Kumar Srinivasan.
Regards,
Amit
Hi,
Then try implementing the following logic. Not sure if this can help you.
Use a material that is set up to trigger the production order and attach this material to a network activity that
is set to be reserved for project stock Q and can only be GI to that WBS element. The planned costs are
recognized in the project but the Actuals are only recognized when the finished material is GI back to the
project. You can use your planned production orders and MRP in exactly the same way but they are just linked
back to the project when they are completed.
If you need to transfer planned orders that are already in place then it can be done in MM.
Theres a goods movement type specific to where you need to reference the WBS element that is
set for requirements grouping.
Regards,
Amit