Professional Documents
Culture Documents
Hotel On A Unused Land
Hotel On A Unused Land
The Report on the Presentation Carried out as Part of Ensuring the Communitys Informed
Consent for the Proposed Structure
Name:
Institution:
Letter of Introduction
Dear Sir,
Ref: Report on The Presentation Carried out as Part of Ensuring the Communitys
Informed Consent For The Proposed Structure
As part of the process of ensuring the local community give an informed consent to the
construction of a 27-story building on an unused section of land at 41 Wharf Street, a
presentation was made to convince the affected community. A group of five engineers set out on
this task. The group isolated the main issue as pedestrian safety and accessibility of the city
during and after construction as the main problem. Kindly note that this issue had been raised in
the scoping report.
The local administration government was approached to help in organizing the meeting,
which had a fair representation. The group divided the main issues into various subtopics and
applied the symposium strategy to inform the audience. The audience was allowed to ask
questions and all clarifications made. Each speaker tackled the allocated issue effectively and
assured the audience that the proposed solution would be implemented. The report has
recommended four issues the project manager needs to implement for the project to be accepted
by the community. Please see to it that the recommended issues are tackled.
Thank you very much.
Yours faithful
(Your name)
Executive Summary
After the scoping report on the proposed site for construction of a 27-story building in an unused
section of land at 41 Wharf Street was prepared and consent sought, the community needed to be
convinced before making an informed consent. This report details a presentation on the issues
arising from the project and how the project manager ought to deal with them for the project to
be accepted. The study employed a group presentation method involving modified symposium
technique. In the presentation, the group was convinced that the main problem focused on traffic
caused by the project, parking during the building process, and dealing with tracks that are
entering the construction site. Also, the pedestrian access was considered as the main issues
during the project operation phase. The report recommends an appropriate action to the project
engineer. In addition, the report has made an evaluation of the entire process of presentation so as
to take note of future improvements.
Introduction
This report follows a scoping report on the proposed site for construction of a 27-story
building on an unused section of land at 41 Wharf Street. After an evaluation of the scoping
report, a consent for building the hotel was sought, but it could only be issued after the
community had been informed and agreed to the issue arising out of the project and how they
will be solved. The purpose of this report is thus to document the presentations made to the local
community as part of the process of ensuring the community is informed.
The group tasked with educating the community on these issues identified the issues
falling under accessibility, and connectivity as the main issues affecting the community. The
group was of the view that the problem be grouped in two phases; during the project construction
phase, and during the operation. It was agreed that several items, including traffic, parking
during the building process, and dealing with tracks that are entering the construction site be
considered as the main issues during the project construction phase. It was further agreed that the
pedestrian access be considered as the main issues during the project operation phase.
The main approach of the group was for each member of the group to make a
presentation on an allocated issue tactfully to convince the audience. Arrangement for the
meeting was effected through the help of the local administration.
Discussion of Group Issues
The Perspective and Stance of the Group
The group was of the professional opinion that the project would affect the surrounding
people in Dunedin city, and the main issues the community was concerned with was the safety,
and accessibility during and after the project had been constructed. The group adopted that stance
that all the issues likely to result from the project are technical in nature and could, thus be
solved using various engineering techniques. In this case, they adopted the perspective that the
community should allow the project to go on as planned and allow the project manager to see to
it that solution to all issues has been found per the recommendation of the group. Each speaker
was determined to convince the community how a given issue that was raised will be handled.
The Issues the Group Considers to be the Most Important
During the process of submitting issues from the community, various issues were
brought forward. However, the issues that the group considered important and needed to be
addressed focused on accessibility and connectivity during the project construction phase, as
well as after the project has been concluded. In this case, several items, including traffic, parking
during the building process, and dealing with tracks entering the construction site were the main
issues during the project construction phase. Also, the pedestrian access was considered as the
main issues during the project operation phase.
The Nature, Scale, Likelihood, and Importance of Issues
Traffic
The proposed structure will house hotel rooms and apartments. As a result, many people
will come from various points as tenants, as well as customers for various businesses that will be
housed in the structure. This means that the number of people leaving and coming into the
building will increase. If most of them will be owning cars, they will add to the traffic on the
Wharf street. Public service vehicles, as well as taxis will also increase on this street to cater for
those without cars. By the time the building is completely occupied, there will be at least more
than 1000 additional cars on the already busy street. The surge in traffic is certain and will
commence as soon the building process starts. However, a surge in traffic is inevitable in any
developing city and does not pose a serious threat (Hoek & Imrie, 1995).
Figure 1: Dunedin city showing the proposed building (Mccorkindale & Houlahan, 2013, p.
1)
In the diagram, it can be seen that a road passes between the proposed site for project and
the harbor. The entire map of the site is shown below:
Figure 2:The Dunedin City map showing the names of various streets and roads (The
Dunedin City Council, 2013)
Figure 3:the site map for the proposed project (Mccorkindale & Houlahan, 2013). The
exact spot is colored red
From the maps in figure 2 and 3, the arrangement of roads implies that once the project is
completed, it will be difficult to connect the city and the harbor through the Wharf Street from
the proposed hotel. This is because the proposed structure lies between the city and the harbor.
Many pedestrians will be inconvenienced, and they may interfere with normal traffic on Wharf
Street. In addition, it will be difficult for pedestrians to cross the railway to Cumberland street. If
no proper connection is made to cater for pedestrians, especially those crossing to and from the
harbors, accidents are likely to be common on the Wharf street. In addition, the wharf street will
experience notorious traffic surge that may persist as long as the building is occupied.
Although pedestrian access seems a major problem, this problem can be solved by constructing
an overpass bridge over Wharf street, as well as an overpass pedestrian bridge over the railway
line to Cumberland street. Overpass pedestrian bridges, also called flyovers, are common
engineering structures that can help solve connectivity problem, such as the one in this case
(Construction Management Engineers, 2012). The diagram below indicates an example of a
flyover:
beyond the topic and this caused some panicking tendencies among the group. Nevertheless, the
collaboration among the group made the presentation successful and convincing.
How the Group Methodology Approach Impacted the overall Hearing
The group methodology approach impacted the entire hearing process positively. In the
first place, a group approach indicated the weight with which the group had approached the
issues, and thus, the audience were keen to listen to what the group had to say. Each speaker of
the group had his or her style of speaking and this contributed to the alertness of the audience
whereby the monotony of one speaker was broken by another speaker. The process of shifting
from one speaker to another provided a good break and a time of reflection to the audience and
this improved the general hearing. However, slow learners in the audience may have been lost in
the process of changing from one speaker to another.
How the Experience Has Informed My Knowledge of Consent Hearing Process
Any project proposal must first be rubberstamped by the community, and thus, the project
manager must ensure that he or she convinces the community to accept the project. Consent
hearing process requires the speaker to be knowledgeable of the problem affecting the audience
and various ways of solving it. The speaker must be genuine and concerned about this problem
for the audience to accept the information. As a result, a group approach is an effective way of
enhancing credibility and keenness from the audience. Each presentation must be backed by
scientific or engineering explanation for the idea to be accepted.
What Should be Done Differently In Future
The group symposium method used in this study has various drawbacks. In the first
place, some members are likely to go beyond their allocated topic thereby inconveniencing the
next speaker. The presentation can turn out to be a series of events that are not related to each
other if there is no effective transition. As a result, there will be a mock presentation before an
actual presentation in future presentation. Mock presentation will be done in secret, but before a
panel of critics to weed out some mistakes.
Conclusions and Recommendations
This paper focused on convincing the community to give a consent for the construction of
a 27-story building. The study discovered that the community was concerned about accessibility
and safety during and after the project, and thus, needed professional information on how these
issues would be handled before consenting to the idea. The study developed a stance that a group
symposium to discuss the issues and their solutions would convince the audience to consent to
the idea. The presentations during the symposium convinced the community to consent to the
idea. The speakers majorly focused on traffic caused by the project, parking during building
process, and dealing with tracks that are entering the construction site. Also, the pedestrian
access was considered as the main issues during the project operation phase. The group could not
find a solution to the increased traffic after the project rolls in operations, but recommends the
following:
A flyover footbridge to be constructed across the wharf street to link the building and the
harbor.
Another flyover footbridge to be constructed across the railway line to link the building
to the Cumberland street.
The project manager to construct a parking for all trucks carrying materials to the site so
as not to interfere with the traffic on the Wharf Street.
Heavy trucks carrying materials to come to the site during the time when the traffic is
low, especially at night so as not to interfere with the smooth flow of traffic in the city.
References
Mccorkindale, W., & Houlahan, M. (2013). Dunedin waterfront hotel consent denied . Retrieved
Nov 9, 2013, from Business Day:
http://www.stuff.co.nz/business/industries/8758022/Dunedin-waterfront-hotel-consentdenied
Construction Management Engineers . (2012). McKeesport Fly-Over Bridge. Retrieved Nov 9,
2013, from Construction Management Engineers : http://www.alcm.com/projects/mckeesport-fly-over-bridge
Evans, H. (1990). Engineering handbook. New Haven, Connecticut: Institute of Traffic
Engineers.
Hoek, E., & Imrie, S. (1995). Consulting Boards for large civil engineering projects. Water
Power and Dam Construction , 47 (8), 33-34.
The University of Mary Washington . (2012). Formats for Group Presentations. Retrieved Nov
09, 2013, from University of Mary Washington :
http://academics.umw.edu/speaking/resources/handouts/formats-for-group-presentations/
The Dunedin City Council. (2013). Street map. Retrieved Nov 9, 2013, from The Dunedin City
Council: https://www.dunedin.govt.nz/council-online/webmaps/street-map