AmAL HRSG Schedule PDF

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

AL HASSAN ENGINEERING CO S.A.O.G.

OMAN

AMAL HEAT RECOVERY STEAM GENERATOR (HRSG) - 1

B- 200

(C311333)
Activity ID

Activity Name

Original Duration % Start


Duration Complete

AMAL HEAT RECOVERY STEAM GENERATOR ( HRSG) - 1


Start Up

Finish

660

0% 27-Mar-12

15-Jan-14

0% 27-Mar-12

05-Apr-12

ST010

Award of Contract / Commencement Date

0% 27-Mar-12

ST020

Kick Off Meeting

0% 05-Apr-12

618

0% 07-May-12

15-Jan-14

MS01

Mobilization

0%

07-May-12*

MS02

Site Establishment

0%

25-Jun-12*

MS03

Upon issue of purchase order for 6.6 KV, 415V, IAC, UPS (A/C & D/C)

0%

26-Jun-12*

MS04

Engg-Detail Degn,IPF/HAZOP,SAFO P,design calcul'n, CCMS check sheets 0

0%

25-Mar-13

MS05A

Upon completion of civil foundations for HRSG and Ancillaries

0%

11-Feb-13*

MS05B

Civil works Completion - HRSG Control Building, blow down pit and pipe racks
0

0%

22-May-13*

MS06

Rcpt Eqpt-Matl for 6.6 KV, 415 V panels, IAC, DC & AC UPS, Bulk piping

0%

22-Apr-13*

MS07

Erection completion of HRSG columns, Installation floor, wall casing, roof beam,
0
module
0%and pump package
17-Sep-13
erection

MS08

Construction completion for electrical works, instrument works, Energizing 6.6


0 KV, 4150%
V panels and IAC27-Sep-13

MS09A

Upon Mechanical completion EPC scope of work

MS09B

Upon completion and precommissioning of HRSG package including including


0 all auxiliaries
0%

27-Oct-13

MS10

Completion & De-mobilization

0%

15-Jan-14*

424

0% 27-Apr-12

24-Jun-13

Milestone

0
0

0
0

Major PDO Inputs (Customer Responsibility)


Major PDO Obligation

0%

22

0% 27-Apr-12

18-May-12

Receipt of editable drgs & initial eng inputs for process

0% 27-Apr-12

27-Apr-12

PDOINP020

Receipt of inputs for Civil Foundations (including HRSG)

0% 16-May-12

16-May-12

PDOINP030

Receipt of Engineering in puts for Mechanical

0% 18-May-12

18-May-12

30

0% 26-May-13

24-Jun-13

30
30

0% 26-May-13
0% 26-May-13

24-Jun-13
24-Jun-13

Mechanical and Piping


FIMHRSG1010
Diverter Damper\Guilliotin gate valve\seal air system
FIMHRSG1020

Main steel structures

12

0% 26-May-13

06-Jun-13

FIMHRSG1030

Modules

12

0% 01-Jun-13

12-Jun-13

FIMHRSG1040

Casing

12

0% 07-Jun-13

18-Jun-13

FIMHRSG1050

Duct

10

0% 07-Jun-13

16-Jun-13

FIMHRSG1060

Stack

12

0% 13-Jun-13

24-Jun-13

FIMHRSG1080

Feed water pumps

0% 13-Jun-13

20-Jun-13

Primary Baseline

Summary

Project Start Date :27-Mar-12

1 of 12

Actual Work
Remaining Work
Critical Remaining Work
Milestone

Project End Date :15-Jan-14


Data Date:27-Mar-12

2013
J

2014

F M A M J Jul A S O N D J

27-Sep-13*

PDOINP010

Free Issue Material- for HRSG

2012
M A M J Jul A S O N D

Primavera Systems, Inc.

Date
02-Apr-12

Revision
Checked
PROJECT ... ARD

Approved
KGB

AL HASSAN ENGINEERING CO S.A.O.G. OMAN

AMAL HEAT RECOVERY STEAM GENERATOR (HRSG) - 1

B- 200

(C311333)
Activity ID

Activity Name

Original Duration % Start


Duration Complete

FIMHRSG1100

External Heat Exchanger, Expansion Tank, recirculation pumps

FIMHRSG1110

Purge air blower with Accessories

FIMHRSG1120

Interconnecting piping

Finish

0% 15-Jun-13

22-Jun-13

0% 15-Jun-13

22-Jun-13

12

0% 13-Jun-13

24-Jun-13

HRSG Power and control cable

12
12

0% 13-Jun-13
0% 13-Jun-13

24-Jun-13
24-Jun-13

FIMHRSG1140

HRSG Lighting and Earthing materials

10

0% 15-Jun-13

24-Jun-13

FIMHRSG1150

HRSG Electrical bulk Materials ( Cable ladder, JB )

0% 17-Jun-13

24-Jun-13

FIMHRSG1200

HRSG Aviation light panel and JB's

10

0% 15-Jun-13

24-Jun-13

MAC system ( FGS, IPS, FCS )

30
25

0% 26-May-13
0% 26-May-13

24-Jun-13
19-Jun-13

FIMHRSG1170

HRSG Field instruments

20

0% 26-May-13

14-Jun-13

FIMHRSG1180

HRSG control cables

25

0% 31-May-13

24-Jun-13

FIMHRSG1190

HRSG Instrumentation bulk materials

30

0% 26-May-13

24-Jun-13

361

0% 07-Apr-12

02-Apr-13

361

0% 07-Apr-12

02-Apr-13

0% 07-Apr-12

0% 16-Apr-12

16-Apr-12

20

0% 17-Apr-12

14-May-12

Electrical
FIMHRSG1130

Instrumentation
FIMHRSG1160

Engineering
General Activities and Mi lestones
G100

Award of Engineering contr ac t

G110

Kick-off meeting

G112

Data Collection and input Verification

G114

Reciept of PDO approved HRSG & auxillary documents for Process Engineering
0

0% 30-Apr-12

G116

Reciept of PDO approved HRSG & auxillary documents for Civil Engineering0

0% 19-May-12

G118

Reciept of PDO approved HRSG & auxillary documents for Mechanical Engineering
0

0% 19-May-12

G122

Site Vis it

0% 28-Apr-12

30-Apr-12

G140

DESIGN Review meeting

0%

17-Jul-12

G142

Electrical Design review meeting

0%

01-Oct-12

G150

HAZOP Review meeting

0%

10-Nov-12

G160

60% Model review meeting

0%

13-Nov-12

G200

SAFOP Review meeting

0%

18-Dec-12

G202

IPF Review meeting

0%

07-Jan-13

G250

Issue Final Drgs - AFC

0%

02-Apr-13

335

0% 25-Apr-12

25-Mar-13

Process Engineering
R100

Design Basis

20

0% 25-Apr-12

22-May-12

R110

PFS

15

0% 02-May-12

22-May-12

Primary Baseline

Summary

Project Start Date :27-Mar-12

2 of 12

Actual Work
Remaining Work
Critical Remaining Work
Milestone

Project End Date :15-Jan-14


Data Date:27-Mar-12

2012

2013

M A M J Jul A S O N D

Primavera Systems, Inc.

Date
02-Apr-12

2014

F M A M J Jul A S O N D J

Revision
Checked
PROJECT ... ARD

Approved
KGB

AL HASSAN ENGINEERING CO S.A.O.G. OMAN

AMAL HEAT RECOVERY STEAM GENERATOR (HRSG) - 1

B- 200

(C311333)
Activity ID

Activity Name

Original Duration % Start


Duration Complete

Finish

R120

PEFS : issued for review

22

0% 16-May-12

16-Jun-12

R122

PEFS : issued for Design review

10

0% 30-Jun-12

11-Jul-12

R130

Process Datasheets for Equipments

15

0% 23-May-12

12-Jun-12

R132

Process Datasheets for Control valves

10

0% 17-Jun-12

27-Jun-12

R134

Process Datasheets for Field Instruments

0% 14-Jul-12

21-Jul-12

R140

Equipment List

0% 13-Jun-12

20-Jun-12

R150

Line List

10

0% 30-Jun-12

11-Jul-12

R160

Tie-in & Shutdown Philosophy

15

0% 17-Jun-12

04-Jul-12

R180

Design Review meeting

0% 17-Jul-12

17-Jul-12

R190

Design Review Report & Close out actions report

30

0% 17-Jul-12

28-Aug-12

R192

HAC drawings

0% 28-Aug-12

08-Sep-12

R194

Process Docs. & Drwgs : incorporate DR comments & Re-issue for Hazop35

0% 08-Sep-12

27-Oct-12

R210

Hazop review meeting

0% 07-Nov-12

10-Nov-12

R220

Hazop review Report

0% 11-Nov-12

19-Nov-12

R230

Hazop review close-out actions report

25

0% 20-Nov-12

24-Dec-12

R240

PEFS Final - AFC

10

0% 29-Jan-13

11-Feb-13

R242

Plant Operating manual

35

0% 22-Jan-13

11-Mar-13

R244

CCMS

30

0% 12-Feb-13

25-Mar-13

Civil works Engineering

303

0% 19-May-12

17-Mar-13

C102

Site Grading, Fencing & Access Road drgs : AFC

20

0% 09-Jun-12

03-Jul-12

C104

HRSG & accesories foundation Design & Drwgs : AFC

60

0% 19-May-12

07-Aug-12

C106

Blowdown pit drawings : AFC

40

0% 14-Aug-12

09-Oct-12

C120

Control Building Architectural Drgs : AFC

20

0% 05-Jun-12

01-Jul-12

C130

Control Building foundation Drgs : AFC

25

0% 16-Jun-12

17-Jul-12

C140

Control Building Super structure Drgs : AFC

30

0% 11-Jul-12

21-Aug-12

C150

Control Building Misc Drgs : AFC

35

0% 15-Jul-12

01-Sep-12

C152

Piperack Design & drwgs : AFC

45

0% 24-Oct-12

25-Dec-12

C160

Equipment Foundation drgs : AFC

45

0% 12-Nov-12

13-Jan-13

C170

IA Shelters : AFC

35

0% 17-Dec-12

03-Feb-13

C180

Pipe Support & Sleeper Drgs : AFC

40

0% 07-Jan-13

03-Mar-13

C182

Misc shelters , Platforms , crossovers

35

0% 28-Jan-13

17-Mar-13

204

0% 13-May-12

02-Dec-12

Mechanical Engineering
Primary Baseline

Summary

Project Start Date :27-Mar-12

3 of 12

Actual Work
Remaining Work
Critical Remaining Work
Milestone

Project End Date :15-Jan-14


Data Date:27-Mar-12

2012

2013

M A M J Jul A S O N D

Primavera Systems, Inc.

Date
02-Apr-12

2014

F M A M J Jul A S O N D J

Revision
Checked
PROJECT ... ARD

Approved
KGB

AL HASSAN ENGINEERING CO S.A.O.G. OMAN

AMAL HEAT RECOVERY STEAM GENERATOR (HRSG) - 1

B- 200

(C311333)
Activity ID

Activity Name

Original Duration % Start


Duration Complete

M120

MR : Service water tanks

M122
M124
M130

MR : Service water Pumps

M134

Finish

0% 13-Jun-12

21-Jun-12

Bids review ,TQ & TBA - Service water Tanks

15

0% 14-Jul-12

01-Aug-12

Vendor Doc review -Service water Tanks

40

0% 29-Sep-12

21-Nov-12

0% 23-Jun-12

01-Jul-12

Bids review ,TQ & TBA - Service water Pumps

15

0% 23-Jul-12

12-Aug-12

M136

Vendor Doc review -Service water Pumps

40

0% 08-Oct-12

02-Dec-12

M140

MR : IA compressor package

0% 13-May-12

21-May-12

M142

Bids review ,TQ & TBA - IA compressor package

15

0% 12-Jun-12

01-Jul-12

M144

Vendor Doc review -IA compressor package

40

0% 27-Aug-12

21-Oct-12

M222

MR : HVAC

0% 02-Jul-12

08-Jul-12

M252

TQ / TBA - HVAC

15

0% 30-Jul-12

19-Aug-12

M254

Vendor Doc review - HVAC

30

0% 19-Sep-12

30-Oct-12

279

0% 15-May-12

17-Feb-13

Electrical Engineering
E100

Electrical Load List

10

0% 16-May-12

29-May-12

E103

MR's for Electrical equipments

25

0% 15-May-12

18-Jun-12

E120

SLD's

15

0% 16-May-12

05-Jun-12

E123

Bid Receipt & TAQ

20

0% 09-Jul-12

05-Aug-12

E124

Vendor Doc Review

50

0% 10-Sep-12

18-Nov-12

E127

Electrical Equipment layout

20

0% 05-Jun-12

01-Jul-12

E129

Electrical Design Review meeting

0% 01-Oct-12

01-Oct-12

E130

SAFOP-2 review meeting

0% 18-Dec-12

18-Dec-12

E136

SAFOP-2 close out actions Report

20

0% 18-Dec-12

15-Jan-13

E140

Electircal Layout's (Cable,Lighting,Earthing)

50

0% 03-Dec-12

11-Feb-13

E160

Cable Schedule

15

0% 27-Jan-13

17-Feb-13

E240

Bulk MTO Electri cal

10

0% 27-Jan-13

10-Feb-13

336

0% 02-May-12

02-Apr-13

Piping Engineering
D100

Plot Plan : IFR

10

0% 02-May-12

15-May-12

D102

Plot Plan : Client Review

10

0% 16-May-12

29-May-12

D103

Plot Plan : Issue for Design Review

0% 30-May-12

06-Jun-12

D109

PDMS Modelling

170

0% 19-May-12

08-Jan-13

D110

Preliminary MTO

10

0% 14-Jul-12

25-Jul-12

D111

Stress Analysis of Critical Lines

115

0% 27-Jun-12

04-Dec-12

Primary Baseline

Summary

Project Start Date :27-Mar-12

4 of 12

Actual Work
Remaining Work
Critical Remaining Work
Milestone

Project End Date :15-Jan-14


Data Date:27-Mar-12

2012

2013

M A M J Jul A S O N D

Primavera Systems, Inc.

Date
02-Apr-12

2014

F M A M J Jul A S O N D J

Revision
Checked
PROJECT ... ARD

Approved
KGB

AL HASSAN ENGINEERING CO S.A.O.G. OMAN

AMAL HEAT RECOVERY STEAM GENERATOR (HRSG) - 1

B- 200

(C311333)
Activity ID

Activity Name

Original Duration % Start


Duration Complete

D120

PDMS Model Review 60% meeting with Client

D123
D124

Finish

0% 12-Nov-12

13-Nov-12

Tie-in Schedule

10

0% 26-Nov-12

09-Dec-12

Extraction of Isometric drgs

50

0% 26-Nov-12

03-Feb-13

D155

Extraction of Piping GA drgs

35

0% 13-Feb-13

02-Apr-13

D160

Final MTO-Piping

10

0% 04-Feb-13

17-Feb-13

282

0% 17-Jun-12

26-Mar-13

Instrumentation Engineering
F100

MR : Control Valves

10

0% 30-Jun-12

11-Jul-12

F105

MR : Field instruments

10

0% 22-Jul-12

04-Aug-12

F108

TQ / TAQ

20

0% 26-Aug-12

22-Sep-12

F109

Vendor Document Review

40

0% 28-Oct-12

22-Dec-12

F110

I/O list

0% 07-Jul-12

11-Jul-12

F142

Control & Auxiliary Room Layout

11

0% 17-Jun-12

01-Jul-12

F160

Cable Block Diagrams

15

0% 14-Jul-12

01-Aug-12

F161

Control & Safegaurding narrative for BOP

20

0% 04-Aug-12

29-Aug-12

F170

Instrument Layout drwgs

35

0% 04-Dec-12

21-Jan-13

F180

ICTD

10

0% 18-Dec-12

31-Dec-12

F190

Instrument Name Plates

10

0% 29-Dec-12

09-Jan-13

F200

Instr Impulse Lines

10

0% 07-Jan-13

20-Jan-13

F210

Electr/Pneumatic Hook-ups

10

0% 16-Jan-13

29-Jan-13

F230

Summary of Instrument Cables

10

0% 27-Jan-13

09-Feb-13

F235

Bulk MTO Ins trumentation

10

0% 05-Feb-13

18-Feb-13

F250

Plant Instrument Layout

15

0% 20-Feb-13

12-Mar-13

F252

AFC Drawings

35

0% 06-Feb-13

26-Mar-13

293

0% 19-May-12

08-Mar-13

128

0% 19-May-12

24-Sep-12

Procurement (From issue spec to Order Placement)


Procurement - Mechanical
PRMECH010

Piping Bulk MTO( CS, SS & G I)

16

0% 10-Jun-12

25-Jun-12

PRMECH020

Instrument Air package

38

0% 19-May-12

26-Jun-12

PRMECH030

service water Pumps with bladder tank

45

0% 01-Jul-12

15-Aug-12

PRMECH040

Service water tank

45

0% 21-Jun-12

05-Aug-12

PRMECH050

HVAC system HRSG Control building

45

0% 08-Jul-12

22-Aug-12

PRMECH060

Structural Materials ( Civil and pipe Racks)

20

0% 05-Sep-12

24-Sep-12

292

0% 20-May-12

08-Mar-13

Procurement - Electrical
Primary Baseline

Summary

Project Start Date :27-Mar-12

5 of 12

Actual Work
Remaining Work
Critical Remaining Work
Milestone

Project End Date :15-Jan-14


Data Date:27-Mar-12

2012

2013

M A M J Jul A S O N D

Primavera Systems, Inc.

Date
02-Apr-12

2014

F M A M J Jul A S O N D J

Revision
Checked
PROJECT ... ARD

Approved
KGB

AL HASSAN ENGINEERING CO S.A.O.G. OMAN

AMAL HEAT RECOVERY STEAM GENERATOR (HRSG) - 1

B- 200

(C311333)
Activity ID

Activity Name

Original Duration % Start


Duration Complete

Finish

PRELEC010

6.6 / 0.433 kv Unit Auxiliary Xmer( 2 NO)

36

0% 21-May-12

26-Jun-12

PRELEC020

6.6 KV MV Auxiliary Switchboard( 1 no)

30

0% 26-May-12

25-Jun-12

PRELEC030

415 V AC Unit Auxiliary Switc hboard( 1 no)

30

0% 26-May-12

25-Jun-12

PRELEC040

125 V DC UPS System with batteries/DCDB (1 no)

36

0% 20-May-12

25-Jun-12

PRELEC050

240 V AC UPS System with batteries/ACDB (1 no)

36

0% 21-May-12

26-Jun-12

PRELEC060

LV DB's for indoor and outdoor Lighting, HVAC DB

35

0% 29-Oct-12

03-Dec-12

PRELEC080

LV & MV Cables

25

0% 30-Dec-12

24-Jan-13

PRELEC090

Earthing materials

25

0% 03-Feb-13

28-Feb-13

PRELEC100

Lighting Indoor & outdoor

25

0% 11-Feb-13

08-Mar-13

PRELEC110

Bulk electrical Materials ( Cable Trays ,Cathodic protection, Supports )

25

0% 25-Nov-12

20-Dec-12

189

0% 11-Jul-12

16-Jan-13

45

0% 11-Jul-12

25-Aug-12

Procurement - Instrumentation, Control


PRIC010

F & G ,smoke detection equipments/Detectors

PRIC020

Field instrument ( Pressure & Level Transmitters, Level and pressure Guages)
30

0% 04-Aug-12

03-Sep-12

PRIC030

Instrument cable (signal and control)

25

0% 13-Nov-12

07-Dec-12

PRIC040

Bulk Instrumentation Materials( cable trays, supports ,etc)

30

0% 18-Dec-12

16-Jan-13

PRIC050

Telecommunication system ( Patch panel, CCTV, ACS,incl 48 V DC UPS) 45

0% 16-Jul-12

30-Aug-12

336

0% 05-Jul-12

06-Jun-13

Manufacturing
Manufacturing - Mechanical

221

0% 11-Jul-12

16-Feb-13

MDMECH010

Piping Bulk Materials

145

0% 11-Jul-12

02-Dec-12

MDMECH020

Instrument air Package

210

0% 16-Jul-12

11-Feb-13

MDMECH030

Service water pumps with bladder tank

140

0% 29-Sep-12

16-Feb-13

MDMECH040

Service water tank

135

0% 19-Sep-12

01-Feb-13

MDMECH050

HVAC System

130

0% 22-Aug-12

30-Dec-12

MDMECH060

Structural Materials ( Civil and pipe racks)

55

0% 25-Sep-12

18-Nov-12

336

0% 05-Jul-12

06-Jun-13

Manufacturing - Electrical
MDELEC010

6.6 / 0.433 kv Unit Auxiliary Xmer( 2NO)

230

0% 21-Jul-12

08-Mar-13

MDELEC020

6.6 KV Unit Auxiliary Switchboard

195

0% 30-Jul-12

10-Feb-13

MDELEC030

415 V AC Unit Auxiliary Switc hboard

220

0% 25-Jul-12

02-Mar-13

MDELEC040

125 V DC UPS System with batteries/DCDB

200

0% 05-Jul-12

21-Jan-13

MDELEC050

240 V AC UPS System with batteries/ACDB

210

0% 06-Jul-12

01-Feb-13

MDELEC060

LV DB's for indoor and outdoor Lighting, HVAC DB

150

0% 03-Dec-12

02-May-13

MDELEC070

LV and MV Cables

90

0% 24-Jan-13

24-Apr-13

Primary Baseline

Summary

Project Start Date :27-Mar-12

6 of 12

Actual Work
Remaining Work
Critical Remaining Work
Milestone

Project End Date :15-Jan-14


Data Date:27-Mar-12

2012

2013

M A M J Jul A S O N D

Primavera Systems, Inc.

Date
02-Apr-12

2014

F M A M J Jul A S O N D J

Revision
Checked
PROJECT ... ARD

Approved
KGB

AL HASSAN ENGINEERING CO S.A.O.G. OMAN

AMAL HEAT RECOVERY STEAM GENERATOR (HRSG) - 1

B- 200

(C311333)
Activity ID

Activity Name

Original Duration % Start


Duration Complete

Finish

MDELEC080

Earthing materials

75

0% 28-Feb-13

14-May-13

MDELEC090

Lighting Indoor & outdoor

90

0% 08-Mar-13

06-Jun-13

MDELEC100

Bulk electrical Materials ( Cable Trays ,Supports, cathodic protection )

90

0% 20-Dec-12

20-Mar-13

219

0% 25-Aug-12

01-Apr-13

140

0% 25-Aug-12

12-Jan-13

Manufacturing - Instrument & Control


MDIC010

F & G ,smoke detection equipments/Detectors

MDIC020

Field instrument ( Pressure & Level Transmitters, Level and pressure Guages)
165

0% 18-Sep-12

02-Mar-13

MDIC030

Instrument cable (signal and control)

95

0% 08-Dec-12

12-Mar-13

MDIC050

Bulk Instrumentation Materials( cable trays, supports ,etc)

75

0% 17-Jan-13

01-Apr-13

MDIC060

Telecommunication system ( Patch panel, CCTV, ACS,incl 48 V DC UPS) 160

0% 30-Aug-12

06-Feb-13

230

0% 19-Nov-12

06-Jul-13

145

0% 19-Nov-12

12-Apr-13

Delivery of Material Ex works To site


Material Delivery - Mechanical & Piping
MDMECH070

Piping bulk Materials

45

0% 03-Dec-12

16-Jan-13

MDMECH080

Instrument air Package

60

0% 11-Feb-13

12-Apr-13

MDMECH090

Service water pumps with bladder tank

40

0% 16-Feb-13

28-Mar-13

MDMECH100

Service water tank

45

0% 01-Feb-13

18-Mar-13

MDMECH110

HVAC System

45

0% 30-Dec-12

13-Feb-13

MDMECH120

Structural Materials (CIVIL and Pi pe racks)

20

0% 19-Nov-12

08-Dec-12

166

0% 21-Jan-13

06-Jul-13

Material Delivery - Electrical


MDELEC130

6.6 / 0.433 kv Unit Auxiliary Xmer

45

0% 08-Mar-13

22-Apr-13

MDELEC140

6.6 KV Unit Auxiliary Switchboard

50

0% 10-Feb-13

01-Apr-13

MDELEC150

415 V AC Unit Auxiliary Switc hboard

45

0% 02-Mar-13

16-Apr-13

MDELEC160

125 V DC UPS System with batteries/DCDB

45

0% 21-Jan-13

07-Mar-13

MDELEC170

240 V AC UPS System with batteries/ACDB

40

0% 01-Feb-13

13-Mar-13

MDELEC300

LV DB's for indoor and outdoor Lighting, HVAC DB

30

0% 02-May-13

01-Jun-13

MDELEC360

LV and MV Cables

30

0% 24-Apr-13

24-May-13

MDELEC370

Earthing materials

30

0% 14-May-13

13-Jun-13

MDELEC380

Lighting Indoor & outdoor

30

0% 06-Jun-13

06-Jul-13

MDELEC390

Bulk electrical Materials ( Cable Trays ,Cathodic protection, Supports )

30

0% 20-Mar-13

19-Apr-13

104

0% 12-Jan-13

26-Apr-13

45

0% 12-Jan-13

26-Feb-13

Material Delivery - Instrumentation


MDIC120

F & G ,smoke detection equipments/Detectors

MDIC150

Field instrument ( Pressure & Level Transmitters, Level and pressure Guages)
45

0% 02-Mar-13

16-Apr-13

MDIC160

Instrument cable

0% 13-Mar-13

06-Apr-13

Primary Baseline

25
Summary

Project Start Date :27-Mar-12

7 of 12

Actual Work
Remaining Work
Critical Remaining Work
Milestone

Project End Date :15-Jan-14


Data Date:27-Mar-12

2012

2013

M A M J Jul A S O N D

Primavera Systems, Inc.

Date
02-Apr-12

2014

F M A M J Jul A S O N D J

Revision
Checked
PROJECT ... ARD

Approved
KGB

AL HASSAN ENGINEERING CO S.A.O.G. OMAN

AMAL HEAT RECOVERY STEAM GENERATOR (HRSG) - 1

B- 200

(C311333)
Activity ID

Activity Name

Original Duration % Start


Duration Complete

Finish

MDIC180

Bulk Instrumentation materials ( Cable trays, tubing, and conduits)

25

0% 02-Apr-13

26-Apr-13

MDIC190

Telecommunication system ( Patch panel, CCTV, ACS,incl 48 V DC UPS) 39

0% 06-Feb-13

17-Mar-13

32

0% 06-Apr-12

07-May-12

Mobilization
MOB010

Set-up of offi ces in Oman

10

0% 06-Apr-12

15-Apr-12

MOB020

Contract Execution Plan with a prelim Const Plan

28

0% 08-Apr-12

05-May-12

MOB030

The Contract Specific Quality Plan

30

0% 08-Apr-12

07-May-12

MOB040

Contract Specific HSE Programme & detailed plan

25

0% 10-Apr-12

04-May-12

MOB050

Start of detailed design

30

0% 06-Apr-12

05-May-12

MOB060

Approval of Key Personnel

20

0% 13-Apr-12

02-May-12

MOB070

Mobilization of identified key personnel

18

0% 19-Apr-12

06-May-12

MOB080

Finalized detailed Contract Work Plan& programme

30

0% 06-Apr-12

05-May-12

MOB090

Completed HSE kick off meeting

0% 03-May-12

03-May-12

MOB100

Final subcontracts list & mobilizekey personnel

32

0% 06-Apr-12

07-May-12

MOB110

Submission of documents as per C4 General

32

0% 06-Apr-12

07-May-12

562

0% 06-Apr-12

19-Oct-13

81

0% 06-Apr-12

25-Jun-12

0% 06-Apr-12

12-Apr-12

15

0% 08-Jun-12

22-Jun-12

Construction
Site Establishment
CNSITE010

Handing over of Plot ( Customer Responsibility)

CNSITE020

Completed & signed off HSE KO M,HSE Workshop@site

CNSITE030

Complet'n,Approval all activities on HSE certifi

0% 21-Jun-12

25-Jun-12

CNSITE040

Comple'n all safety trainning & equipment certif

45

0% 06-May-12

19-Jun-12

CNSITE050

Compl'n mobiliz'n, estb of sitecamp/shop/offic e faci lities

65

0% 17-Apr-12

20-Jun-12

480

0% 26-Jun-12

19-Oct-13

350
35

0% 26-Jun-12
0% 26-Jun-12

11-Jun-13
31-Jul-12

Plant Fencing

120

0% 11-Feb-13

11-Jun-13

Civil Work- Control Building


CCVMCC2010
Sub-Structure

280
63

0% 17-Jul-12
0% 17-Jul-12

23-Apr-13
18-Sep-12

100

0% 25-Sep-12

03-Jan-13

75

0% 04-Dec-12

17-Feb-13

120

0% 24-Dec-12

23-Apr-13

35

0% 10-Mar-13

14-Apr-13

187

0% 11-Sep-12

17-Mar-13

Civil Work
Civil Work- Site Preparation
CNSITE130
Initial Site levelling & Grading
CNSITE140

CCVMCC2020

Super structure

CCVMCC2030

Building Block work/Ironmongery

CCVMCC2040

Building Finishing

CCVMCC2050

Building Services/HVAC

Civil work HRSG


Primary Baseline

Summary

Project Start Date :27-Mar-12

8 of 12

Actual Work
Remaining Work
Critical Remaining Work
Milestone

Project End Date :15-Jan-14


Data Date:27-Mar-12

2012

2013

M A M J Jul A S O N D

Primavera Systems, Inc.

Date
02-Apr-12

2014

F M A M J Jul A S O N D J

Revision
Checked
PROJECT ... ARD

Approved
KGB

AL HASSAN ENGINEERING CO S.A.O.G. OMAN

AMAL HEAT RECOVERY STEAM GENERATOR (HRSG) - 1

B- 200

(C311333)
Activity ID

Activity Name

Original Duration % Start


Duration Complete

Finish

CCVHRSG1010

Stack Foundation

90

0% 11-Sep-12

10-Dec-12

CCVHRSG1020

Foundation for Main steel structure

75

0% 26-Sep-12

10-Dec-12

CCVHRSG1030

Foundation for other Auxillary equipment

75

0% 26-Oct-12

09-Jan-13

CCVHRSG1050

Cable trenches

90

0% 17-Dec-12

17-Mar-13

CCVHRSG1060

Pipe trenches ( burried and concrete)

90

0% 16-Dec-12

16-Mar-13

220
60

0% 09-Oct-12
0% 25-Dec-12

17-May-13
23-Feb-13

Civil Work- Plant Auxiliaries


CCVPLAX010
Pipe rack foundation
CCVPLAX015

Precast of pipe sleeper and Installation

75

0% 03-Mar-13

17-May-13

CCVPLAX020

IA Compressor foundation including shed foundation

45

0% 03-Feb-13

20-Mar-13

CCVPLAX030

Feed water pumps foundation with shed foundation

30

0% 13-Jan-13

12-Feb-13

CCVPLAX040

Service Water Tank foundation

30

0% 28-Jan-13

27-Feb-13

CCVPLAX050

Unit aux 6.6/0.433 kv Tx for MCC buildi ng

60

0% 03-Jan-13

04-Mar-13

CCVPLAX060

Construction of Blow down pit

90

0% 09-Oct-12

07-Jan-13

CCVPLAX070

Foundation for Heat exchanger, Expansion tank, recirulation pumps with Shed
55 foundation
0% 14-Jan-13

29-Mar-13

Civil Work- Finishing Work


CCVFINL010
Final levelling & grading

298
90

0% 25-Dec-12
0% 11-Jun-13

19-Oct-13
09-Sep-13

CCVFINL020

Drainage

120

0% 12-May-13

09-Sep-13

CCVFINL030

Plant Roads

100

0% 11-Jul-13

19-Oct-13

CCVFINL035

Plant pavement

120

0% 27-May-13

24-Sep-13

CCVFINL040

Precasting of sleeper & Trench cover

130

0% 25-Dec-12

04-May-13

CCVFINL050

Precast cover fixing for trenches

120

0% 20-Mar-13

18-Jul-13

CCVFINL060

Backfilling works

150

0% 30-Mar-13

26-Aug-13

187
167
65

0% 09-Dec-12
0% 09-Dec-12
0% 23-Feb-13

13-Jun-13
24-May-13
29-Apr-13

Structural Works
Fabrication Works
CCVSTRF010
Fabrication of Pipe rack structure
CCVSTRF020

Fabrication of Pipe supports

60

0% 05-Mar-13

04-May-13

CCVSTRF040

Fabrication of Shed Materials

75

0% 09-Dec-12

21-Feb-13

CCVSTRF050

Hot dip Galvanisation

75

0% 10-Mar-13

24-May-13

76
60

0% 30-Mar-13
0% 14-Apr-13

13-Jun-13
13-Jun-13

Erection & Installation


CCVSTRE010
Erection & Installation of Pipe rack
CCVSTRE020

Installation of Pipe supports

45

0% 04-Apr-13

19-May-13

CCVSTRE040

Erection & Installation of Shed

60

0% 30-Mar-13

28-May-13

189

0% 28-Mar-13

03-Oct-13

Installation
Primary Baseline

Summary

Project Start Date :27-Mar-12

9 of 12

Actual Work
Remaining Work
Critical Remaining Work
Milestone

Project End Date :15-Jan-14


Data Date:27-Mar-12

2012

2013

M A M J Jul A S O N D

Primavera Systems, Inc.

Date
02-Apr-12

2014

F M A M J Jul A S O N D J

Revision
Checked
PROJECT ... ARD

Approved
KGB

AL HASSAN ENGINEERING CO S.A.O.G. OMAN

AMAL HEAT RECOVERY STEAM GENERATOR (HRSG) - 1

B- 200

(C311333)
Activity ID

Activity Name

Original Duration % Start


Duration Complete

Mechanical Installation HRSG

Finish

109

0% 01-Jun-13

17-Sep-13

CHRSGME010

Installation of Main steel structure erection

45

0% 01-Jun-13

15-Jul-13

CHRSGME020

Modules erection

45

0% 21-Jun-13

04-Aug-13

CHRSGME030

Casing Erection and welding

45

0% 06-Jul-13

19-Aug-13

CHRSGME040

Inlet duct erection

35

0% 31-Jul-13

03-Sep-13

CHRSGME050

Out let duct Erection

35

0% 05-Aug-13

08-Sep-13

CHRSGME060

Stack Erection

60

0% 19-Jun-13

17-Aug-13

CHRSGME080

Diverter Damper / Gilotine valve erection

60

0% 01-Jun-13

30-Jul-13

CHRSGME140

Final painting works

75

0% 05-Jul-13

17-Sep-13

129

0% 28-Mar-13

04-Aug-13

Mechanical Installation BOP


CHRSGME090

Instrument air compressor and Air Receiver

65

0% 07-May-13

11-Jul-13

CHRSGME100

Heat Exchanger , Expansion tank installation

45

0% 21-Jun-13

04-Aug-13

CHRSGME110

Feed water pumps, Recirculation pumps, purge air blower system

35

0% 21-Jun-13

25-Jul-13

CHRSGME120

GRP tank s and SW Tanks

20

0% 12-Apr-13

02-May-13

CHRSGME130

SW pumps with bladder tank

15

0% 28-Mar-13

12-Apr-13

94

0% 21-Jun-13

23-Sep-13

Piping Installation HRSG and BOP


CHRSGPI010

Boiler piping

70

0% 27-Jun-13

04-Sep-13

CHRSGPI030

Feed Water Piping

60

0% 01-Jul-13

29-Aug-13

CHRSGPI040

Blow down piping

50

0% 07-Jul-13

25-Aug-13

CHRSGPI050

Steam piping

60

0% 12-Jul-13

09-Sep-13

CHRSGPI060

SW line and purge air line , instrument air line

75

0% 21-Jun-13

04-Sep-13

CHRSGPI070

Hydrotest

60

0% 26-Jul-13

23-Sep-13

164

0% 22-Apr-13

03-Oct-13

156
75

0% 22-Apr-13
0% 23-Apr-13

25-Sep-13
07-Jul-13

Electrical Installation
Electrical Control building
CHRSGEL005
Cable tray support and cable tray installation
CHRSGEL010

6.6 KV MV Panel

45

0% 08-May-13

22-Jun-13

CHRSGEL020

415 V LV panel

45

0% 23-May-13

07-Jul-13

CHRSGEL030

110 V DC UPS system

35

0% 02-Jun-13

07-Jul-13

CHRSGEL040

240 V AC UPS system

35

0% 07-Jun-13

12-Jul-13

CHRSGEL050

Unit Auxiliary transformer (2 No's)

30

0% 22-Apr-13

22-May-13

CHRSGEL060

MV cable laying, glanding and Termination

65

0% 06-Jul-13

09-Sep-13

CHRSGEL070

LV and control cable laying, glanding and Termination

110

0% 28-May-13

15-Sep-13

Primary Baseline

Summary

Project Start Date :27-Mar-12

10 of 12

Actual Work
Remaining Work
Critical Remaining Work
Milestone

Project End Date :15-Jan-14


Data Date:27-Mar-12

2012

2013

M A M J Jul A S O N D

Primavera Systems, Inc.

Date
02-Apr-12

2014

F M A M J Jul A S O N D J

Revision
Checked
PROJECT ... ARD

Approved
KGB

AL HASSAN ENGINEERING CO S.A.O.G. OMAN

AMAL HEAT RECOVERY STEAM GENERATOR (HRSG) - 1

B- 200

(C311333)
Activity ID

Activity Name

Original Duration % Start


Duration Complete

Finish

CHRSGEL080

Indoor lighting and area lighting

60

0% 06-Jul-13

04-Sep-13

CHRSGEL140

Earthing works

75

0% 14-May-13

28-Jul-13

CHRSGEL170

Panel testing and charging

75

0% 12-Jul-13

25-Sep-13

Cable tray support and cable tray installation

90
90

0% 06-Jul-13
0% 06-Jul-13

03-Oct-13
03-Oct-13

CHRSGEL090

Aviation light Panel instal lation and Electrical system JB installation

45

0% 03-Aug-13

16-Sep-13

CHRSGEL100

HRSG Lighting works

35

0% 20-Aug-13

23-Sep-13

CHRSGEL110

Earthing works

75

0% 06-Jul-13

18-Sep-13

CHRSGEL120

Cable laying, glanding and Termination

54

0% 31-Jul-13

22-Sep-13

CHRSGEL150

Electrical works for feed water, SW, R ecir cul ation pumps

45

0% 11-Jul-13

24-Aug-13

CHRSGEL160

Electrical works for Instrument air compressor and other BOP equipments 50

0% 11-Jul-13

30-Aug-13

CHRSGEL180

Cathodic Protection

25

0% 26-Aug-13

19-Sep-13

CHRSGEL190

Completion of Electrical activities for Control building

0% 25-Sep-13

26-Sep-13

157

0% 23-Apr-13

27-Sep-13

145
72

0% 23-Apr-13
0% 20-Jun-13

15-Sep-13
30-Aug-13

HRSG and BOP


CHRSGEL085

Instrumentation Installation
Control Building
CHRSGIN010
MAC system ( IPS/ FGS /FCS)
CHRSGIN020

Fire and Gas system

60

0% 23-Apr-13

22-Jun-13

CHRSGIN030

Telecommunication system

90

0% 23-Apr-13

22-Jul-13

CHRSGIN050

Cable tray support and tray installation

75

0% 23-Apr-13

07-Jul-13

CHRSGIN060

Cable laying , glanding and termination

90

0% 17-Jun-13

15-Sep-13

105
45

0% 15-Jun-13
0% 18-Jul-13

27-Sep-13
31-Aug-13

HRSG and BOP


CHRSGIN040

Cable tray support and cable tray installation

CHRSGIN055

JB support and JB installation

40

0% 18-Jul-13

26-Aug-13

CHRSGIN080

Instrument calibration

60

0% 15-Jun-13

13-Aug-13

CHRSGIN090

Field instrument installation

60

0% 15-Jul-13

12-Sep-13

CHRSGIN095

Tubing works

60

0% 25-Jul-13

22-Sep-13

CHRSGIN100

Cable laying, glanding and termination

60

0% 28-Jul-13

25-Sep-13

CHRSGIN110

Instrumentation works completion

12

0% 16-Sep-13

27-Sep-13

64

0% 25-Aug-13

27-Oct-13

Pre-commissioning
Pre-commissioning HRSG

64

0% 25-Aug-13

27-Oct-13

CHRSGPI080

Insulation works for piping and equipment

60

0% 25-Aug-13

23-Oct-13

PREHRSG1010

Hot and Cold Loops & Functional checks

58

0% 31-Aug-13

27-Oct-13

Primary Baseline

Summary

Project Start Date :27-Mar-12

11 of 12

Actual Work
Remaining Work
Critical Remaining Work
Milestone

Project End Date :15-Jan-14


Data Date:27-Mar-12

2012

2013

M A M J Jul A S O N D

Primavera Systems, Inc.

Date
02-Apr-12

2014

F M A M J Jul A S O N D J

Revision
Checked
PROJECT ... ARD

Approved
KGB

AL HASSAN ENGINEERING CO S.A.O.G. OMAN

AMAL HEAT RECOVERY STEAM GENERATOR (HRSG) - 1

B- 200

(C311333)
Activity ID

Activity Name

PREHRSG1020

Original Duration % Start


Duration Complete

Hydrotesting & Flushing

Commissioning
Commissioning - HRSG
COMHRSG1010

Commissioning Assistant

Completion & Demobilization

Finish

15

0% 24-Sep-13

08-Oct-13

75

0% 23-Oct-13

05-Jan-14

75

0% 23-Oct-13

05-Jan-14

75

0% 23-Oct-13

05-Jan-14

77

0% 31-Oct-13

15-Jan-14

DEMOV010

Closeout All Punch list Items

45

0% 31-Oct-13

14-Dec-13

DEMOV020

As builds/Manuals

40

0% 22-Nov-13

31-Dec-13

DEMOV030

Site demobilization

30

0% 14-Dec-13

12-Jan-14

DEMOV040

HSE Site Restoration Certificate

10

0% 06-Jan-14

15-Jan-14

Primary Baseline

Summary

Project Start Date :27-Mar-12

12 of 12

Actual Work
Remaining Work
Critical Remaining Work
Milestone

Project End Date :15-Jan-14


Data Date:27-Mar-12

2012

2013

M A M J Jul A S O N D

Primavera Systems, Inc.

Date
02-Apr-12

2014

F M A M J Jul A S O N D J

Revision
Checked
PROJECT ... ARD

Approved
KGB