PROJEK LEBUHRAYA PANTAI TIMUR FASA 2,

TERENGGANU
PAKEJ 1A : DARI CH.0.00 KE CH.3750
JABATAN KERJA RAYA
PASUKAN PROJEK
LPT FASA 2
Ref No.

Title:

QBR/MS/ENV/0411/01

1.0

METHOD STATEMENT

MainContractor.
Q-BENA RESOURCES
SDN BHD
Date :

MAINTENANCE/DESILTING SILT TRAP

April 20, 2011

INTRODUCTION & PURPOSE


This method statement has been prepared for the work to be carried out
desilting, repair and replacement of damage/worn parts and materials at
existing Silt Trap constructed by the previous contractor as established at
site. The purpose is to outline the Method and Procedures required to carry
out the desilting of silt traps and to maintain the silt trap that has been
constructed to functional silt traps to avoid silt overflows beyond the
working boundary. Should the Silt trap found Not Functional then the
existing Silt trap shall be demolishes and a New Silt trap shall be
constructed as Directed by S.O.

2.0
2.1

WORK SEQUENCE
Join Inspection shall be conducted visually and photograph shall be taken

2.2

before the silt trap to the existing the silt trap and its location.
To double check the location of silt traps and confirmed the location as

2.3

constructed previously as indicated in the construction issued.


To carry out the clearing of small vegetation inclusive of stripping silt and
dispose of surplus material to approved dumping area. (Photograph Shall

2.4
2.5

be taken during The process)


Desilting work by excavator or backhoe shall be carried out in accordance.
Repairing of required gabion (wire mesh and stone) crossing the silt trap
area and make good to the existing drain (if required). Should the Gabion
Wired Mesh is beyond repaired then the damage gabion shall be

2.6

demolished and New Gabion to be install as directed by S.O.


Make good to the layer of geotextile (Terrain T1000 or equivalent) and
make sure coarse gravel as filter material in are in good condition or

2.7

otherwise replace and ensure is in a acceptable functional condition.


Upon completion of the desilting work Photograph shall be taken to proof
of work of desilting has been carried out for record

3.0

EQUIPMENT

3.1
3.2

Survey Equipment/ Camera


-1No
Excavator/Backhoe
-1 No

4.0

MANPOWER

Rev.00

Page 1of

PROJEK LEBUHRAYA PANTAI TIMUR FASA 2,


TERENGGANU
PAKEJ 1A : DARI CH.0.00 KE CH.3750
JABATAN KERJA RAYA
PASUKAN PROJEK
LPT FASA 2
Ref No.

Title:

QBR/MS/ENV/0411/01

4.1

METHOD STATEMENT

- 1 person
- 1 person
- 2 persons

5.0

RELEVANT DRAWING

5.1
5.2
5.3

KPKR/J/R/130507 (LPT2)/1A/EMP3A
KPKR/J/R/130507 (LPT2)/1A/EMP4A
KPKR/J/R/130507 (LPT2)/1A/EMP5A
6.0

Rev.00

Q-BENA RESOURCES
SDN BHD
Date :

MAINTENANCE/DESILTING SILT TRAP

Supervisor
4.2Operator
4.3General Worker

MainContractor.

RELEVANT FORM
6.1Request for Inspection Form
6.2
JKR SPK form is not required
6.3
Attached relevant sketch.