Professional Documents
Culture Documents
Optimizacion de Procesos de Planta Mexicana PDF
Optimizacion de Procesos de Planta Mexicana PDF
Minera Mexicana la Cienega has three Smart Process Plant modules: the SAG
Milling and the Balls Milling projects, implemented from August, 2006 to January
2007 and the Flotation project from June 2007 to June 2008, with an ongoing
optimisation and logic verification in 2009.
METHODOLOGY
The implementation of the Smart Process System for the milling circuit required the execution of some
previous tasks. After the completion of these preliminary tasks the implementation of the Smart Process
Systems was carried out.
The previous tasks included changes in the circuit, a review of instrumentation and the execution of some
simulations. Specifically the following tasks were conducted:
Sampling and mass balance for the SAG-Ball mill circuit
Change the ball mill circuit from parallel to series
Flow
% Fresh Load
Mineral
Water to SAG
Pebbles
4.0
Unloading SAG
In order to comply with the particle size required in the product for
the flotation process, two particle analysers PSI-200 were installed,
after collecting fines from the cyclones connected to the SAG mill
and the ball mill, in order to have real time data. Figure 2 shows the
calibration chart obtained from the software of the equipment PSI200 in which a good correlation between the data generated in line
by the equipment and the results of the laboratory can be seen
60
80
70
50
60
45
40
50
35
40
30
30
25
20
20
VP nivel de cajon
15
SP nivel de cajn
10
velocidad bomba
7:50
7:27
7:04
6:41
6:18
5:55
5:32
5:09
4:46
4:23
4:00
3:37
3:14
2:51
2:28
2:05
1:42
1:19
0:56
0:33
0:10
23:47
0
23:24
10
23:01
Nivel Level
de cajon
Sump
(%)(%)
55
velocidad
bomba
(Hz)
Speed
of pump
(Hz)
Linear regression
between laboratory
grading & PSI-200
Tiempo
(min)
Time (min)
Figure 3 Tuning of the control loops for the sump level in mill
number two
For the implementation of the flotation Smart Process Plant Systems the following activities were
realised:
Back log information analysis on the use of reagents from the operators logs
addition of Aerophine to primary flotation lead cells
Addition of Aerophine on ml
140.00
130.00
120.00
110.00
100.00
90.00
80.00
-0.5
0.5
1.5
2.5
3.5
Survey the operators methodology to make adjustments to the process for the Smart Process Plant
System
The first stage to implement the Smart Process Plant System was to
survey the operators methodology for the SAG and ball milling and
flotation logic programming; this logic is designed by interviewing the
personnel of the area to find out the best operative practices. Once the
information is reviewed and approved by the process supervisors, it is
represented in a logical diagram. An example of the addition of the
frother to the lead circuit is showed.
Using the information obtained from the operators methodology to develop program logic
Once the logic diagrams are accepted by the operators and supervisors, the programming technicians design and write the
program needed in the Smart Systems Server. Once this program is on line it changes the set point for all the variables that
control the process.
250
1400
1200
1000
150
800
600
100
Power (Kw)
200
400
50
200
23:15
21:15
22:15
20:15
19:15
18:15
17:15
16:15
15:15
05:25
06:25
04:25
03:25
02:25
01:25
00:25
23:25
Tonnagesintonia
Fine Tuning
tonelaje
fina
potencia
sintonia
Power Fine
Tuningfina
21:25
22:25
20:25
19:25
18:29
17:30
16:30
15:30
13:30
14:30
12:30
11:30
10:30
09:30
08:30
07:30
05:30
06:30
04:30
03:30
02:30
01:30
00:30
Tonnage sintonia
Implementation
tonelaje
gruesaTuning
Potencia
sintonia gruesa
Power Implementation
Tuning
Time (min)
25
Implementation Tuning
Xanthate Addition
variability: 11.27
g/t
20
Fine Tuning
Xanthate Addition
variability: 9.06
15
10
0
0
200
400
600
800
1000
1200
1400
1600
1800
2000
Samples
Optimisation
% -200 #
70
60
50
PARALLEL CIRCUIT
64.7 %
40
SERIESCIRCUIT
73.3 %
30
After Project
20
0
200
400
600
800
1000
Shift
% INCREASE
SERIES
SMART SYSTEM
- 1.67
4.97
11.55
7.10
with Smart
System
% Diff
Without Smart
System
with Smart
System
Recovery Pb
62.29
64.46
2.17
129.26
104.72
Grade Pb
42.64
42.22
-0.41
75.6
56.97
Head Grade Pb
1.4
1.44
0.04
0.08
0.11
Tails Pb
0.25
0.22
-0.03
0.05
0.03
with Smart
System
% Diff
Without Smart
System
with Smart
System
Recovery Zn
45.63
48.18
2.55
136.04
95.15
Grade Zn
52.25
51.93
-0.32
25.55
21.02
Head Grade Zn
2.22
2.36
0.14
0.1
0.19
Tails Zn
0.53
0.44
-0.09
-0.04
0.03
CONCLUSIONS
By implementing the smart system in the milling area, a major SAG mill fed stability was obtained, thus
obtaining a 7.1% increase of the milling capacity. For the product sent to flotation, classification was
improved to less than 200 mesh by 11.5%.
As result of milling capacity, grade and recovery improvement, an extra 3.5% in net sales was increased.
A significant improvement in recovery of lead and zinc of 2.17% and 2.55% respectively, plus a considerable
reduction in the consumption of reagents was obtained.
Flotation circuits stability was significantly improved, for the grade and recovery in lead circuit of 18.63%
and 24% in variance respectively and for grade and recovery in zinc circuit of 4.53% and 40.89% in variance
respectively.
Additional benefits of the smart system installation:
Training and knowledge development for supervisors and operators
Higher economical incentives for the personnel because of the increase in milled tonnes recovered and
fewer costs
Opportunity for the operations personnel to analyse and integrate information for decision-making
ACKNOWLEDGEMENTS
We want to thank the group of people who collaborated in the realisation of this project, executive personnel; Dr. Rodolfo
Espinosa, Ing. Joaqun Barba; line operators, Vernica Rodrguez, Heladio Gonzlez, Jorge Pinales, Nicols Guzmn,
Isidro Guzmn, Claudia Carrola. Translations support Omar Pinedo.