Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Understanding the S-Curve Theory for Project Management

Monitoring
written by: ciel s cantoria edited by: Michele McDonough updated: 5/26/2011
This article discusses S-Curve theory and how it is used in project management as a tool for monitoring the growth, progress and
performance of ongoing projects. Understand the S-Curve model, its analysis, data and schedules needed to create the graph that
reveals deviations from baseline metrics.

Introduction to the S-Curve Concept

An understanding of S-Curve theory and its analyses will help learners and team members grasp the importance
of monitoring the progress and growth of an ongoing projectat a specific stage or percentage of completion.
Outside of the technical jargon, the S-Curve model simply makes use of the projected number of man-hours and costs to
complete the project vs. the actual number of hours and costs incurred within the same time frame. The proposed time, man-hour
and cost data are referred to as the baseline data.

HR Jobs in Qatar
gulftalent.com

Careers in HR and Recruitment with top companies in Qatar


Ads by Google

Understanding the S-Curve Model

The S-Curve is a form of mathematical theory, which aims to represent the utilization of resources over the proposed time of the
project. Simply stated, the curvature illustrates the side by side comparisons of the actual time and expenditure components vs.
the proposed time and costs allocations of specific resources.
As a tracking tool, comparisons of different S- Curves against the standard S-Curve help in monitoring the growth or progress of
the project. Data that is simultaneously plotted in graph form will clearly present how efficiently the team has performed so far,
in accordance with the time or budget limitations.

Two or more curved lines running symmetrically should both be flat at the beginning and become steep in the center and become
flat again towards a convergence at the projects completion date. This is how most project timelines would be depicted. In
todays highly technological work environment, there are varioussoftware-scheduling packages that can automatically generate
these S-Curves.
However, the matter of understanding the significance of its theory and its analyses is of utmost importance.
Image Credit: Coupled S-Curves courtesy of Wikimedia Commons

Plotting and Analyzing the S Curves


If done accurately, the S-Curve analysis of the "actual progress to-date curve" against the "baseline curve" facilitates the
achievement of project goals by providing a warning of any project deviations from the baseline standards.
The S-Curve is constructed using the dates on the X-Axis and the calculated values on the Y-Axis and by plotting data extracted
from baseline or production schedules for each task.
The Necessary Tools
The Baseline Schedule: It contains information about the actual start date and finish date as well as the information on proposed
man-hours and expenditure allocations. Use the data contained in this schedule to create the Baseline S Curve.
The Production Schedule: It contains information of the actual man-hours and expenditures incurred for a particular stage of the
project.

The Different S-Curve Models and Analysis


The Standard S-Curve Metrics:
Baseline S-Curve:
This is the S-Curve against which all other S-Curves will be compared as it comprises the proposed allocation of expenditures
and man hours to be used for the projects completion within a proposed duration.
The Growth Metrics this makes use of the Target S-Curve:
The Target S-Curve represents the modified Baseline S-Curve figure, inasmuch as the constant monitoring of project
performance could result to certain adjustments of the baseline elements. A new standard will then be calculated and becomes the
representative of a new set of metrics.
They are, however, called target values, to distinguish them from the originally proposed time and costs. As such, these values
now represent the new set of metrics after the original baseline was modified. They are applicable as bases for analyses of
succeeding work performances after the adjustment cut-off date.
Comparisons between the Baseline and the Target curvatures denote growth of the project as far as scope is concerned. Plotting
of the Target S-Curve may finish above or below the Baseline S-Curve, in which case:

If the scope increases and the baseline duration or time allotment is fixed, then it is likely that the project will becompleted
beyond the targeted date. This results to what is called the Project Slippage, or the difference between the targeted finish

dates vs. the baseline finish date.


If the scope increases and the baseline costs or proposed costs are fixed, then it is likely that the project will be completed

beyond the budgeted costs, which could result to fewer profits or even potential losses.
If the scope decreases and the baseline duration or time allotment is fixed, then it is likely that the project will be completed

ahead of the targeted date.


If the scope decreases and the baseline costs or proposed costs are fixed, then it is likely that the project will be completed at
less than the budgeted costs, which spells greater profits.


The Progress Metrics This is a comparison between the Target S-Curve and the Actual S-Curve, in which the latter is a
measure of the actual man-hours and expenditures of a project on a specific completion stage date.
Ordinarily, the Actual S-Curve is expected to run below the lines of the Target S-Curve, since the results of constant monitoring
entails compliance and observance of the targeted time and costs. Hence, the two curved lines are expected to meet or converge
towards the end of the project completion.
If the curvatures present a graph where the Actual S-Curve runs open-ended above the Target S Curve as of cut-off monitoring
date, consider the possibility of errors in the data contained in the production schedules. A careful review should be made to
pinpoint unrealistic values of man-hours and costs incurred for the already completed stage.
Image Credit S-curve(Asymmetric).jpg courtesy of Wikimedia Commons

Value and Percentage Metrics:


Cost vs. Time S-Curve: This type of analysis is suitable for projects that require both labor and non-labor intensive
elements. The main concern here is the cumulative costs at a specific stage of the project and its effect on the cash flow as
well as the potential risks of exceeding the allotted costs.
Creating the Cost vs. Time S-Curve
Use the actual cumulative amount of expenditures incurred from baseline start date to cut-off date of progress stage and compare
the S curve created against the Baseline S curve for total cost allotment for the same cut-off date.

Man Hours vs. Time S-Curve: This type of analysis is suitable for projects that are estimated as labor intensive, in which
the project manager has to know the cumulative amount of man hours worked at a specific stage of the project. Results of
the graph will provide the basis for adjustment, whether there is underperformance that warrants additional labor force or

the implementation of closer supervision.


Creating the Man Hours vs. Time S-Curve:
Use the actual cumulative amount of man-hours worked from baseline start date to cut-off date of progress stage and compare the
S curve created against the Baseline S curve for man-hour allotment for the same cut-off date.
As a note, the models and analyses can be used to monitor the different phases or tasks of a project. Since time is of the essence,
the convenience of using the most appropriate and multi-faceted project management software allows the application of this
theory for different project management scenarios

You might also like