Professional Documents
Culture Documents
Managing Offshore Process Plant Integrity
Managing Offshore Process Plant Integrity
Abstract
Loss of hydrocarbon containment accidents present the
greatest threat to the offshore workforce. Hence it is
imperative that the highest standards are maintained with
respect to the design and operation of offshore process plant.
The Offshore Safety Division (OSD) of the UK Health and
Safety Executive, the British health and safety regulatory
body, has undertaken a series of theme audits examining the
management of offshore hydrocarbon production facilities.
The focus for the audits was the adequacy of the safety
management systems in place to control hydrocarbon
containment and included both design and operational
aspects. The paper discusses the principal findings from the
audits and describes actions required to further improve
process plant integrity management over the lifecycle of an
offshore installation.
Introduction
This paper describes the main general problem areas with
respect to offshore process integrity management identified
during 8 audits of installations on the UK Continental Shelf
over the period 1996 to 1998. The audits which were carried
out by the Offshore Safety Division of the UK Health and
Safety Executive, encompassed a range of operating
companies and also covered different installation types from
large oil installations through to floating production facilities
and manned gas platforms.
The audits examined the management of process operations
by each dutyholder. This involved looking in detail at a
process related 'slice' of each dutyholder's safety
management system against the concepts expressed in
was greatly increased due to the low level alarm and low low
level trip being taken from the same tapping as the primary
level controller.
Unlocked bypass valves around shutdown valves
Shutdown valves are frequently fitted with bypass valves to
permit their removal for maintenance purposes or to prevent
excess differential pressure across the valve seat. However if
the purpose of the associated shutdown valve is not to be
seriously compromised, it is essential that the bypass valves
are closed in normal operation. This is usually achieved by
locking them and placing them on the locked valve register.
On several installations, bypass valves were not locked
closed and on 2 installations bypass valves were found to be
open. Figure 1 below shows a typical bypass arrangement as
shown on a P&ID.
Fig 1
out.
Common alarms to different locations
Individual process systems, (eg gas compression) are
sometimes designed to operate with a local control panel
with some alarms relayed to a central control room (CCR).
In general such arrangements can work well if appropriate
attention is paid to the alarm provisions in the central
facility. Particular problems identified were: (a) systems
which only had 'common' alarms in the CCR, providing
insufficient detail as to the nature of the fault condition.
More detailed diagnosis required dispatch of an operator to
the local control panel. Safety critical fault alarms should
always be repeated in both locations; (b) where the receipt
and acceptance of a single fault condition in the CCR would
'overwrite' the receipt of any further alarms from the same
system.
Training and Competence
Emergency training and procedures. Written procedures
did not always cover process upset conditions or describe
what action should be taken under different process
emergency conditions. This was an aspect also absent from a
number of the training and competence schemes where the
emergency training element was focused on actions to be
taken following a major incident rather than actions relevant
to preventing a process upset developing into a major
incident.
Familiarity with key risk areas
A knowledge of the principal sources of risk on an
installation may assist in modifying the behaviour of
personnel such that increased care and attention will be taken
within 'higher risk' areas such as gas compression and with
'higher risk' activities . However, although the key risk areas
on different installations had been identified during
preparation of the Safety Case, this information had not
always been successfully conveyed to operations personnel.
Lack of adequate handover of specialist process
packages
Typical process plant will incorporate a number of specialist
packages, (eg gas compression units) which will normally be
commissioned by the manufacturers own teams. Evidence
from the audits indicated that whilst platform staff were
meant to be involved in this work to gain familiarity with the
equipment, they were sometimes seen as 'in the way' and
slowing down progress and hence discouraged from detailed
involvement. This had resulted in packaging being handed
over to process personnel with only a limited knowledge of
how to operate them. One company had had two loss of
hydrocarbon containment incidents in quick succession
attributable to operator unfamiliarity.
Training and competence programmes
Some training and competence programmes were in the
process of being developed or upgraded. In general, whilst
very good training programmes appeared to be in place for
new recruits, there sometimes appeared to be gaps present
Fig. 2
GAS / WATER IN
GAS OUT
LIC
SEPARATOR
VENT
LCV
SUMP TANK
Conclusions
The Health and Safety Executive undertook this series of
audits in the light of concerns over the number of loss of
hydrocarbon containment incidents which were being
reported each year from installations in the UKCS. The
findings highlight areas of process operation where
additional management effort by dutyholders may be
beneficial
in
securing
better
compliance