PARAMETERS
1. Project Location
2. Land Allocation for
Projects 1 hectare &
above
a. Saleable area
b. Non-saleable area
b.1 area for parks and
playgrounds for projects 1
hectare and above
70% (maximum)
30% (minimum)
PARAMETERS
Mandatory provision of area for neighborhood multi-purpose center both for economic and
socialized housing projects with an area of 1 hectare and above. These areas are nonsaleable. However, the developer may provide for areas for community facilities such as
schools and convenience/retail centers in excess of the mandatory requirement set forth
in this rule which shall be deemed saleable. The use of the said area shall be indicated in
the plan and annotated in the title thereto.
REVISED IMPLEMENTING RULES & REGULATION FOR PD957
Open Market Housing
Medium Cost Housing
100 sqm.
PARAMETERS
6. Road Right of Way
54 sqm.
36 sqm.
48 sqm.
32 sqm.
96 sqm.
60 sqm.
80 sqm.
50 sqm.
Saleable lots designated as duplex/ single attached and/ or row house lots shall be
provided with housing components
Saleable lots designated as duplex/ single attached and/ or row house lots shall be
provided with housing components
Price of saleable lots intended for single-detached units shall not exceed of 40% of the
maximum selling price for house and lot package.
Price of saleable lots intended for single-detached units shall not exceed of 40% of the
maximum selling price for house and lot package.
8m
8m
4m
3m
6m
4m
Maximum length of block is 400 meters. However, blocks exceeding 250 meters shall be
provided with a 2-meter alley approximately at mid length.
Note:
1. Interior subdivision project must secure right-of-way to the nearest public road
and the right-of-way shall be designated as the interconnecting road with a
minimum right-of-way of 10 meters. This fact shall be annotated on the title of
said road lot and must be donated and deemed turned over to the LGU upon
completion of the said interconnecting road.
REVISED IMPLEMENTING RULES & REGULATION FOR BP220
Economic Housing
Socialized Housing
2. Subdivision projects abutting main public thoroughfare must provide efficient
setbacks (at least 3.0 meters in depth by 5.0 meters in length) at both sides of
the subdivision entrance to accommodate loading and unloading of passenger.
3. Contiguous projects or projects to be developed by phases shall be provided
with interconnecting road with a minimum right-of-way of 10 meters.
4. Alley shall have a width of 2.0 meters intended to break a block and to serve
both pedestrian and for emergency purposes, both ends connecting to streets. It
shall not be used as access to property
5. Path walk shall have a width of 3.0 meters intended only to provide pedestrian
access to property for socialized housing projects. It shall have a maximum
length of 60 meters
12 m
10 m
6m
3m
8m
4m
Maximum length of block is 400 meters. However, blocks exceeding 250 meters shall be
provided with a 2-meter alley approximately at mid length.
Right-of-way (ROW) of major roads shall be increased as project size increases.
Major road shall maintain a uniform width of road right-of-way. Tapering of road width shall
not be allowed, where the road right of way is wider than the prescribed standard for the
interconnecting road of the proposed subdivision.
REVISED IMPLEMENTING RULES & REGULATION FOR PD957
Open Market Housing
Medium Cost Housing
Note:
1.
2.
3.
Interior subdivision project must secure right-of-way to the nearest public road and
the right-of-way shall be designated as the interconnecting road with a minimum
right-of-way of 10 meters. This fact shall be annotated on the title of said road lot
and must be donated and deemed turned over to the LGU upon completion of the
said interconnecting road.
Subdivision projects abutting main public thoroughfare must provide efficient
setbacks (at least 3.0 meters in depth by 5.0 meters in length) at both sides of the
subdivision entrance to accommodate loading and unloading of passenger.
Subdivision projects shall have provision for future expansion where applicable, by
designating a minimum interconnecting road right-of-way of 10 meters.
PARAMETERS
Major
(m)
8
10
10
10
12
15
Collector
(m)
8
8
8
10
Minor
(m)
6.5
6.5
6.5
6.5
6.5
6.5
Major
(m)
8
10
10
10
12
15
Collector
(m)
8
8
10
Minor
(m)
6.5
6.5
6.5
6.5
6.5
6.5
ROW
Carriageway
ROW
Carriageway
6
5
6
5
2
2
The minimum right-of-way of major roads shall be in accordance with the preceding table.
However in the case where the major road will serve as the interconnecting road, it shall
have a minimum right of way of 10 meters. It shall have a 15-centimeter mix gravel (pit
run) basecourse on well compacted subgrade.
REVISED IMPLEMENTING RULES & REGULATION FOR BP220
Economic Housing
Socialized Housing
Major roads shall maintain a uniform width of road right-of-way tapering of road width shall
not be allowed where the right-of-way is wider than the prescribed standard for the
interconnecting road of the proposed subdivision.
Major
(m)
10
12
12
12
15
15
Collector
(m)
10
10
10
12
12
Minor
(m)
8
8
8
8
10
10
Major
(m)
10
10
12
12
12
15
Collector
(m)
10
10
10
12
Minor
(m)
8
8
8
8
8
8
PS
1.30 m
0.80 m
0.80 m
0.40 m
SW
1.20 m
1.20 m
1.20 m
0.60 m
PS
1.30 m
0.80 m
0.80 m
0.40 m
-do-do-do-
SW
1.20 m
1.20 m
1.20 m
0.60 m
Optional
0.50 m
Optional
Optional
PARAMETERS
Concrete / Asphalt
Concrete / Asphalt
Macadam
Macadam
Macadam
REVISED IMPLEMENTING RULES & REGULATION FOR BP220
Economic Housing
Socialized Housing
Concrete road pavement shall have a minimum thickness of 150 millimeters and a
minimum compressive strength of 20.7 Mpa at 28 days. Asphalt pavement shall have a
minimum thickness of 50 millimeters.
Mandatory connection to appropriate public water system. Each subdivision shall have at
least an operational deep well and pump sets with sufficient capacity to provide ADD to all
homeowners provided further that a spare pump and motor set is reserved. Water Supply
shall be potable and adequate.
150 liter per capita per day for household connection
Concrete / Asphalt
Concrete / Asphalt
Concrete / Asphalt
Concrete / Asphalt
Concrete / Asphalt
Concrete / Asphalt
Concrete / Asphalt
Concrete / Asphalt
Concrete / Asphalt
Concrete / Asphalt
REVISED IMPLEMENTING RULES & REGULATION FOR PD957
Open Market Housing
Medium Cost Housing
Concrete road pavement shall have a minimum thickness of 150 millimeters and a
minimum compressive strength of 20.7 MPa while roads may either be concrete of same
thickness and compressive strength or asphalt with minimum thickness of 50 millimeters.
Side walk pavement shall have a minimum compressive strength of 17.2 MPa
Mandatory connection to appropriate public water system; centralized water supply system.
Each subdivision shall have at least an operational deep well and pump sets with sufficient
capacity to provide ADD to all homeowners.
150 liters per capita per day for household connection
Provision for fire protection facilities shall comply with the requirements of the Fire Code of Provision for fire protection facilities shall comply with the requirements of the Fire Code of
the Philippines.
the Philippines.
o Mandatory individual household connection to primary and alternate sources of
o Mandatory individual household connection to primary and alternate sources of
power if service is available in the locality.
power if service is available in the locality.
o Mandatory provision of street lighting per pole if 50-meter distance; at every
o Mandatory provision of street lighting per pole if 50-meter distance; at every pole,
pole, if the distance is less than 50 meters.
if the distance is less than 50 meters.
o Electric bills shall be proportionately shouldered by users prior to issuance of
o Electric bills shall be proportionately shouldered by users prior to issuance of
COC and turnover of open space to LGU.
COC and turnover of open space to LGU.
o Installation practices, materials and fixtures used shall be in accordance with the
o Installation practices, materials and fixtures used shall be in accordance with the
provision of the Philippine Electrical Code and Local Utility Company.
provision of the Philippine Electrical Code and Local Utility Company.
o The drainage system for economic and socialized housing projects shall be The drainage system must conform with the natural drainage pattern of the subdivision
made of concrete lined canal with adequate capacity with load bearing cover
site, shall drain into appropriate water bodies, public drainage system of natural outfalls.
o The drainage system must conform with the natural drainage pattern of the
subdivision site, shall drain into appropriate water bodies, public drainage For both open market and medium cost subdivision projects, underground drainage system
system of natural outfalls
shall be properly engineered and environmentally sound, and shall be provided with
o If applicable, underground drainage system shall be provided with adequate adequate Reinforced Concrete Pipes (RCP), catch basins, manholes/inlets and cross drain
reinforced concrete pipes (RCP), catch basins, manholes/inlets and cross drain for efficient maintenance. Minimum drainage pipe diameter shall be 30 centimeters.
for efficient maintenance. Minimum drainage pipe diameter shall be 30
millimeters.
REVISED IMPLEMENTING RULES & REGULATION FOR BP220
REVISED IMPLEMENTING RULES & REGULATION FOR PD957
Economic Housing
Socialized Housing
Open Market Housing
Medium Cost Housing
Individual Septic Tank conforming to the standards and design of Sanitation Code of the
Philippines.
Construction of the individual septic tanks shall conform to the standards and design of
Sanitation Code of the Philippines.
Whenever applicable, connection shall be made to an approved public or community
sewer subject to the requirements and provisions of the Sanitation Code of the Philippines
and other applicable rules and regulations.
Provide Sanitary and efficient refuse collection and disposal system whether
independently or in conjunction with the local government garbage collection and disposal
services.
22 sqm
22 sqm
18 sqm
18 sqm
22 sqm
18 sqm
Mandatory provision of firewall for duplexes/ single-attached units and at every unit for
row houses.
Individual Septic Tank shall conform to the standards and design of the Sanitation Code of
the Philippines (PD 856) and its implementing Rules and Regulation.
Whenever applicable, connection shall be made to an approved public or community sewer
subject to the requirements and provisions of the Sanitation Code of the Philippines and
other applicable rules and regulations.
Provide Sanitary and efficient refuse collection and disposal system whether independently
or in conjunction with the local government garbage collection and disposal services.
42 sqm
42 sqm
30 sqm
30 sqm
42 sqm
30 sqm
In no case shall the number of row houses exceed 20 units per block/ cluster and/ or
beyond 100 meter in length.
The number of row houses shall not exceed 20 units per block/ cluster but in no case
shall be more than 100 meters in length.
15.2 Minimum Level of
Completion
a. Single Detached
b. Duplex/ Single
Attached
c. Row house
PARAMETERS
16. Setback/ Yards
a. Front Setback
b. Side Yard
c. Rear Yard
d. Abutments
Same
Same
Same
Same
Mandatory provision of firewall for duplexes/ semi-attached units and for every unit of row
houses.
REVISED IMPLEMENTING RULES & REGULATION FOR PD957
Open Market Housing
Medium Cost Housing
Shall conform to the provisions of the National Building Code of the Philippines