Professional Documents
Culture Documents
BAM Clough Woodside LNG Jetty
BAM Clough Woodside LNG Jetty
Expansion
Key Aspects
99 Self Performed
99 Construction at in an operational
LNG export facility requiring
unobstructed access.
99 Project site in cyclone area
Project Highlights
99 Excellent Safety Performance
- Zero Lost Time Incidents
99 Project completed on schedule
99 Added scope to reinforce
existing material offloading
facility.
99 Existing facilities fully operational
during construction.
99 Crane installed on breasting
dolphin for sea condition
independent craneage.
BC010c
Page 1 of 2
99 Prefabricated concrete
structures reduced labour
installation requirements.
www.bamclough.com
PROJECT DETAILS:
Location:
NorthWest Shelf,
Western Australia
Contract Value:
Contract Period:
Safety Statistics:
Manhours: 344,440
LTIFR: 0
Tie-in works at the existing trestle were executed in a planned three-day shutdown of the existing LNG berth
and involved installation of a pre-assembled steel unit for the piping tie-ins.
BC010c
Page 2 of 2
To reduce labour installation requirements and meet the schedule, the 30 metre long access trestle units were
fabricated off site in Perth and transported 1,800 kilometres over land to the site. The 120 tonne modules were
then shipped via the Material Offloading Facility to the jetty for installation by the crane barge.