Professional Documents
Culture Documents
Petroleum Development Oman L.L.C. Schedule D' - Unit Rates For Alterations & Day Works C-5
Petroleum Development Oman L.L.C. Schedule D' - Unit Rates For Alterations & Day Works C-5
C311333
Amal HRSG -1 Project
Section C5 Schedule D - Page 2 of 10
1.
DESCRIPTION
UNIT
Excavation
a)
b)
c)
d)
1.
Filling
a)
a)
b)
c)
d)
e)
f)
Cable tile
No
2.
a)
b)
c)
d)
15 N/mm
25 N/mm
35 N/mm
2
2
2-
3.
a)
a)
b)
c)
25 N/nm
35 N/nm
2
2
m
m
m
m
m
m
m
m
m
m
m
m
m
3
3
3
3
3
3
3
3
3
3
3
3
3
UNIT RATE
RO
C311333
Amal HRSG -1 Project
Section C5 Schedule D - Page 3 of 10
CIVIL WORKS
Ref.
No.
DESCRIPTION
UNIT
4.
Reinforcement
a)
kg.
b)
c)
d)
5.
Foundation protection
a)
b)
c)
6.
Grouting
a)
7.
Anchor Bolts
a)
8.
Block work
a)
b)
c)
9.
Plastering
a)
b)
c)
gauge
polythene
sheet below
m
m
m
m
m
2
2
2
2
2
item
m
m
3
3
3
2
2
UNIT RATE
RO
C311333
Amal HRSG -1 Project
Section C5 Schedule D - Page 4 of 10
CIVIL WORKS
Ref.
No.
DESCRIPTION
UNIT
d)
10.
Painting
a)
Prepare and apply one coat of primer and two coats of paint
of approved shade on concrete and plastered surfaces
b)
c)
11.
Fencing
a)
b)
No.
c)
No.
12.
Roads
a)
b)
c)
d)
e)
13.
Steelworks
m
m
m
m
m
m
2
2
2
3
2
2
kg
b)
kg
c)
kg
d)
kg.
14.
UNIT RATE
RO
C311333
Amal HRSG -1 Project
Section C5 Schedule D - Page 5 of 10
CIVIL WORKS
Ref.
No.
a)
DESCRIPTION
UNIT
UNIT RATE
RO
C311333
Amal HRSG -1 Project
Section C5 Schedule D - Page 6 of 10
PLANT
Ref.
No.
1.
DESCRIPTION
Unit
6.6kV Cabling
a)
6.6kV 400 Amps three phase cable, supply, direct buried, test
and commission.
b)
c)
each
d)
each
2.
33kV Cabling
a)
33kV 400 Amp three phase cable, supply, install direct buried,
test and commission.
b)
each
c)
each
d)
each
3.
a)
b)
UNIT RATE
RO
C311333
Amal HRSG -1 Project
Section C5 Schedule D - Page 7 of 10
DESCRIPTION
Unit
Design Engineer
Hr.
Hr.
Protection Engineer
Hr.
Hr.
Hr.
Hr.
Hr.
Commissioning Engineer
Hr.
QA/QC Engineer
Hr.
10
Designer
Hr.
11
Draughtsman
Hr.
12
Technical Assistant
Hr.
14
Hr
UNIT
RATE RO
OVERTIME
UNIT
RATE RO
UNIT
RATE RO
OVERTIME
UNIT
RATE RO
23
SITE LABOUR
Ref.
No.
DESCRIPTION
Unit
Mechanical
1
Foreman
Hr.
Welder
Hr.
Hr.
Millwright
Hr.
Rigger
Hr.
Plant Fitter
Hr.
A/C Mechanic
Hr.
Hr.
Foreman
Hr.
10
Electrician
Hr.
11
Cable Jointer
Hr.
12
Telecom Technician
Hr.
C311333
Amal HRSG -1 Project
Section C5 Schedule D - Page 8 of 10
SITE LABOUR
Ref.
No.
DESCRIPTION
Unit
UNIT
RATE RO
OVERTIME
UNIT
RATE RO
Foreman
Hr.
14
Mason
Hr.
15
Concrete Labourer
Hr.
16
Unskilled
Hr.
17
Painter
Hr.
18
Steel Fixers
Hr.
19
Steel Erectors
Hr.
20
Plasterers
Hr.
21
Plant Operator
Hr.
22
Hr.
Plant
Ref.
No.
DESCRIPTION
Unit
Hr.
Hr.
Hr.
Hr.
Hr.
Hr.
Hr.
Hr.
Hr.
10
Hr.
11
Hr.
12
Hr.
13
Hr.
14
Hr.
UNIT
RATE RO
OVERTIME
UNIT
RATE RO
C311333
Amal HRSG -1 Project
Section C5 Schedule D - Page 9 of 10
15
Hr.
16
JCB 3c or equivalent
Hr.
17
Pick-up truck
Hr.
18
Truck 5T
Hr.
19
50T Crane
Hr.
20
15T Crane
Hr.
21
5T Crane
Hr.
22
Hr.
23
Generator 10 - 25 KW
Hr.
24
Generator 100 - 15 KW
Hr.
25
Hr.
26
26
Hr.
27
Hr.
28
Hr.
29
Hr.
30
Hr.
31
Hr.
32
Blast unit,
personnel
Hr.
33
Bucket Truck
fully
operational
Per Day
with
operating
Hr
FOR
ADDITIONAL SERVICES
AND
Applicable Schedule
% Adjustment
+/- 3%
+/- 3%
C311333
Amal HRSG -1 Project
Section C5 Schedule D - Page 10 of 10
IMPORTED MATERIALS
Adjustment to the net cost of Materials procured from
outside of the GCC countries for costs of handling,
administration, financing, overheads, profit, all other
costs related to such procurement.
+/- 3%