MAIN ACHIEVEMENTS
Description of the situation before the project implementation:
There are several elements of infrastructure for road monitoring on A2 motorway in Romania but there is
still a demand for integration of these infrastructures. A study and pilot project for A1 motorway BucharestPitesti/Bucharest ring is needed.
In Romania there is no centralized information regarding the traffic and roads infrastructure status.
Different information exists at different Infrastructure Administrators or Authorities, but there is no system
gathering all the relevant information from one area and presenting it to the public.
2) Definition of regional corridor, project area limitation, corridor description, administrators, operators,
technological level;
3) Identification and definition of monitoring elements (pavement, parking areas, equipments and systems,
bridges, signs, vehicles)
4) Identification and definition of ITS solutions for monitoring (sensors, cameras, operators, drivers,
travelers)
5) Planning of ITS deployment on road monitoring (phases, sources of information, actors, users, political
aspects, connection with other modes of transport and corridors)
6) Interfaces with other ITS systems a minimal ITS architecture for Road Monitoring
7) System components that creates the ITS infrastructure for road monitoring Data Quality
B. The elaboration of the Technical Specification/tender documentation for the study and for the pilot project.
1) The study regarding traffic monitoring and road infrastructure- Technical Specification
Identification and definition of the main monitoring elements
Identification and definition of ITS solutions for monitoring (sensors/network sensors, cameras, data
acquisition equipment, fixed and mobile communication network)
Planning of ITS deployment on road monitoring
Interfaces with other ITS systems a minimal ITS architecture for Road Monitoring
System components that creates the ITS infrastructure for road monitoring
Requirements for the consultant team
2) Pilot Project - Technical Specification
Location
Structure and Functions
Technologies
Execution technical project
Testing
Evaluation pilot system
Recommendations regarding system extend at the national level
3) Justificatory note regarding Cost Estimation
4) Assignation motivation Criteria
Sensors network the sensors will be monitoring three aspects: traffic, weather conditions and
equipment state
Communications network this network has three main components: peripheral, local and central
Date (mm/yyyy)
Offers submission
Contract signature no.93/20626
Submission of report
Report Acceptance
09/2008
10/2008
12/2008
12/2008
600.000
TOTAL
600.000
Study
Spent
Internal
External
26.587
TOTAL
26.587
4,43%
ECB monthly accounting rate of the euro for December 2008 EUR/RON: 3,9227
DELIVERABLES
Title of deliverable
MONI-EasyWay_National and International Status Report
MONI-EasyWay_Technical Specification
Language
Deliverable
Romanian
Romanian
Summary