MD 119 (Great Seneca Highway)

.Intersection Improvement Project

At Kentlands Avenue/Orchard Ridge Drive


.

CONSTRUCTION BEGINS THIS SPRING.

The Maryland State Highway Administration (SHA) is resurfacing a section of MD 119 (Great Seneca Highway) in
Gaithersburg, Montgomery County, as part of a $765,000 project at the Kentlands Boulevard/Orchard Ridge Drive
intersection. Weather permitting, improvements should be complete by late fall 2015. Utility conflicts within the work
zone delayed the start of work late last fall and necessitated an adjustment of the projects original estimated
completion date of summer 2015.
SHA designed the project to increase the left turn lane vehicle capacity to address current and future traffic demands
along westbound Orchard Ridge Drive, improve left turn movements from MD 119 onto Orchard Ridge Drive and
enhance pedestrian safety across MD 119.
Work for the 0.6-mile project consists of:

Extending the westbound left turn lane on Orchard Ridge Drive to provide a total of 350 feet of vehicle storage
capacity;
Modifying the median on Orchard Ridge Drive to improve turning movements from southbound MD 119 onto
Orchard Ridge Drive;
Modifying the median and realigning the crosswalk across the northern leg of MD 119 to improve pedestrian
visibility for drivers making right turn movements from Orchard Ridge Drive onto northbound MD 119;
Constructing sidewalk ramps, curb and gutter median cut-throughs, and detectable warning surfaces for
Americans With Disabilities (ADA) compliance; and
Resurfacing all traffic lanes and applying new pavement markings consistent with the new improvements.

Pedestrian traffic will be maintained at all times during construction. Signs will direct pedestrians to safe crossings
within the project limits. SHA may use electronic message boards, construction cones, barrels, arrow boards and a
flagging operation to direct motorists through the work zone.

.TEMPORARY LANE CLOSURES


To complete the work, crews may temporarily close one lane in either direction of MD 119:

Weekdays, northbound, between 6 a.m. and noon and southbound between 10 a.m. to 7 p.m.;
Overnight, Sunday through Thursday, between 9 p.m. and 6 a.m.; and
Weekends, northbound, between 6 a.m. and 10 a.m. and southbound between 6 a.m. and 7 p.m.

QUESTIONS FF
The following SHA representatives are available to answer questions regarding roadwork on this
MD 119 project:

Matthew Bartgis, SHA Project Engineer, mbartgis@sha.state.md.us, 301-990-0500


Vince Rethemeyer, SHA District 3 Area Engineer, vrethemeyer@sha.state.md.us, 301-513-7334