Simple Scope Change Process and Plan
Simple Scope Change Process and Plan
Solicit potential scope change requests from any project stakeholder, including the
project team, clients, sponsors, etc.
2.
Smaller projects can document the scope change in a short form or an e-mail. For
larger projects, the scope change request should be formally documented using a
Scope Change Request Form. The important thing is that you need to document the
scope change in writing. Don't act on scope change requests you receive verbally.
3.
Enter the request into the Scope Change Log for tracking purposes.
4.
The person making the scope change request should define the business value to
the project. The sponsor will need this information to make a final decision.
5.
The project manager request to a team member for further investigation. (The project
manager could assign it to himself.) -----first determine how much time it will take to
investigate the scope change request.
Note If the time required to perform the analysis will cause deliverable dates
to slip, the request must first be taken to the sponsor to determine whether
the request should be investigated or not.
6.
If the sponsor gives the initial approval to proceed, the analysis is done AND
workplan and budget may need to be updated to reflect this new work.
However - If the sponsor does not agree to investigate the change request, then the request
should be placed closed as "not approved" on the Scope Change Log.
7.
Once Analysis is done - Take the scope change request, alternatives, business value
and project impact to the sponsor for a resolution (yes we do it or no, we dont do it).
8.
9.
Document the resolution briefly on the Scope Change Log. If the Sponsor does not
agree to the change request, then the request should be closed as 'not approved' on the
Scope Change Log.
10.
If the scope change request is approved, the appropriate activities are added to the
workplan to ensure the change is implemented. The project budget should also be
updated, if necessary.
11.
Throughout the process, make sure that you communicate all scope change status and
resolution to project team members and other appropriate stakeholders. This is usually done
by attaching your current Scope Change Log to your Status Report. This helps manage
expectations and shows how approved scope change requests are impacting the project
end date and budget.