Professional Documents
Culture Documents
WORLD VISION MALAWI-Design Report For Chilenje Piped Water Scheme 14
WORLD VISION MALAWI-Design Report For Chilenje Piped Water Scheme 14
CHILENJE
RURAL
PIPED WATER SCHEME
MALAWI
BOARD
OF ENGINEERS
Tuesday, January
Page 1
07, 2014
_______
________________
W. E. Mtonga
(GRADUATE ENGINEER)
Tuesday, January 07, 2014
with
the
Malawi
Board
of
Engineers
and
hereby
Page 2
Project Objectives
The main objective of the project was to carry out hydraulic analysis for all
extension lines of the scheme and to design the entire infrastructure
necessary for the transmission of water to the beneficiaries.
Page 3
The scope of works was as follows:a) To take an inventory of what was in the field in October 2011.
b) To assess the functionality of the existing infrastructure and their
conformity to design standards.
c) To make recommendations on whether the existing infrastructure could
still be incorporated in the new design to ensure that the scheme
performs to its intended design capacity.
d) To conduct demographic survey to establish the baseline number of
beneficiaries and to determine the levels of service for the scheme
over the design period.
e) To conduct detailed topographic survey for the intended water supply
system including distribution networks.
f)
Project Findings
The project analysis revealed that it is possible to extend the scheme
southwards to supply more areas under Group Village Headmen Chauwa and
Gwenembe. The source had a collective discharge capacity of 5.2l/s which is
adequate to accommodate the demand for the target villages over a design
period of 20 years.
Page 4
Page 5
Acknowledgement
I would like to accord special thanks to the staff of World Vision International that
worked tirelessly and contributed to the development of this report. Special thanks
are also extended to Mr Peter Matipwiri, Water and Infrastructure Manager for his
support during and after field visit. I would like to thank field staff for their support
and providing population head counts for the area.
I would like to thank Eng. B.B. Nkhoma , my supervisor for his guidance in the
development of this report. His contribution is highly commended.
Page 6
Page 7
Foreword
This report is one of the four documents that were produced in partial fulfillment for
the requirements for registration with Malawi Board of Engineers. The brief outline of
all the documents is indicated below.
1)
2)
3)
4)
Volume
Volume
Volume
Volume
1
2
3
4
Design Report
Bills of Quantities
Drawings
Specifications
The Design Report gives design information. The Bills of quantities give an outline of
quantities of works taken off from the drawings according to standard methods of
measurements. The drawings specify the dimensions of the structures while
Specifications indicate the standards of performance in the execution of works.
Table of Contents
Page 8
PROJECT BACKGROUND.................................................................1
1.1
Introduction....................................................................................................... 1
1.2
Intakes Location................................................................................................. 2
1.3
Sources of Information.......................................................................................3
1.4
1.5
CHAPTER TWO
2.1
Introduction....................................................................................................... 5
2.1.1
2.1.2
Weather...................................................................................................... 6
2.1.3
Political Boundaries.....................................................................................7
2.2
2.3
2.4
2.5
Socio-economic Activities..................................................................................9
2.6
Infrastructure..................................................................................................... 9
2.7
2.8
2.9
Proposed Solution............................................................................................10
CHAPTER THREE
DESIGN CONSIDERATIONS..........................................................12
3.1
Introduction..................................................................................................... 12
3.2
3.2.1
3.2.2
Field Observations....................................................................................12
3.3
3.4
3.4.1
3.4.2
Design Period............................................................................................ 14
Page 9
3.4.3
3.4.4
3.4.5
Peak Factor............................................................................................... 14
3.4.6
3.4.7
3.4.8
Level of Service........................................................................................14
3.4.9
3.4.10
3.4.11
Residential Head...................................................................................15
3.4.12
3.5
Population in 2011...........................................................................................15
3.6
3.7
3.7.1
Supply Criteria.......................................................................................... 18
3.7.2
Field Observations....................................................................................18
3.8
3.8.1
3.9
CHAPTER FOUR
FIELD SURVEY............................................................................21
4.1
4.2
4.3
4.3.1
4.3.1
CHAPTER FIVE
5.1
Introduction..................................................................................................... 25
5.2
Design Criteria.................................................................................................25
5.3
Design Population............................................................................................25
5.4
5.5
5.5.1
5.6
Review for the Design of storage tanks and Spring Capping Structures..........30
5.6.1
5.7
Design Criteria..........................................................................................28
Design Criteria for the Intake Structure....................................................31
5.7.1
Design Criteria..........................................................................................33
5.7.2
Tank Location............................................................................................ 33
5.7.3
Tank Volume.............................................................................................34
5.7.3.1
Page 10
5.7.3.2
5.7.4
Tank Dimensioning....................................................................................38
5.7.5
5.7.6
5.7.7
5.7.7.1
5.7.7.2
Top Slab.................................................................................................40
5.7.7.3
Concrete Wall........................................................................................40
5.7.7.4
5.7.7.5
5.8
5.8.1
Design Criteria..........................................................................................41
5.8.2
Alignment of Pipelines..............................................................................42
5.8.3
Pipe Materials........................................................................................... 43
5.8.4
5.8.5
Hydraulic Design of the Distribution Line between the Storage Tank and
Chauwa Primary School..........................................................................................45
5.8.6
Hydraulic Design of the Distribution Line between the Storage Tank and
Gwenembe............................................................................................................. 46
5.8.7
5.7.9
5.8
Relocated Villages...........................................................................................47
5.9
Profiles............................................................................................................. 48
5.10
Tap Locations................................................................................................ 49
5.11
5.12
Thrust Blocks................................................................................................50
5.13
CHAPTER SIX
6.1
Introduction..................................................................................................... 51
6.2
Conclusion....................................................................................................... 51
6.3
Recommendations........................................................................................... 51
APPENDICES............................................................................................................... 53
References................................................................................................................. 59
List of Figures
Page 11
List of Tables
Table
Table
Table
Table
Table
Table
Table
Page 12
CHAPTER ONE
1.1
PROJECT BACKGROUND
Introduction
World Vision Malawi through Nkhoma Area Development Programme is
providing water to rural communities in the area where it renders its services
and ensures that people have convenient access to water in sufficient
quantity and adequate quality for basic use. In view of the above objective
World Vision Malawi planned to upgrade and extend a small existing scheme
with intakes arising from spring capping structures in Ngala Hills in Lilongwe
District. This scheme was originally implemented by Africare. However,
Africare is no longer operating in the area at the moment.
Page 13
Field investigations revealed that the springs had sufficient flows especially if
the design was in an augmented arrangement. In October 2011 very few
communities located along the foot of the mountain benefited from the
scheme.
Flow observations coupled with the terrain of the area indicated that the
scheme could be extended to benefit more people living in the Chilenje Plain.
Chilenje is part of the area where World Vision Malawis Nkhoma Area
Development Programme provides its services. This influenced World Vision to
engage an engineer to provide consultancy services to carry out detailed
analysis and design of the scheme. The main tasks of the Engineer were to
confirm the previously identified potential of the flows, to assess the
possibility of extending the scheme and to design all the components of
scheme so that the people living in the technically feasible area could benefit
from it.
The scope of works included the following:a) To take an inventory of what was in the field in October 2011.
b) To assess the functionality of the existing infrastructure and their
conformity to design standards.
c) To make recommendations on whether the existing infrastructure could
still be incorporated in the new design to ensure that the scheme
performs to its intended design capacity.
d) To conduct demographic survey to establish the baseline number of
beneficiaries and to determine the levels of service for the scheme
over the design period.
e) To conduct detailed topographic survey for the intended water supply
system including distribution networks.
f)
Page 14
1.2
Intakes Location
Chilenje Gravity Fed Water Supply scheme was a proposed upgrading and
extension to the existing small schemes arising from springs on the southern
side of Ngamba hills. Field investigations revealed that there were five (5No)
springs. Four springs had brick wall storage tanks, one for each spring. At the
time of carrying out field investigations the fifth spring had not been
developed yet. The developed springs supplied few communities located close
to them. Figure 1 below shows the aerial view of the area where springs are
located.
Area for
springs
1.3
Sources of Information
In order to successfully carry out the assignment, the following information
was utilized;a) Topographic maps of the area with scale 1:50,000 produced by the
Department of Surveys.
b) Aerial photographs from Google earth
c) Population figures from National statistical office and head count by
World vision Malawi.
d) Related development information of the project area was sourced from
World Vision Malawi and field observations.
Page 15
g) Reference Literature
1.4
1.5
Page 16
CHAPTER TWO
2.1
Introduction
Page 17
The average altitude ranges between 900m and 1000m above sea level.
However, there are some hills which rise as high as 1400m above sea level.
The Supply area is located to the south of Ngamba Hills. In figure 2 above the
area is covered under the blue line. The area has a mild slope southwards and
towards Linthipe River with another slope eastwards, following the direction of
flow for Linthipe River.
2.1.2 Weather
The area is cool with average temperatures ranging from 18 0 C to 210 C.
Average annual rainfall ranges between 900mm and 1000mm.
The rainy season runs from December to April while the dry season runs from
May to November with some months shared between the rainy season and
the dry season. Minimum flows are observed in the months of October and
November.
Welton Eddie Mtonga
Page 18
2.2
No
1
2
3
4
5
6
7
GVH
MADZUM
BI
Khoko
Ndindi
Kulandira
Chimwenje
Nkhono
GVH CHAUWA
Myowe
Galanga 1
Galanga 2
Zukutu 1
Zukutu 2
Kuntheta
Andevu
Kuselikwambiy
8
a
Table 1: Villages that utilized taps from springs in 2011
2.3
Page 19
Proposed
Gwenembe
Springs
Proposed
Sedimentation/S
torage Tank
Proposed
Chauwa Line
Page 20
2.5
Socio-economic Activities
Chilenje is generally an agricultural area with most people engaged in
subsistence farming. Maize is a staple food crop. Other crops include
groundnuts, beans, sugarcanes, vegetables etc. They also rare animals like
cattle, goats, chickens, pigeons etc.
2.6
Infrastructure
The major infrastructures in the area include gravel roads, school blocks, play
grounds, churches and water points like shallow wells and boreholes
2.7
Page 21
2.8
2.9
Proposed Solution
From the studies conducted, the feasible option was to tap excess water from
the existing springs and gravitate it to the target areas. It was further
observed that the springs that had not been developed could also be tapped
to augment the existing supply. It was therefore proposed that water from all
the springs should be transmitted to a common storage tank that would also
act as a sedimentation tank. The outline of the scheme was as follows;1) Five (5No) Spring Capping Structures.
2) Five (5No) transmission lines to a common reservoir.
3) Existing storage tanks for individual springs were to be maintained in
the scheme but control of their operations was proposed through
introduction of new outlets and valves.
4) Common storage/sedimentation tank was proposed at reduced level
1219.2m above sea level.
5) One (1 No) Distribution main to Chauwa was proposed with a branch to
Mkhalala Village.
6) One (1 No) Distribution main to Gwenembe.
Page 22
CHAPTER THREE
3.1
DESIGN CONSIDERATIONS
Introduction
Page 23
The proposed solution outlined in 2.9 provided the basis for the design of the
scheme. According to the design, the existing lines that supplied water to 7No
taps including the one at the maize mill were not supposed to be disturbed. As
such the new design concentrated on the structures that facilitated upgrading
and extension to the target villages
3.2
Page 24
The results revealed that water was not contaminated and hence no
complicated treatment facilities were required. A simple tank that acts as
balancing tank for water demand and also as a sedimentation tank was
adequate. The only change required to the existing facilities design was
reservoir sizing to accommodate the projected demand in 2031
3.3
3.4
Page 25
Page 26
For the application of Colebrook White formula PVC pipes have a roughness
factor of 0.01mm. For Hazen Williamss formula PVC pipes have a C value of
145. These were adopted in the design of this scheme.
3.4.11Residential Head
The scheme was designed for an ideal head of between 5m and 10m at the
tap. However, heads between 10m and 15m were also acceptable.
3.5
Population in 2011
According to Nkhoma Area Development Area Project Design Report (World
Vision Malawi), the target population comprised 4,155 people in 2011. This
population was basically made up of indigenous people of the area. There
were no records of migration or emigration. This data was based on Population
and Housing Census 2008 Main Report and Analytical Report Volume
7(National Statistical Office 2009). There was also head count carried out by
World Vision Malawi.
According to the design the target population was located in the areas with
altitude lower than the altitude of the source. Administratively there were two
group village headmen sharing the supply area. These are GVH Chauwa and
GVH Madzumbi. Each GVH had a number of villages. The spatial distribution of
these villages was that some were located along the foot of Ngamba Hills
while others were located in the Linthipe Valley. There were 1045 people
under GVH Chauwa that were living in the foot of Ngamba Hills in 2011. Table
3 below shows 8No villages located in the upper part of Chauwa that had the
potential to utilize taps from springs. Note that some of these people already
had the service from 4No existing taps.
Chauwa there were 6No villages with a total population of 810 people under
Madzumbi within the same belt that had the potential of utilizing the water
Welton Eddie Mtonga
Page 27
from the scheme. Amongst these people some already had the service from
3No taps.
Table 4 below indicates the villages located in Chilenje Valley but under GVH
Chuwa
Page 28
The table indicates that there were 1000 people in 2011. A combination of
data in table 3 and table 4 gives the total population under GVH Chauwa that
had the potential of benefiting from the project. The population was 2,045
people.
Table 5 below indicates the villages located in the upper part of GVH
Madzumbi that were utilizing taps from springs in 2011. There was a total
population of 810 people in the area.
Page 29
Table 7 below shows the villages under GVH Madzumbi located in the Chilenje
Valley close to Linthipe River.
By combining the data from all the tables, it is noted that there was a total
population of 4155 people in 2011.
3.6
3.7
36 x 4155.
=1.73l/s in 2011.
24 x 60 x 60
Page 30
Flow measurements were taken at the outlets of all the springs. Table 7 below
indicates the flows that were observed from the five springs that had potential
for development.
Field Observations on flows
Time to
Spring
fill 20l
Discharge
No
Buckets
Rate (l/s)
1
14
1.43
2
10
2.0
3
40
0.5
4
21
0.95
5
63
Total
Table 7: Yields of springs
0.32
5.20
From the supply point of view, it was observed that there was plenty of water
for meeting future demand. It was also noted that some of the houses within
the list of villages outlined above are restrained from relying on the scheme
due to topographic location and distance to the nearest tap.
3.8
3.9
Page 31
Pn=Po x(1+r)
where
36 x 6808.
=2.84l/s by the end of the design period.
24 x 60 x 60
It was noted that this demand level was still far much less than the supply of
5.2l/s. Even if the scheme was extended as required, it would supply enough
water up to the design period. 30% of unaccounted for water was added to
the demand and the ultimate figure was 3.69l/s. It was observed that the
figure was still very safe compared to the supply of 5.2l/s.
Page 32
CHAPTER FOUR
4.1
FIELD SURVEY
4.2
4.3
Page 33
The
reduced
level
for
the
proposed
storage/sedimentation
tank
was
Spring Capping 1 was located to the far west. The estimated distance
from the storage tank for this spring to the proposed common storage
tank was 500m.
capping at this site to ensure that all the water from this source was
directed towards the common storage tank. There was untapped water
flowing by the side of this spring. This water was used for irrigating
ii.
vegetables nearby.
Spring capping 2 was located near Spring Capping 1 but to the eastern
side. The estimated distance from this spring to the proposed common
tank was about 450m. There were two spring capping structures which
were poorly located. As a result flows from the two structures were
inadequate. One capping structure was observed to have very small
quantity of water that was stagnant and muddy. However, it was noted
that there was a point nearby that had flows of at least 2l/s. It was
observed that this point could be capped and the flows would rise
significantly. It was therefore proposed that a capping structure should
iii.
iv.
v.
Page 34
Two distribution lines were proposed from the common storage tank. One line
was designed to go to Chauwa Primary School and a nearby village. At the
time of designing this scheme the nearby village was the headquarters of GVH
Chauwa. The line was designed from chinage 0+00 at the proposed common
tank site to chainage 1+600 at Chauwa. Reduced levels varied from 1219.20
m above sea level at the proposed common tank down to 1199.471m above
sea level at the end of the line. Static head at the end of the line was
43.303m. This line was designed to have a branch to Mkhalala Village. The
branch was located at chainage 0+960m and at reduced level 1180.73m. At
the end of the branch the chainage was 1+240m while the reduced level was
1173m above sea level. Static head at the end of the branch was 45.739m.
Page 35
Gwenembe Line
S. Tank
Springs
Linthipe River
Line to
Chauwa
Page 36
CHAPTER FIVE
5.1
Introduction
This chapter looks at detailed design of the individual components of the
scheme except those that were considered to function without disturbance in
the upgrading and extension. The components that were considered in this
chapter comprised the following;a)
b)
c)
d)
e)
5.2
Design Criteria
The general design criteria outlined in chapter three still applied in this
chapter. However, each component had its own design criteria based on the
principles that were supposed to be satisfied. At each stage a particular
component was under design, specific design criteria applicable to that
component were considered in depth.
5.3
Design Population
The population in 2011 was based on the data collected by World Vision in the
target villages. According to Nkhoma Area Development Programme, Project
Design Report,(World Vision Malawi) this data was collected in March 2011.The
data was synthesized using information contained in Population and Housing
Census 2008, Main Report (National Statistical Office).
It was noted that the target villages for the components in this chapter were
located in the lower areas. The villages located along the foot of Ngamba Hills
were already supplied using either the existing taps from the springs or from
alternative sources such as shallow wells that use elephant pumps or
boreholes.
Page 37
Figure 6 below shows a shallow well with an Elephant Pump providing water to
residents along the foot of Ngamba Hills.
It was observed that villages located in upper areas but far away from the hills
could not access water from this scheme due to their topographic locations
and hence were not considered for design purposes of the proposed
improvements. However, villages that use existing taps were accounted for in
evaluating adequacy of flows from the springs in chapter three.
The design population in 2011 for these components was 2,300 people i.e. a
combination of the new target population from GVH Chauwa and the new
target population from GVH Madzumbi.
Table 8 below shows the villages and their respective 2011 population. Design
population was derived by projecting the 2011 population over the design
horizon using the existing growth rates. In this case the population was
projected to 2031 using 20yrs as design period.
As explained in section 3.9, population growth in rural areas follows a
geometric trend due to availability of land and other resources that sustain
human activities. Geometric increase in population is given by the following
formula which has already been described above;-
Page 38
Current
population
Madzumbi
1300
Chauwa
1000
Total
2,300
Table 8: Target Population
5.4
Groth Rate
Population
2.5%
2.5%
20yrs
2130
1639
3,769
in
A per
Yea
Estimated
Daily water
Flow
rate
population
day
demand
required l/s
consumption
m/d
5.175
1.4375
201
2300
in litres
36
1
202
2944
36
6.624
1.84
1
203
3769
36
8.48
2.356
1
Table 9: Water Demand Calculations based on projected Population
It was noted that a total demand of 2.356l/s will be required by 2031.
The major difference from the first approach is that a parameter related to
distance walked to access water was incorporated. According to guidelines
Welton Eddie Mtonga
Page 39
provided by the Malawi Government an individual should not walk more than
500m to access safe water as indicated in section 3.4.7. Additional taps were
therefore provided in a locality even if the number of people per tap was less
than 120 people. Where the number of people exceeded 120 an additional tap
is provided also.
Table 10 below shows the calculations and the parameters involved.
It was observed that the required flow rate in 2031 would be 3.1l/s
5.5
Page 40
The two equations are the same only that there is rearrangement to make the
required item subject. The following are the descriptions of parameters in the
equations;Q=flow either in m3/s or l/s.
D=pipe diameter in m or in mm
G=acceleration due to gravity =9.81
H1=Height of the initial position in m above a datum
H2=Height of the second point of consideration in m above datum.
L=length of pipe under consideration.
Ln = natural logarithm
e =average roughness of pipe material in mm
Welton Eddie Mtonga
Page 41
Transmission
Transmission
Transmission
Transmission
Transmission
Line
Line
Line
Line
Line
No1No2No3No4No 5-
75mm
75mm
75mm
50mm
50mm
of
of
of
of
of
Galvanized
Galvanized
Galvanized
Galvanized
Galvanized
Steel
Steel
Steel
Steel
Steel
pipe
pipe
pipe
pipe
pipe
5.6
Review for the Design of storage tanks and Spring Capping
Structures
Field observations revealed that the storage tanks were stable. There were no
visible cracks. There was no excessive or differential settlement. Figures 7 and
8 show how one of the storage tanks looked like from the side and from the
top respectively. In like manner the spring capping structures were also stable.
Figure 9 below shows how one of the spring-capping structures looked like
from side view. All structures were intact. Interviews with the community
revealed that there had not been any problem since the time they were
commissioned. They only needed cleaning to remove some dirt that
accumulated on the floor due to sedimentation process.
The design life for these types of structures is usually above 30 years. It was
therefore assumed that these structures would be stable throughout the
design horizon of 20 years. Therefore the proposed improvements would
utilize these structures without any modification.
For new springs the same technological design for spring capping structure as
shown in figure 9 was adopted. It was in brickwork with some rocks fitted in
such a way that there was no disturbance to water discharge that was finally
being collected by a pipe underneath downstream.
5.6.1 Design Criteria for the Intake Structure
The spring intake structure was designed to ensure free flow of the water but
at the same time securely protecting it. A wall extending a little above the
maximum level to which the water rises under static conditions should
Welton Eddie Mtonga
Page 42
surround the seepage area. The seepage area was designed to be filled with
stones with enough pore space to allow free flow of water. The lower area was
designed to be cleared to create a pool where water could collect and get
tapped using a strained ended pipe. A V notch was added for flow
measurements.
Page 43
Page 44
5.7
ii.
iii.
Page 45
Pipeline to
Gwenembe
Storage Tank
Pipeline to
Chauwa
Case 1:
Sedimentation Tank
Page 46
of the design is judged on its ability to maintain the required throughput and
the required effluent water quality under adverse raw water quality conditions
which generally occur at the end of the dry season or during the first flood of
the wet season when riverside pollutants are flushed downstream. In rural
water supply systems the approach is simplified due to lack of capacity to
handle chemicals. At the same time the water is assumed to be of
substantially good quality due to natural treatment processes in the aquifer. In
this scheme there were two advantages.
i.
ii.
The water comes from springs which are natural screening devices.
The water passes through other storage tanks that are located
immediately
after
spring
capping
structures.
These
settle
out
This criteria ensures that particles with falling velocity of more than or equal
to surface loading rate will be effectively removed by the tank. Looking at the
environment the most likely type of suspended solid were soil particles. Area
of the tank was evaluated from other requirements and then it was checked if
surface loading removes the desired particles.
The other parameter considered in the design of a sedimentation tank is
detention time. This depends on several factors and amongst them are the
following:a.
b.
c.
d.
e.
Quantity of flow.
Amount of suspended particles.
Size of suspended particles.
Surface area of water in the tank
Presence of a reservoir downstream.
t is the detention time. The design flow was 3.1l/s. Therefore the minimum
volume of the tank should be 0.0031x60x60 m3=10.8m3.
Page 47
5.7.3.2
Case 2:
Storage Tank
In order to assess the adequacy of the tank in terms of evening out hourly
demand there is need to look at demand variations across the day. There is a
typical trend where by the demand reaches the peak between 6.00am and
9.00am. It falls slightly thereafter and rises again to another peak between
5.00pm and 8.00pm. There is generally no water drawing between 8.00pm
and 4.00am. This leads to a simple assumption that water is collected over
16hrs in a day and hence the 16hr demand.
There are typical factors based on long-term observations on how people draw
water in rural areas of Malawi and indeed nearby countries. These factors are
applied to find the amount of water that is needed in each hour of the day
based on total daily demand. The cumulative amount is evaluated for each
hour. Balancing requirement is found by subtracting the lowest accumulated
value from the highest accumulative value (Ref: Santiago Alnararch, Gravity
Flow Water Supply.
Table 11 below shows a summary of calculations carried out in an excel
spreadsheet based on demand of 3.1l/s which translates to a total demand of
267.84m3 per day.
Page 48
Page 49
Looking at the setting of the supply area, there were no critical items requiring
water for fire- fighting. This component was therefore neglected. An additional
volume of 5% of the balancing requirement was added for emergency cases.
This led to a total volume of 107.31m3.
The other approach for calculating the volume of the tank is stipulated by
Design Manual for Piped Water Supply Systems, Ministry of Works, Malawi
Government by Carl Bro International, which states that as a minimum
requirement tank size must be 2 times the difference between the 16hour flow
and 24 hour flow.
Tap demand was taken to be 3.1l/s as evaluated above. The 24 hour flow was
calculated by multiplying by 2/3. The result was 2.067l/s. The difference
between the two was 1.033l/s. Thus minimum tank volume was evaluated as
1.033x16x3.6x2=119m3.
The required tank volume was the higher between the two values evaluated
above. This was 119m3.
5.7.4 Tank Dimensioning
A rectangular tank was chosen for two reasons namely:a) It is easy to construct.
b) The tank was designed to serve as a sedimentation tank as well. A
circular tank would bring complications since water has to flow
upwards.
The major forces in a tank are the hydrostatic forces which are evaluated by
the product of water density, acceleration due to gravity and the height. The
only variable is the height. It was therefore important to limit height in order
to reduce hydrostatic forces. Taking height H=2m then the product of width
and length should help to determine volume i.e. L x B=59.5. Take L=8.5 then
B=7.0
The tanks internal dimensions were found to be as follows;L=8.5m
B=7.0m
H=2.0m
Welton Eddie Mtonga
Page 50
Tank partitioning was noted to be necessary and this was designed in concrete
work. Walls were introduced dividing the length and breadth in half each. That
means that there were four compartments with baffle walls inside.
The outside dimensions of the tank were as follows;Length =9.1m
Width =7.6m.
5.7.6 Tank Site Conditions
The geology of the proposed tank site revealed that the area was underlain by
a mature granitic rock that protruded in some places. This granitic rock was
considered to be strong enough to support the foundation of the proposed
tank. The same rock structure supports the existing infrastructures. The rock
was found at an average depth of about 500mm.
The average slope of the tank site was found to be about 1:7. The upper side
of the tank site would require considerable cutting to reach the required
formation.
The following assumptions have been applied in the design of the tank.
Page 51
5.7.7.2
Top Slab
The top slab was designed to carry self-weight of concrete including screed.
Looking at the arrangement, the slab was two way spanning because effective
L
= 2 . Bending moments and shearing forces were determined using
B
appropriate coefficients from Table 3.14 of BS 8110 part one. Deflection and
cracking were checked at the centre of the spans. Even though shear was not
critical, it was also checked at supports. Reinforcement for torsion was
provided at the edges of the slab.
Design Calculations are found in appendix five.
5.7.7.3
Concrete Wall
The wall was designed to resist bending moments and shearing forces
generated by hydrostatic forces of water. The bending moments and shearing
forces were determined from relevant coefficients. Moment Distribution
method was applied to determine member moments in the lateral direction.
The wall was designed for hoop forces and bending moments. Deflections,
shear and cracking were checked at appropriate critical sections.
Design calculations are found in appendix five.
5.7.7.4
Reinforced concrete raft slab/floor system was adopted in order to satisfy both
the architectural and structural requirements of the tank. The design approach
for solid rafts is to treat them as inverted slabs. Punching shear and cracking
were checked.
Welton Eddie Mtonga
Page 52
5.7.7.5
5.8
Page 53
Table 12 below shows how peak factors were varied in assigning flow
requirements for branches.
No of Taps
Required Flow in l/s
1
0.15
2
0.28
3
0.40
4
0.50
5
0.58
6
0.65
7
0.70
8
0.73
9
0.74
10
0.75
>10
0.075X No of Taps
Table 12: Required flow (l/s) for respective No of Taps
This implies that the figure indicated in the draw off column of the design
calculations was related to the projected number of taps that could be
connected by 2031. The actual number of taps in the year of project
implementation was dependent on the current set up of communities and
their respective population.
In this scheme roads from the source to the target communities were
generally absent. Since the flow was designed to be by gravity the terrain of
the area and proximity of the target communities dictated the alignment of
lines. In some cases the existing physical features prohibited accessibility and
as such the proposed lines were diverted to proper locations. The plan for pipe
alignment is shown in figure10 above.
5.8.3 Pipe Materials
Page 54
In this scheme PVC class 10 was specified for all pipelines except in areas
where the lines crossed gullies and rocky areas. HDPE was proposed for
community connections.
functionality.
From the design flow and the selected pipe size calculate flow velocity.
Check the velocity compliance with standards.
Calculate static head.
Establish the class of the pipe required from the list of commercially
In this exercise Hazen Williams Formula was utilized to calculate pipe losses.
The formula is indicated as follows:
13
1.85
10 x Q x L
H L = 1.77 x 1.85
4.865
C xD
where
H L =Head loss in m
Q=Flow rate in l/s
L=Pipe length in kilometres
C=Constant and is dimensionless and is dependent on pipe materials
D=Pipe diameter in mm
Welton Eddie Mtonga
Page 55
Table 13 below shows the values of C for different materials that were applied
in the analysis.
Pipe Material
Value of C
PVC or HDPE
145
GS
120
Table 13: C values for pipe materials
Velocity of water was limited to values between 0.5 to 2.0 m/s. This was
applied to ensure that stagnation due to low velocities is prevented while at
the same time pressure surges that cause water hammer, due to high
velocities are also prevented. The formula for velocity is as follows.
V=
Q
where
A
Page 56
In the Design Calculation Tables;Hydraulic Gradient Level (HGL) =Static Head Head loss
Working Pressure (WP) =HGL-Ground Level.
5.8.5 Hydraulic Design of the Distribution Line between the Storage Tank
and Chauwa Primary School
The hydraulic calculations revealed that 50mm PVC pipe was adequate to
deliver the required flow from chainage 0+0.00m to chainage 0+960m. It was
recommended to reduce this diameter to 40m at this chainage and a further
reduction to 32mm at chainage 1+520m which should be maintained until the
end of the pipeline at chainage 1+600m. Hydraulic analysis also revealed that
there was a working pressure of about 23m at the end of the line. This
pressure was adequate to make a minor extension on it hence a provision of
an end cap at the far end.
There was a draw off of 0.58l/s at Mkhalala profile junction. This was the flow
requirement for Mkhala Village. The total number of taps for Chauwa line was
14. Subtracting 5 taps for Mkhala line from 14, 9 taps remained for the rest of
the pipe. The second draw off of 0.4l/s was lumped at this point for design
purposes. The actual points for draw-offs would depend on the communitys
requirements as the village was concentrated. In other words the actual
connections were expected to be distributed along the main line.
For Design Calculations refer to Appendix 2
5.8.6 Hydraulic Design of the Distribution Line between the Storage Tank
and Gwenembe
Hydraulic calculations revealed that 63mm PVC pipe was adequate to deliver
the required flow from chainage 0+0.00m to 1+260m. At this chainage the
pipe diameter was reduced to 50mm. The 50mm diameter run to a chainage
of 2+660m where further reduction to 40mm was recommended. Like in the
Page 57
line to Chauwa, hydraulic analysis revealed that there was a working pressure
of about 27m at the end of the line.
This line passed through a place that was very close to Njovu Village. This
village was relatively big and required at least three taps in 2011. The
connections could be directly installed at chainage 1+260m. There was a
projection of 5taps by 2031 and hence a draw of 0.58l/s. This demand was
lumped at this point because the set-up of villages demanded that one pipe of
at least 32mm be connected at one point. The demand would be distributed
to the rest of the nearby villages using this line.
Again the draw off of 0.4l/s towards the end of the line was just for design
purposes so that the line did not have to continue with a constant diameter.
The actual set up would depend on community requirements which essentially
meant that the demand would be distributed.
Page 58
5.8
Relocated Villages
During desk study it was observed from the map (produced in 1972) that
there were some villages that needed separate profiles as branches from the
two main lines. These villages included Mjolo and Kasadwa. However, these
villages were not observed in their expected places during field survey. They
got relocated either closer to the hills or closer to Linthipe River. One distinct
observation was that Gwenembe looked a bit extended compared to what is
presented on the map. Interviews with villagers revealed that the area has
three villages namely Kasinje, Gwenembe and Julius.
Figure 11 below shows some of the areas that appear to have communities on
the map but there is an empty space in the field.
Figure 11: Project area indicating communities close to hills and Linthipe
River but empty in between
5.9
Profiles
Page 59
The invert level of the pipe is dictated by pipe size, soil conditions, expected
loading on top of the pipeline and risk to vandalism. In this scheme the
community expressed willingness to have the facility and to contribute
towards its implementation. In this case it was assumed that the risk of
vandalism from the communities is minimal. However, the area is not closed
up. It can be accessed by outsiders who may vandalize the facilities.
In all cases pipe diameters are 110mm or less. Generally minimum cover over
the top of the pipe should be as follows:
The lines from the spring boxes will cross the road. Therefore they will be
subjected to heavy loading from passing vehicles.
Considering all these factors the invert level for all main lines is taken to be at
900mm below the surface while the smaller branches are put at 600mm.
5.10
Tap Locations
Taps are located in all areas where the population is concentrated. In the
Chauwa Distribution Line there is Chauwa Primary School which needs a tap of
20mm because it is an institution. In general each tap is designed to serve a
maximum of 120 people. Where communities have more than 120 people
additional taps are provided. The other limiting factor is that people should
not walk more than 500m to access water. Therefore isolated communities
with more than 500m radius will have taps allocated to each of the
communities.
According to the information gathered during field visits and surveys, taps
supplying communities close to the springs will be maintained.
5.11
Page 60
In general all PVC pipes are jointed using rubber-rings located at one end of
each pipe. The end without a rubber-ring is carefully inserted into the end with
a rubber-ring. Where the PVC pipe is jointed to a GI pipe like in case of stream
crossings, an appropriate size of VJ coupling or CI Joint may be used.
HDPE pipes are jointed using couplings of appropriate sizes determined by the
pipe size.
Y fittings will be installed at all places where there are branches. The size of
the fittings will be dictated by the diameter of the branch. Please refer to the
profiles for specifications of each fitting.
Sluice Valves will be located in each line just after the branch. Air valves will
be installed on all high spots to prevent air-locks. Wash-out valves and drains
will be provided on all lower spots to ensure that water is flushed out during
maintenance.
Gate valves will be installed to all smaller lines immediately after branches to
ensure that they are isolated when need arises. In like manner gate valves or
stopcocks will be installed just before taps.
A section of about 5m to the stand pipe including the stand pipe itself will
utilize GI pipes. The GI pipes will be fitted to HDPE using couplings of
appropriate size. Bends, elbows and bib taps will be of GI.
Isolation valves have been proposed in section which are more than 2.5Km
long
Adaptors or reducers will be installed where a smaller pipe is joined to a larger
pipe.
5.12
Thrust Blocks
Thrust blocks have been proposed for all valves (but not gate valves), bends,
tees and reducers. The general requirement is that thrust blocks must be
strong enough to resist the maximum expected pressure.
Page 61
5.13
CHAPTER SIX
6.1
Introduction
The conclusion and recommendations provided hereunder were based on the
conditions observed at the time of field investigations and design of the
scheme in September 2011.
6.2
Conclusion
Field investigations revealed that it is possible to upgrade and extent Chilenje
Rural Piped Water Scheme to serve more people residing in the Linthipe Valley.
There is adequate water to meet the demand over the design period. The
terrain of the area permits water transmission by gravity from the sources to
the storage reservoir and from the reservoir to all water points.
6.3
Recommendations
The following recommendations were proposed: In view of the growing population against a constant yield from the
springs, all the available waters should be trapped using the same
Page 62
Page 63
APPENDICES
Page 64
APPENDIX 1
APPENDIX 3
GWENEMBE PROFILE
SURVEY DATA, DESIGN CALCULATIONS AND HYDRAULIC CHART
Page 65
APPENDIX 4
MKHALALA PROFILE
SURVEY DATA, DESIGN CALCULATIONS AND HYDRAULIC CHART
Page 66
APPENDIX 5
References
Welton Eddie Mtonga
Page 67
10. Ian Batty and Roger Westbrook, The Design of Water Retaining Structures.
11. Indian Standard, Code of Practice for Concrete Structures for the Storage of
Liquids, Part IV, Design Tables.
12. IRC, Small Community Water Supplies.
13. Mackenzie L.D., Water and Wastewater Engineering, Design Principles and
Practice.
20. National Statistical Office, Population and Housing Census, Main Report,
2008.
21. N. Krishnan Raju and R.N. Pranesh, Reinforced Concrete Design, IS 456-200,
Principles and Practice.
22. N. Trifunovic, Introduction to Urban Water Distribution.
23. P. K. Swamee and A.K Sharme, Design of Water Supply Pipe Networks.
24. R. Cheng, Design Tables to BS 8007, Design of Concrete Structures for
Retaining Aqueous Liquids.
25. R. D. Anchor, Design of Liquid Retaining Concrete Structures.
26. Republic of Malawi, Gravity Fed Rural Piped Water Schemes, Rural Water
Operators Handbook.
Welton Eddie Mtonga
Page 68
27. T.D. Jordan Jr. Handbook of Gravity Flow Water Systems for Small
Communities
28. T.M. Walski, D.V. Chase, D.A. Savie, W. Grayman, S. Beckwith and E. Kelle,
Advanced Water Distribution Modeling and Management
29. Santiago Alnarach, Gravity Flow Water Supply.
30. UNHABITAT, Gravity Water Supply System Design Tools.
Page 69