Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

FR-HSR-0040-11-01-00

Tim Doherty, MassDOT


Cherron Riddick
i
i
i
route
Project will enable Amtrak's
East Northfield , MA. The Project will utilize a $75 million Federal Railroad Administration (FRA) grant from the American Recovery and Reinvestment
(ARRA) to undertake rail improvements in the Pioneer Valley in Western Massachusetts. The Project also includes bicycle/pedestrian improvements in
City of Northampton , MA with the construction of an underpass that runs under the rail line. An additional benefit of the rail line rehabilitation will be
improved freight service for customers along the line and within western Massachusetts.
improvements to the Knowledge Corridor will occur on the Connecticut River mainline of the Pan Am Southern (PAS) railroad , a joint venture between
i
Am Railways and Norfolk Southern . MassDOT , through its Rail and Transit Division , has designated the Massachusetts Bay Transportation
Design and Construction Department to oversee the implementation of the Project through final design and construction and has entered into a
I r.,,n,,tnJclinn Agreement with Pan Am Southern , LLC to construct the Project.
and
is currently being revised to
' high level platforms. To mitigate the delay to ready for revenue service, MBTA will construct temporary platforms and perform other work
to support revenue service as an emergency repair contract through MassDOT managed by MBTA. Damon Road Traffic Signal Installation has
from Underpass and will be incorporated into the emergency repair contract. The Underpass will be included in the Stations bid package.
E CORRIDOR PAN AM - Grade crossings, track work & signal equip. & infrastructure installations ongoing . PAS completed grade crossings
throughout the Right of Way. Line of sight clearing , roadway striping and signage remain to be completed . PAS Signal crew installing conduit &
control devices at grade crossings. PAS crew preparing Greenfield & Northampton track beds and clear ROW edge . NS track crew completed CWR
I
, with 4.5 mile remaining to be constructed by PAS .

Cumulative Financial Trends

Project Progress

60000
0%

20%

40%

60%

80%

100%

120%

60000

50000
C)

40ctb

-:

70000 f--

300lltl
20000

10000
E

Arr

M :l ll

June

July

August

~ E sti ma te d

~ Act u a l

::;!Planned ..

Actu al 0/a ..

Planned

i
i
i
I
PAS- Welding Main Li ne Track, Special Track work , and Surfacing. PAS continuing with installation of turnouts. Grade Crossing and wayside signal work ongoing.
MASS DOT- Provide add itional funding for the project.
MBTA- Advertise Stations and Underpass .
URS - Continue Program and Construction Management.

Sept

You might also like