremediation Performance of Remedial Techniques (in preparation)
Environment Agency (1988) Review of LNAPL Monitoring Techniques in Groundwater. R&D Project
Record P2/080/1/M.
Guidance Document for Combined Geoenvironmental and Geotechnical Investigation. AGS 2000.
Idel, K.H., Muhs, H., and Von Soos, P. (1969) Proposals for quality classes in soil sampling and the importance
of boring methods and sampling equipment. In: Soil Mechanics and Foundation Engineering, Mexico,
Speciality Session No 1. Rotterdam: Balkema.
Ministere de l'Industrie (SQUALPI). Applied Geophysics Code of Practice. With BRGM, CGG,CGGF and
LCPC, France.
Nielson, D.M. (1991) Editor. Practical Handbook of Groundwater Monitoring. Lewis Publishers, Michigan,
USA (Chapters 6 and 7).
British Standard Institution, BS 10175:2001. Code of Practice for the Investigation of Potentially
Contaminated Sites.
Reynolds, J.M. An Introduction to Applied and Environmental Geophysics.
Site Investigation Steering Group (1993) Guidance for the Safe Investigation by Drilling of Landfills and
Contaminated Land. Thomas Telford, London.
Telford, Geldart, Sheriff and Keys. Applied Geophysics.
USEP (1991) Handbook of Suggested Practices for the Design and Installation of Ground-Water
Monitoring Wells EPA1600 14-89 1034 (available on the Internet: http://www.epa.gov/swerust1/
at/wwelldct.pdf last accessed August 2000).
94
5.
SAMPLING
5.1 - Checklist of major issues to be considered in preparation for and when sampling
5.2 - Labelling samples information needed
5.3 - Type and amount of samples (Table A5 from Environment Agency R&D Technical
Report Number P5-066/TR Secondary Model Procedures for the Development of
Appropriate Soil Sampling Strategies)
5.4 - Field techniques used in soil sampling (Table A7 from Environment Agency R&D
Technical Report Number P5-066/TR Secondary Model Procedure for the Development
of Appropriate Soil Sampling Strategies)
5.5 - Sample chain of custody record
5.6 - Further reading
95
5.1 - Checklist of major issues to be considered in preparation for and when sampling
This checklist uses the simple example of a site on which two pollutant linkages have been identified, namely
leakage from an underground petrol tank and known disposal of lead catalyst waste.
Issues
Tick
preliminary/exploratory/main/validation?
e.g.
location?
Issues
Tick
97
any laboratory reference (often pre-printed onto labels provided by the laboratory);
site name/location;
name of company taking the sample and possibly also the name of the person taking
the sample;
sample depth.
Note:
A sample may be made up of several different bottles/pots etc and the same information needs
to be included on each.
Labelling must comply with legislative requirements e.g. the:
98
Type of sample
Typical application
Amount of sample
For
head-space
testing
of
volatile/semi-volatile substances in
the field (indicative only)
Approximately 1 kg
U100
sample
Chemical composition
Pressurised
steel
or
cylinder
Approximately
100
mls
(pressurised to 10 atmospheres)
Laboratory
vapours
organic
Colorimetric
tube
undisturbed
Non-Aqueous
Liquids
Large
sample
Phase
undisturbed
stainless
aluminium
detection
analysis
of
99
Type of sample/test
Technique
Large
undisturbed/U100
undisturbed samples
Ground gases
Organic vapours
Other gases/vapours
100
101
British Standard ISO/5667- 18: Guidance on sampling groundwaters from potentially contaminated sites
(ISO/DIS 5667-18).
Bymes, M.E. (1994) Field Sampling Methods for Remedial Investigations CRC Press - Lewis Publishers.
Carter, M.R. Soil Sampling and Methods of Analysis. CRC Press - Lewis Publishers.
Cheremisinoff, P.N., Gigliello, K.A., ONeill, T.K. Groundwater-Leachate: Modelling, Monitoring,
Sampling. ASIN: 0877623767.
Department of the Environment (1994) CLR 4. Sampling strategies for contaminated land. Report by The
R&D Technical Report P5-065/TR
102
Centre for Research into the Built Environment. The Nottingham Trent University.
Department of the Environment (1994) CLR 5. Information systems for land contamination. Report by
Meta Generics Ltd.
Department of the Environment, Transport and the Regions CLR 11 Handbook of Model Procedures for the
Management of Contaminated Land. Contaminated Land Research Report (2000 in preparation).
Environment Agency (1998) National Sampling Procedures Manual.
Environment Agency R&D Technical Report Number P5-066/TR Secondary Model Procedure for the
Development of Appropriate Soil Sampling Strategies)
Environment Agency. Guidance on Monitoring of Landfill Leachate, Groundwater and Surface Water (in
preparation).
Environment Agency. Guidance on Monitoring the Operational and Post-remediation Performance of
Remedial Techniques. R&D Project P5-044.
Hvorslev, M.J. (1948) Subsurface exploration and sampling of soils for civil engineering purposes.
Vicksburg, Miss: Waterways Experiment Station.
Idel, K.H., Muhs H., and Von Soos, P. (1969) Proposals for quality classes in soil sampling and the importance
of boring methods and sampling equipment. In: Soil Mechanics and Foundation Engineering, Mexico,
Speciality Session No 1. Rotterdam: Balkema.
International Standards Organisation ISO/DIS 10381-1. Soil quality: Sampling Guidance on the design of
sampling programmes.
International Standards Organisation ISO/DIS 10381-2. Soil quality: Sampling Guidance on sampling
techniques.
International Standards Organisation ISO/DIS 10381-4. Soil quality: Sampling Guidance on the procedure
for the investigation of natural, near-natural and cultivated sites.
International Standards Organisation ISO/DIS 10381-5. Soil quality: Sampling Guidance on procedures
for the investigation of soil contamination of urban and industrial sites.
International Standards Organisation ISO/DIS 10381-6 (1993) Soil quality: Sampling Guidance on the
collection, handling and storage of soil for the assessment of aerobic microbial processes in the laboratory.
International Standards Organisation ISO/DIS 10381-7 (1993) Soil quality: Sampling Guidance on the
investigation and sampling of soil gas.
International Standards Organisation ISO/DIS 10381-8 (1993) Soil quality: Sampling Guidance on the
sampling of stockpiles.
Saxena, K.S., Gill, S.A., Lukas, R.G. Subsurface Exploration and Soil Sampling. American Society of Safety
Engineers.
Tan, K.M. Soil Sampling, Preparation, and Analysis. Marcel Dekker.
Wilson, N. Soil Water and Ground Water Sampling. CRC Press - Lewis Publishers.
103
6.
ON-SITE MEASUREMENTS
104
Analytes/capabilities
Applications
Detection/
quantification
limits
Interference
Maintenance/
care
Groundwater monitoring.
Resolution: 1mm
Check calibration,
batteries, filters.
Typically detection
limits: 0.5 ppm,
1ppm; typical
accuracies: +/-1-5%
(for semi-logarithmic
scales) or +/-0.1ppm.
Check calibration,
batteries, filters;
high
concentrations of
hydrocarbons can
contaminate
(poison) the
detector for a
considerable time.
Interface meter
Air/water,
air/product
water/product
interfaces;
intrinsically safe.
Landfill gas
analyser
Flame
ionisation
detector
(F.I.D.)
and
is
105
Instrument
Analytes/capabilities
Applications
Detection/
quantification
limits
Interference
Maintenance/
care
buildings, etc.
Personal gas
monitors
Silicones, halogens
(>1000ppm),
halogenated
hydrocarbons, volatile
organometallics,
phosphorous and
sulphur containing
compounds may
damage the sensor.
Check batteries;
do not replace
dry-cell batteries
in a hazardous or
potentially
dangerous area.
Photoionisation
detector (PID)
Analysis
of
volatile
organic
compounds (VOCs) within soil
samples using photoionization and a
UV lamp.
Check
batteries
and calibration.
Portable
hydrocarbon
analyzer
Avoid long-term
exposure to product or
water, especially at
depth of more than
0.5m of water; the
probe can be used for
short periods of time to
depths up to 8m.
Geiger-Mueller
counter
106
Check batteries.
Instrument
Electronic
meters and
probes
Analytes/capabilities
Applications
Detection/
quantification
limits
Interference
Maintenance/
care
Calibration check;
store probes
according to
manufacturers
instructions.
Notes
Confirmatory laboratory analysis:
All measurements made on site with portable instruments should be supported by confirmatory laboratory analysis.
Test kits and ion specific probes:
A range of chemical and biological field test kits, such as immuno-assays, and ion selective probes are commercially available. These provide for a rapid analysis in the field
and are useful screening tools. However, their sensitivity and accuracy are relatively coarse and may be affected by site conditions. Thus, for quantitative assessment,
measurements should to be accompanied laboratory analysis. Test kits should also be used only for testing a matrix for which they have been validated. Thus a test kit
validated for testing of soils should not be used for groundwater until the kit has been validated for groundwater.
107
6.2 - Groundwater field sampling installations commonly used for site investigations
Sampling
installations
Principle/description
applications
Comments/
limitations
Dependent on
sampling extraction
method.
Dependent on
sampling extraction
method.
Can cause
excessive ground
disturbance.
Nested
piezometers
Dependent on
sampling extraction
method. Allows for
depth profiling.
Multi-level
sampler
Dependent on
sampling extraction
method. Allows for
depth profiling.
Difficult to install
and requires
specialist
knowledge. Costly.
Piezometer
Multiple
borehole/
piezometer
arrays
108
6.3 - Groundwater sample extraction methods commonly used for site investigations
Sample
extraction
methods
Principle/description
Applications
Bailer (grab
sampler)
If the number of
monitoring points and/or
sampling frequency are
high, purging and
sampling can be
laborious.
Inertia pumps
Sampling can be
laborious. Limited to
depth of approx. 60 m.
Bladder pumps
Suction/vacuum
pumps
Limited to a depth of
around 10 m. Limited by
the small number of
suitable determinands.
109
Limitations
6.4 - Soil gas sampling equipment commonly used for site investigations
Sampling
installations
Principle/description
Applications/limitations
As in table 6.2
Steel pipes of small diameters (approx 80 mm
o.d) with a perforated section or gas inlet at
the lower end, which are directly driven into
the ground using a hammer or engine-driven
device.
Principle/description
Applications/limitations
Gas sampling
bulbs/cylinders
Pressurised
gas cylinders
Adsorbent tubes
Gas sampling
bags
Inflatable light-weight bags which are preemptied before sampling. The sample may be
released directly into the bag or injected with
a syringe. Available in different materials,
such as Tedlar, Teflon, aluminium or saran
gas sampling bags.
Drive-in
piezometers/gas
spike
Sample
containers
110
Construction Industry Research and Information Association (1993) The Measurement of Methane and Other
Gases from the Ground. Report 131.
Department of the Environment (1991) Landfill Gas: A Technical Memorandum Providing Guidance on
the Monitoring and Control of Landfill Gas. Waste Management Paper No. 27, HMSO, London.
Environment Agency (2000) Guidance on the Monitoring of Landfill Leachate, Groundwater and Surface
Water. Consultation Document.
111
7.
CROSS-CONTAMINATION
7.1 - Some ways in which cross-contamination can occur during a site investigation
7.2 - Examples of well and badly constructed trial pits
7.3 - Description of how to drill a borehole through an aquiclude into an aquifer
7.4 - Illustration of how to drill a borehole through an aquiclude into an aquifer
7.5 - Further Reading
112
7.1 - Some ways in which cross-contamination can occur during a site investigation
Possible mitigation measures
Contaminated
construction
installation.
Hydrocarbon
oils
introduced
deliberately into the air line to lubricate
down the hole hammer equipment
avoid use of DTH if other methods are suitable (see Chapter 4);
113
contractors
check that all vessels are clean and caps are well-fitting;
segregate new clean pots from used ones;
wipe sample vessels after filling to remove soil/water residues.
114
115
116
KEY
FILL/MADE GROUND
SAND AND GRAVEL
CLAY
SAND
BENTONITE SEAL
STANDPIPE
PERFORATED
UNPERFORATED
CONCRETE PLINTH
BENTONITE
PLUG
AQUICLUDE
CASING
PULLEDBACK
BENTONITE
PLUG
BENTONITE
PLUG
AQUIFER
RESPONSE
ZONE
BENTONITE
PLUG
117
118
8.
ANALYTICAL STRATEGIES
119
120
Tick
Comments
In situ or ex-situ
analysis, or a
combination of both?
Turnaround time
required?
Detection limits
required?
Initial laboratory
screening techniques
versus speciation?
A PAH screen, for example, could be used to select those samples for
subsequent USEPA 16 PAHs speciation analyses.
Total metals or
bioavailable metals or
particular valency?
Leachate analysis?
Soil characteristics?
For example:
(i)
(ii)
(iii)
pH, organic matter content and clay content can affect the availability
of contaminants and will therefore be important during any subsequent
semi-quantitative risk assessment determination of required RBCLs
(Risk Based Clean-up Levels). The forthcoming CLEA guideline
values are dependent upon organic matter content and clay content.
121
122
9.
TOPOGRAPHIC SURVEYS
123
Arbitrary grid
Survey stations
Detail survey/scale of plot
Detail to be included
1:200
National grid
Ordnance
datum
Permanent
Local grid
Arbitrary
datum
Temporary
1:500
Other
Permanent buildings/structures
Temporary/mobile buildings
Visible boundary features & descriptions
Roads, tracks, footways, paths
Changes in surfaces
Street furniture
Statutory authorities plant & service covers
Underground pipe sizes & inverts
Vegetation
Isolated trees
Wooded areas
Vegetation limits
Pitches/recreation areas
Private gardens or grounds
Water features
Earth works
Industrial features
Railway features
Site access from public highways
Site investigation works
Height information
Drawing information to be
included
Spot levels
Contours
Spacing
Others (specify)
Interval
Road
sections
Spacing
Site address
Site boundary
Site area in acres & hectares
Scale of drawing & scale bar (in metres)
Direction of true north
OS co-ordinates and/or grid
Historical information
Traced on site
Underground services
Gas mains (high, medium, low pressure)
Water
Electrical (HV & LV)
Telephone (including fibre-optic)
Cable TV
Sewers (foul & storm)
Others
Dead services- approx. location & marked as Dead
124
Digitised
125
9.3 - An illustration of the value of assimilating topographic survey data with historic
maps
126
Stop cock type cover set flush with the ground (cap covering well not shown)
cover
ground level
well tube
Measurement point could be:
the top of the well tube; or
!
ground level.
!
Top hat type cover set proud above the ground (cap covering well not shown)
cover
outer tube
ground level
well tube
Measurement point could be:
the top of the well tube;
!
the top of the outer tube; or
!
ground level.
!
127
128
10.
SITE OBSTRUCTIONS
CONSIDERATIONS
AND
GEOTECHNICAL
10.1 - Diagrammatic Presentation of Section 6 of the Party Wall etc. Act 1996 Adjacent
Excavation and Construction
10.2 - Further reading
129
10.1 - Diagrammatic presentation of Section 6 of the Party Wall etc. Act 1996 Adjacent
Excavation and Construction
130
131
11.
132
Tick
Inhalation?
Ingestion?
Skin contact?
Site workers?
Contractors?
Visitors?
General public?
Others?
Site reconnaissance?
Site investigations?
Other?
133
Comments
Issues
Tick
134
Comments
Tick
135
Comments
Yes
No
No
Yes
Yes
No
No
Yes
No
No
136
Yes
No
Yes
No
137
11.5 British Drilling Association site colour coded site characterisation system
BDA site designation
GREEN
Broad description
Subsoil, topsoil, hardcore, bricks, stone, concrete, clay, excavated road materials,
glass, ceramics, abrasives, etc.
Wood, paper, cardboard, plastics, metals, wool, cork, ash, clinker, cement, etc.
NOTE: There is a possibility that bonded asbestos could be contained in otherwise
inert areas.
YELLOW
Waste food, vegetable matter, floor sweepings, household waste, animal carcasses,
sewage sludge, trees, bushes, garden waste, leather etc.
Rubber and latex, tyres, epoxy resin, electrical fittings, soaps, cosmetics, non toxic
metal and organic compounds, tar, pitch, bitumen, solidified wastes, dye stuffs, fuel
ash, silica dust etc.
RED
All substances that could subject persons and animals to risk of death, injury or
impairment of health.
Wide range of chemicals, toxic metal and organic compounds etc., pharmaceutical and
veterinary wastes, phenols, medical products, solvents, beryllium, micro-organisms,
asbestos, thiocyanates, cyanides etc.
Hydrocarbons, peroxides, chlorates, flammable and explosive materials. Materials that
are particularly corrosive or carcinogenic etc.
Source: BDA Guidance Notes for the Safe Drilling of Landfills and Contaminated Land
This guidance should be used with caution and should not replace the assessments required
by COSHH and CDM.
138
Tick
139
Comments
Contact in office:
Grid ref.:
Job reference:
Visit number:
Subject
Information required
140
Tick
141
Comments
142
Health and Safety Executive. Protection of workers and the general public during development of
contaminated land. HSE(G)66, 1991.
Institute of Petroleum (1998)
(London).
143
12.
ENVIRONMENTAL PROTECTION
12.1 - Fauna species that are protected together with their resting place
12.2 - Ecological evaluation checklist
12.3 - Possible mitigation measures
12.4 - Further Reading
144
12.1 - Fauna species that are protected together with their resting place.
Species
Legislation
Habitat notes
Protective Measure
Close season
(approximate dates)
Badger
1992 Badgers
Act
Bats all
species
1981 W&C
Act,
Schedule 5
Requires suitable
soils
for
burrowing
Buildings, caves,
hollow trees
All breeding
wild birds
1981 W&C
Act,
Great crested
newt
1981 W&C
Act
Schedule 5
1981 W&C
Act,
Schedule 5
1981 W&C
Act,
Schedule 5
1981 W&C
Act,
Schedule 5
Otter*
Water vole
Dormouse*
Sand lizard*
Natterjack
toad*
*
1981 W&C
Act,
Schedule 5
1981 W&C
Act,
Schedule 5
Holts may be
established away
from river courses
Burrows in ditch
and river banks
Protects
systems
Occupied
year
Diverse,
especially ancient
coppice
woodland.
Sandy
heath
habitats
in
southern England
Shallow
pools,
especially in heath
and coastal areas
the
burrow
rarer species that could be found at some sites in certain parts of the country
145
throughout
the
Tick
146
Comments
Obtain information on SSSI from the Statutory
Authority, English Nature (or CCW, SNH) or Local
Plans. Where SSSI may be affected the proposed
investigation works must be agreed with the statutory
authority. Seasonal limits on work may be advised
Obtain information on sites from the local Wildlife
Trust (WT), or from Local Plans. The WT or the
Local Authority Ecologist can advise on the
ecological interest of the site and precautions to be
taken, e.g. in the case of protected species being
present or species being the subject of Biodiversity
Action Plans.
Inspect site for presence of trees, scrub, other
potential nesting areas, e.g. derelict buildings. Where
nesting is likely employ seasonal working (between
late July and mid-March) to avoid disturbance
Inspect sites for signs of burrowing or well used
animal pathways. Advice on local badger activity
may be obtained from the local WT, or EN (CCW or
SNH). Avoid works close to setts in the breeding
season
Inspect site for potential habitat, buildings, trees with
hollows or small crevices, underground caves or
crevices. Obtain specialist advice (from the WT, EN
etc) where works may impinge on any such sites.
Note that seasonal restrictions on work will apply.
Ponds are likely to contain amphibia. Obtain specialist
advice (from the WT, EN etc) where works may
impinge on any such sites. Note that seasonal
restrictions on work may apply.
Check with the local authority for the presence of any
TPO, or hedges protected under the Hedgerow
Regulations on the site. Avoid the bird-breeding
season. Where trees are to be felled consult the local
Forestry Commission Conservators Office over the
need for a felling licence. Trees with hollows or
crevices may contain bats (see above).
Potential environmental
impact
Creation of access
routes for tracked or
wheeled vehicles
Borehole installation
Trial pits
Window
and
Penetrometer Sampling
Watercourse
sampling
Conduct ornithological survey or avoid the birdbreeding season, avoid damage to waterside
burrow systems.
sediment
147
Ecology
Coventry S. and Woolveridge C. (1999) Environmental Good Practice on Site CIRIA London.
148
149
13.
Tick
Comments
Appendix A
Cover to include:
Client:
Reporting company (as on front cover)
Report reference
CONTENTS
EXECUTIVE SUMMARY
1.
Introduction
1.1
Background
1.2
1.3
1.4
1.5
Report structure
2.
2.1
Introduction
2.2
Site location
2.3
Site description
2.4
2.5
Archaeological information
3.
3.1
Introduction
3.2
Geology
3.3
Hydrogeology
3.4
Hydrology
4.
Site history
4.1
Introduction
4.2
History
4.3
4.4
4.5
5.
5.1
Introduction
5.2
6.
6.1
6.2
Methodology
6.3
Analytical suites
7.
Factual results
7.1
Introduction
7.2
7.3
7.4
7.5
7.6
10
7.7
10
7.8
10
7.9
10
8.
11
REFERENCES
12
13
APPENDICES
14
EXECUTIVE SUMMARY
Summarise the pertinent issues i.e. the main findings and recommendations.
1.
INTRODUCTION
1.1
Background
Provide reasons for works being undertaken, including whom has commissioned the
work/when/how (e.g. by letter of X/X/X) and, where appropriate, intended future usage of the
site.
1.2
State what is included and also what has been specifically excluded. Mention any:
1.3
1.4
List, briefly, all information sources and nature of information (include source of any
anecdotal information and all references used in the References section). Mention also, any
information that was sought but not obtained/still awaited.
1.5
Report structure
2.
2.1
Introduction
State that this chapter of the report includes Hazard Identification and, where there is some
assessment of potentially relevant exposure scenarios/hazardous conditions, Hazard
Assessment.
2.2
Site location
Include:
location description (e.g. located in the centre of X city, between X river and X canal
and accessed off X road);
2.3
Site description
Include:
current use;
ownership;
general topography, noting ground level of land surrounding the site relative to that of
the site;
notes of any site features that may have the potential to cause ground/groundwater
contamination;
a description of surrounding land uses (identify local receptors e.g. school playing
fields, sensitive habitats, housing and boundaries of neighbouring properties);
current site layout plan (showing site boundary(s) clearly) with notes from site
reconnaissance visit and previous process activity locations (if appropriate); and
NB As appropriate, summarise descriptions from reports of earlier stages and include latest
description in full. Include full references for the previous reports.
2.4
State if an ecological survey has been included during this or any previous stage and provide
details.
2.5
Archaeological information
State if archaeological work has been included during this or any previous stage and provide
details.
3.
SITE
GEOLOGY,
HYDROLOGY
HYDROGEOLOGY
AND
As appropriate, summarise descriptions from other reports and include latest description in
full. Include full references for the previous reports.
3.1
Introduction
State that this chapter of the report includes both Hazard Identification and, where there is
some assessment of potentially relevant exposure scenarios/hazardous conditions, Hazard
Assessment.
3.2
Geology
Include:
a description of the site geology from published geological maps and borehole logs
from the local area (differentiate between solid and drift);
Consider including a conceptual drawing of the geological profile, particularly if the natural
stratigraphy is complex and/or has since become complicated by anthropological activity (e.g.
deeply founded tanks and piles etc).
3.3
Hydrogeology
3.4
Hydrology
Include description and details of local surface watercourses, e.g. distances and direction from
site, flow direction, General Quality Assessment, licensed abstractions (volume, use,
distance/direction from the site) and any reported pollution incidences.
4.
SITE HISTORY
Summarise history from previous desk study/other reports and include any new information in
full. Include full references for the previous reports.
4.1
Introduction
List information sources used (in more detail than in Section 1.3). State that this chapter of
the report includes both Hazard Identification and, where there is some assessment of
potentially relevant exposure scenarios/hazardous conditions, Hazard Assessment.
4.2
History
Provide a description from historical maps, aerial photographs, anecdotal evidence etc. for the
site and surrounding area (list specific sources/information used). In a site investigation
report, it may be appropriate to tabulate much of this information.
NB Avoid taking each map in turn and describing it as a chronology. Instead assimilate the
information first and then describe the history using suitable headings. For example, for a
Power Station Site:
etc.
4.3
E.g. Environment Agency, local authority Environmental Health Department, Health and
Safety Executive.
4.4
4.5
Include potential contamination sources, nature, scale etc. Summarise this information on a
plan of the site if possible.
INCLUDE REPORT REFERENCE IN FOOTER
5.
As appropriate, summarise information and data included in reports of earlier stages in the
main body of the report. If there has been a series of previous investigations, deal with these
one at a time using a separate section for each (using the headings below in each section).
Include the full reference for each previous report.
If there has been only one previous investigation report and this is brief, consider including it
in full in an Appendix to the current report. If there are several reports of previous
investigations, consider including the investigation logs and analytical data in an
Appendix/series of Appendices to the current report.
5.1
Introduction
Provide a summary of why the investigation was undertaken, by whom, what it included and
when and how it was carried out. State that this chapter of the report includes both Hazard
Identification and, where there is some assessment of potentially relevant exposure
scenarios/hazardous conditions, Hazard Assessment.
5.2
Provide a summary of the physical and chemical conditions encountered (include any gas
monitoring results, groundwater levels etc.) and any recommendations made following the
investigation.
Include a drawing showing the locations of trial pits/boreholes etc. at a suitable scale.
6.
SITE
INVESTIGATION
METHODOLOGY
6.1
DESIGN
AND
Include:
give the rationale used in locating boreholes and trial pits etc (e.g. borehole BH328
located on downstream side of a former diesel tank, river sample R303 taken just
downstream of an outfall pipe).
6.2
Methodology
Include:
brief details of the site investigation contractor(s) and laboratory(s) (include laboratory
UKAS testing accreditation number(s), details of other accreditation and QA/QC
procedures);
brief details of any preparatory work (e.g. moving of mounds of waste, breaking
through concrete etc) and all investigation activities included in the activity (e.g.
intrusive work, tank inspections/sampling of contents, gas/groundwater monitoring,
topographic survey etc);
for boreholes and trial pits, state maximum depth achieved, drilling method
(boreholes) and whether groundwater/gas monitoring installations were included;
for gas/other monitoring exercises state the methods, equipment used (e.g. PID with
10.2eV lamp), duration and frequency of monitoring and ambient conditions etc.;
6.3
Analytical suites
Describe the basis of the analytical strategy e.g. how and why analytical suites and samples
were chosen.
Include a summary of chemical analytical suites, samples scheduled for these (including
strata/locations/depths), brief details of the sample preparation and analytical methods used
together with any limitations/constraints on laboratory analysis.
7.
FACTUAL RESULTS
7.1
Introduction
7.2
the physical conditions encountered on site (refer also to the geological information
provided in Chapter 3 and confirm whether the expected geology was proven);
7.3
Provide a full description of the made-ground encountered including any olfactory and/or
visual evidence relating to presence/absence of contamination. Where appropriate provide
descriptions for different areas and identify any emerging patterns.
7.4
Provide a full description of the natural ground encountered including any olfactory and/or
visual evidence of presence/absence of contamination.
7.5
7.6
the type and nature of contamination and its spatial distribution and whether this
accords with the physical conditions observed, any olfactory and visual contamination
indicators, gas readings etc.;
7.7
7.8
7.9
(where relevant)
Present results in tabular/illustrative forms. State what instruments were used as a footnote to
the table(s) and include detection/quantification limits or the instruments used where no gas
was recorded. Provide a description of the findings and relate to physical and chemical
conditions.
10
8.
Other report sections may be required depending on the requirements of the site
investigation, for example:
Hazard assessment;
Risk estimation;
Risk evaluation;
Recommendations;
11
REFERENCES
Include:
standards/codes/guidance documents;
12
current site layout plan with notes from site reconnaissance visit(s), previous process
activity locations (if appropriate);
drawing showing ground investigation locations (may or may not include topographic
survey details).
any cross-sections, plans and other drawings needed to illustrate specific findings from
the desk study, site reconnaissance and site investigation phases.
13
APPENDICES
To contain any information supplementary to that in the main body of the report e.g.:
field data including results of any monitoring data recorded on site and groundwater
data;
14