Professional Documents
Culture Documents
Interstate 91 Presentation
Interstate 91 Presentation
Introduction
The Rehabilitation Project will replace the deck of the I-91 Viaduct, which
is in poor condition, to reduce repair cost, increase safety and accessibility
It is running concurrent with a study of long-term Alternatives for the
Viaduct
The Alternatives Study will have a robust outreach program; investigate
alternatives; and look to permitting, funding and construction options
all long-term activities (possibly more than a 10 year process)
Project Purpose
To replace the bridge deck of the I-91 Viaduct in Springfield, due to its poor
condition the result will be a more reliable and dependable highway
Project Need
The I-91 Viaduct is a critical part of the Interstate Highway System and
closing this structure would have significant impacts to western MA.
Annual maintenance to the bridge deck is increasing
MassDOT wants to be proactive in maintaining the reliability of this
roadway and extending the structures service life.
Project Limits
Project Scope
Rehabilitation Project includes the following:
Project Schedule
September 27, 2014
Project Advertised
December 2014
Bid Opening
March 2015
Contract Award
April 2015
Notice to Proceed
May 2015
Preconstruction Meeting
Bridge Data
Bridge was built in the late 1960s
I-91 Northbound and I-291 EB Ramp represent 67 spans and approx.
321,000 SF of bridge deck
I-91 Southbound and I-291 WB Ramp represent 62 spans and approx.
293,000 SF of bridge deck
The structure is approximately 4,400 feet in length
Construction
I-91 AM peak traffic volumes range between 2,800-4,500 vph per direction
I-91 PM peak traffic volumes range between 3,100-5,700 vph per direction
Individual I-291 ramps process between 1,300-1,800 vph during peak hours
Three (3) lanes per direction with numerous ramps within project area
Traffic consists of approximately 1/3 regional, 1/3 to/from I-291, and 1/3 local trips
Access to downtown and local businesses will be maintained utilizing East Columbus and HOF
Traffic -
(Stage 1)
(Stage
1)
Traffic - Traffic Management Approach
Traffic -
(Stage 2)
Traffic -
(Stage 2)
Critical Intersections:
Monitoring Cameras
Construction Impacts
Two parking structures exist within the
project limits - Temporary closures of
certain areas will be required
(minimum number of spaces required
to remain open on top levels at all
times)
Coordination with other projects in the
project area, including West Springfield
Rotary and Casino projects
Abutting businesses
Factsheets
Fliers
Social media
Presentations
Briefings
Meetings
Newsletters
Signs