Note : This form is designed for general use and may not be exhaustive. Modifications and
additions may be necessary to suit individual projects and to address specific environmental
issues and associated mitigation measures.
Stanley
Bay
Construction stage / status during inspection : Phase 1 Drainage & Road works
0900
Inspection Date :
Inspection Time :
25 January 2006
1500
CY Tam (Project Environmental
Dry
&
Inspected by :
Weather :
Engineer)
cold
Project :
Remarks
Implemented?
Inspection Items
1.
Yes
No*
N/A
1.1.
1.2.
1.3.
1.4.
1.5.
1.6.
1.7.
1.8.
1.9.
1.10.
1.11.
1.12.
Page 1
Site Location :
WBC
Remarks
Implemented?
Inspection Items
Yes
No*
N/A
2.
2.1.
2.2.
2.3.
2.4.
2.5.
2.6.
2.7.
2.8.
2.9.
2.10.
2.11.
2.12.
2.13.
2.14.
2.15.
Page 2
WBC
Remarks
Implemented?
Inspection Items
3.
3.1.
3.2.
3.3.
3.4.
3.5.
3.6.
3.7.
3.8.
4.
4.1.
4.2.
4.3.
4.4.
4.5.
4.6.
4.7.
4.8.
Yes
No*
Noise Control
Is the CNP (Construction Noise
Permit) valid for work during
restricted hours?
Are copies of the valid
Construction
Noise
Permits
posted at site entrance/exit?
Do
air
compressors
and
generators operate with doors
closed?
Is idle plant/equipment turned off
or throttled down?
Do air compressors and handheld breakers have valid noise
emission labels (NEL)?
Any noise mitigation measures
adopted (e.g. use noise barrier /
enclosure)?
Are
silenced
equipments
utilized?
Others (please specify)
Waste Management
Is the site kept clean and tidy?
(e.g.
litter
free,
good
housekeeping)
Are separate chutes used for
inert and non-inert wastes?
Are
separated
labelled
containers / areas provided for
facilitating recycling and waste
segregation?
Are construction wastes /
recyclable wastes and general
refuse removed off site regularly?
Are
construction
wastes
collected
and
disposed
of
properly by licensed collectors?
Are chemical wastes, if any,
collected
and
disposed
of
properly by licensed collectors?
Does chemical waste producer
license covers all major chemical
wastes produced on site?
Are chemical wastes properly
stored and labelled?
Page 3
N/A
WBC
Remarks
Implemented?
Inspection Items
4.9.
4.10.
4.11.
4.12.
4.13.
4.14.
5.
5.1.
5.2.
5.3.
5.4.
5.5.
6.
Are
oil
drums
and
plants/equipments provided with
drip trays?
Are drip trays free of oil and
water?
Is there any oil spillage? Cleanup
the
contaminated
soil
immediately?
Is
litter,
foam
or
other
objectionable matters in nearby
water drain/sewer cleaned?
Are asbestos wastes handled by
registered professionals?
Others (please specify)
No*
N/A
6.1.
7.
Yes
Resource Conservation
Page 4
WBC
Remarks
Implemented?
Inspection Items
Yes
7.1.
7.2.
and
7.3.
8.2.
8.3.
No*
N/A
Date
5 Jan 2006
Date
7 Jan 2006
Page 5
WBC
Page 6
WBC
Improvement Request:
Project
Site Location
Inspection Date
Inspected by
NC Reference
Description of NC
Root cause of NC
CPA adopted Target
completion date
Verified by PEO (Date)
NC Reference
Description of NC
Root cause of NC
CPA adopted Target
completion date
Verified by PEO (Date)
NC Reference
Description of NC
Root cause of NC
CPA adopted Target
completion date
Verified by PEO (Date)
Page 7