Professional Documents
Culture Documents
TNB Tariff Book
TNB Tariff Book
CONTENTS
Page no.
1. Definitions
2-3
2. General Information
4-6
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
2.11
4
4
4
4
5
5
5
5
6
6
6
5. Schedules
5.1 Schedule 1
TNB Tariff Rates
8 - 11
5.2 Schedule 2
Rates for Top-up and Standby Services
12
1.
DEFINITIONS
Unless the context otherwise states the following definitions shall apply:
(a)
CUSTOMER means any person taking a supply of energy from Tenaga Nasionals
supply lines at any one point of supply, provided that if a person takes a supply at more
than one point of supply such person shall be deemed to be a separate customer for each
such point of supply.
(b)
(c)
(d)
(e)
MINING CUSTOMER means a customer using electrical energy for the most part for
extracting mineral and includes dredging.
(f)
(g)
(h)
LOW VOLTAGE in the context of tariff classification means a supply voltage not
exceeding 1,000 volts.
(i)
(j)
(k)
(l)
(m)
AVERAGE POWER FACTOR means the cosine of the angle of which the tangent is
obtained by dividing the total of the reactive kilovolt-ampere hours by the total of the
kilowatt-hours recorded in any month by Tenaga Nasionals meters.
(n)
(o)
(p)
PEAK period means the period between 0800 hours and 2200 hours.
(q)
OFF-PEAK period means the period between 2200 hours and 0800 hours.
(r)
(s)
(t)
(u)
MALAYSIAN GRID CODE means any national grid code or similar Regulations
made under the Electricity Supply Act 1990 relating to the planning, scheduling or
despatch of electricity in Peninsular Malaysia, as the same may be amended from time to
time.
(v)
(w)
(x)
Meters are
2.
GENERAL INFORMATION
2.1
Electricity shall be supplied in accordance with the provisions of the Electricity Supply Act 1990,
the Licensee Supply Regulations 1990 and the Electricity Regulations 1994 and all amendments
thereto.
2.2
VOLTAGES
Tenaga Nasional Berhad(TNB)s declared supply voltages are as per table below:
Voltage Level
Low Voltage
Single Phase
Three Phase
Medium Voltage
High Voltage
2.3
Supply Voltages
240V
415V
6,600V
11,000V
22,000V
33,000V
66,000V
132,000V
275,000V
+5% to 10%
+5% to 10%
To be defined in the future
Malaysian Electricity Distribution
Code
+10% to 5%
+10% to 5%
FREQUENCY
METERS
(a)
All necessary meters shall be provided by TNB for measuring the consumption of
electricity. Customers shall be required to pay a charge for additional meter installed at
their request and may also be required to pay a portion of the cost of any special metering
facilities installed by TNB.
(b)
The customer shall not interfere, nor permit any person other than an authorized
employee of TNB to interfere with TNB s service equipment and meters.
(c)
If a meter is lost, destroyed or damaged, the customer shall pay to TNB the full cost of
repair or replacement.
(d)
Deliberate interference with any aspect of TNB s metering system is an offence under
the Electricity Supply Act 1990.
(e)
If a customer thinks his meter is not registering accurately he can ask for the meter to be
tested. A test fee shall be chargeable and it will be refundable only if the meter is found
to be inaccurate by more than 3%.
2.5
Authorized employees of TNB are permitted under the Licensee Supply Regulations 1990 to have
access to a customers premises at all reasonable times, for purposes connected with the supply of
electricity. All such persons carry a special authorization card.
2.6
ACCOUNTS
(a)
A customer shall be required to pay a Minimum Monthly Charge (MMC) for each supply
taken at a schedule rate for as long as the supply is taken. MMC is the minimum amount
to be paid by a customer in a month and it may be in the form of Project Minimum
Monthly Charge (PMMC) or Guaranteed Minimum Monthly Charge (GMMC) or Tariff
MMC (shown in Schedule 1) which will be mentioned in the supply contract. A customer
taking medium or high voltage supply may initially be required to pay PMMC or GMMC
for the period as specified in the definitions (1(r) and 1(s) above) , after which they shall
be subject to the Tariff MMC only. The Tariff MMC rate for each tariff category is in
accordance with the rates as per Schedule 1.
(b)
Each customer is required to maintain as deposit a sum sufficient to cover the estimated
charges for two months supply of electricity. The deposit less any outstanding amount,
if any, is refundable when the customer ceases to take a supply. Deposits are not
transferable. All cash deposits will entitle the customers to a rebate which will be credited
to the customers account once a year. Currently the rebate is calculated at 5% per annum
of the cash deposit value.
(c)
Accounts are due for payment on or before the date mentioned in the electricity bill
which is 15 days from the meter reading or billing date. The supply of electricity may be
disconnected if accounts are not paid when due and a reconnection fee shall be charged
for restoration of supply.
(d)
A late payment penalty charge may be imposed to customers who fail to settle their
current bill in full within the stipulated time frame. By imposing this late payment
penalty charge TNB does not waive its right to disconnect the supply to such customers.
2.7
(a) All fees and charges referred to above shall be advised to the customer on an official bill and
payment shall be acknowledged by an official receipt.
(b) No money may be handed to any employee of Tenaga Nasional Berhad other than a Cashier.
2.8
The customer shall give at least three (3) working days notice to the local TNB office of his
intention to cease taking supply. If no such notice is given, the customer shall be responsible for
the payment of all charges up to the date of the next meter reading or until a contract is signed by a
new customer for the same premises.
2.9
POWER FACTOR
The customer shall use his best endeavours to obtain the highest Power Factor possible in the
operation of any of his electrical installations. The customer must achieve a minimum power
factor which is currently set at 0.90 for high voltage customers and 0.85 for other customers . A
penalty shall be imposed if this minimum power factor is not achieved. This penalty is calculated
as follows:If the Average Power Factor of any customer in any month is found to be:
(a)
Below 0.85[0.90] and up to 0.75[0.80] lagging, a supplementary charge of one and onehalf per cent (1%) of the bill for that month for each one-hundredth part (0.01) below
0.85[0.90] and up to 0.75[0.80] lagging Power Factor will be added to the bill for that
month, and
(b)
Below 0.75[0.80] lagging, in addition to the charge payable under sub-paragraph (a)
above, a supplementary charge of three per cent (3%) of the bill for that month for each
one-hundredth (0.01) part below 0.75 [0.80] lagging Power Factor will be added to the
bill for that month.
Note: The Malaysian Grid Code specifies that connections made to the system of 132kV and
above are to maintain a minimum power factor of 0.90. Power factor figure shown within
the square bracket is for all high voltage customers and those customers under customised
supply agreements. Power factor figures without the square bracket apply to other
customers.
The minimum power factor of 0.85[0.90] shall be subject to change to comply with the
requirements of the Malaysian Grid Code and Malaysian Electricity Distribution Code when the
latter comes into force. The range of power factors stated in (a) and (b) above for computing the
power factor penalty shall be adjusted equitably to reflect any changes in the minimum power
factor figure as specified in the above codes.
2.10
TEMPORARY SUPPLY
A customer who applies for temporary supply shall be charged at the tariff rate appropriate to their
category plus a thirty-three per cent (33%) surcharge on the total monthly bill. The supply
agreement for the temporary load shall be time restricted and the customer shall be subjected to a
Connection Charge of 100% of the total cost of installing and subsequent dismantling of TNBs
infrastructure to give this temporary supply.
2.11
In addition to the appropriate tariff rate there will be a surcharge for transformer operated electric
welding equipment installed for low voltage customers at RM3 per kVA per month, and for
medium and high voltage customers at RM2 per kVA per month.
Motor-operated welding sets are exempted from the above surcharge.
3.
The present tariff rates which take effect from 1 May 1997 is shown in Schedule 1. These tariff
rates are the approved rates by the government in accordance with section 26 of Electricity Supply
Act 1990. The tariff rates offered by TNB, on average, are among the lowest in the East Asian
Region.
For the approved tariff rates charged, TNB will attempt to maintain minimum standards of
performance as laid down in the Terms and Conditions of Licence to TNB which includes
restoration of supply within 4 hours for minor breakdowns and 2 days for major breakdowns.
Customers who require higher specifications for reliability and quality of supply (which is above
the minimum standards of performance) may apply to TNB for their requirements to be met at
negotiated electricity rates under a special supply agreement provided for under section 29 of
Electricity Supply Act 1990.
4.
Section 29 of Electricity Supply Act 1990, gives a provision for a special agreement to be made between
TNB and customer which defines special terms and conditions of supply including tariff rates to be decided
upon via negotiations.
Tariffs for Top-up & Standby Services, Bulk Supply for Distribution Licensees and Thermal Energy
Storage Installations are among the customised tariffs applicable under the provision of section 29 of the
Electricity Supply Act 1990.
These tariff rates apply to customers who generate their own electricity by way of Cogeneration.
(b)
Top-up supply is the additional supply required by a co-generator who does not produce
sufficient electricity for its own use.
(c)
Standby supply is the supply that TNB provides to a co-generator in the event that the cogenerator does not generate electricity due to plant failure or planned shutdown for
maintenance.
(d)
For standby supply, the customer has a choice of firm or non firm supply. Non Firm Standby
implies that TNB does not guarantee that supply can be given when the co-generator fails or
is shutdown for maintenance.
(e)
The rates for Top-Up and Standby Services under standard conditions of supply are given in
Schedule 2.
(f)
The co-generator is to pay the full costs to TNB for the infrastructure involved in providing
the top-up and/or standby services.
5.0 SCHEDULES
5.1 SCHEDULE 1
TNB TARIFF RATES (Effective from 1 May 1997)
TARIFF CATEGORY
UNIT
RATES
Sen/kWh
Sen/kWh
Sen/kWh
21.8
25.8
27.8
Sen/kWh
28.8
RM/kW
17.30
Sen/kWh
20.8
RM/kW
25.70
Sen/kWh
20.8
Sen/kWh
12.8
Sen/kWh
25.8
Sen/kWh
23.8
UNIT
RATES
TARIFF CATEGORY
RM/kW
17.30
Sen/kWh
19.8
RM/kW
13.20
Sen/kWh
18.8
RM/kW
21.70
Sen/kWh
20.8
Sen/kWh
12.8
RM/kW
18.40
Sen/kWh
18.8
Sen/kWh
10.8
TARIFF CATEGORY
UNIT
RATES
RM/kW
20.80
Sen/kWh
19.8
Sen/kWh
11.8
RM/kW
16.20
Sen/kWh
17.8
Sen/kWh
9.8
Sen/kWh
21.8
RM/kW
12.00
Sen/kWh
17.8
RM/kW
17.00
Sen/kWh
17.8
Sen/kWh
9.8
UNIT
RATES
TARIFF CATEGORY
10
Sen/kWh
17.3
Sen/kWh
10.8
Sen/kWh
11.8
5.2 SCHEDULE 2
11
Unit
Top-Up
Standby
Firm
NonFirm
RM/kW/month
Sen/kwh
17.30
20.8
25.00
9.30
RM/kW/month
Sen/kwh
Sen/kwh
25.70
20.8
12.8
25.00
10.50
RM/kW/month
Sen/kwh
17.30
19.8
25.00
8.80
RM/kW/month
Sen/kwh
13.20
18.8
25.00
6.70
RM/kW/month
Sen/kwh
Sen/kwh
21.70
20.8
12.8
25.00
8.70
RM/kW/month
Sen/kwh
Sen/kwh
18.40
18.8
10.8
25.00
7.30
RM/kW/month
Sen/kwh
Sen/kwh
20.80
19.8
11.8
25.00
7.60
RM/kW/month
Sen/kwh
Sen/kwh
16.20
17.8
9.8
25.00
5.90
RM/kW/month
Sen/kwh
12.00
17.8
25.00
4.80
RM/kW/month
Sen/kwh
Sen/kwh
17.00
17.8
9.8
25.00
6.70
12
Kedai Tenaga adalah satu rangkaian pusat-pusat perkhidmatan dan khidmat nasihat yang ditubuhkan oleh TNB. Antara perkhidmatanperkhidmatan yang ditawarkan di Kedai Tenaga adalah:(a) Perkhidmatan Pelanggan
Kedai Tenaga is a chain of customer service and advisory centres set up by TNB. Among the services offered at Kedai Tenaga are :(a) Customer Service
One stop-payment counter for all electricity and other utility bills.
Electricity supply application.
Inquiries pertaining to billing and others.
Dikeluarkan oleh:
Issued by:
Website: http://www.tnb.com.my
Website: http://www.tnb.com.my