Download as pdf or txt
Download as pdf or txt
You are on page 1of 24

GRID

Renovation, Modernization
and Life Extension of
Power Plants
Opportunities and challenges
Strictly Private
and Confidential
February 2013

Agenda
Page
1
2
3

R&M - opportunity
R&M - challenges
Way forward

Appendices
1 Sustainability of up gradation
2 Case Study

1
8
15

17
19

Section 1
R&M - opportunity

Renovation, Modernization and Life Extension of Power Plants Opportunities and challenges
PwC

February 2013
1

Section 1 R&M - opportunity

Indias growing energy requirements need solutions and options are few...
Highlights:
Total capacity for India is 203 GW
with thermal energy accounting for
73% of capacity as of Jan13.
Thermal power supplied 631 billion
kWh (83%) of Indias electricity in
April- Jan13.
Thermal power has seen a growth
of 9% over past year as compared
to 2% rise in nuclear energy and
decrease of 13% in hydro energy in
the same period
Key
drivers
for
electricity
consumption in India include: 1. Peak shortage of 14% and
ongoing growth
2. Per capita use growing (but <
1/4th global average)
3. 44% households have no access
to electricity
4. Continued rise of urbanization
from 28% to 41% (2030)

... And, supply continues to


depend on thermal power*

Energy Demand is growing

Fuel Mix of capacity


1914
CAGR 7%
5%

1292

2%

350
MW

20%

968

73%

Thermal
2011-12

2016-17

Nuclear

Hydro

RES

2021-22

R&M program provides cost and fuel efficient thermal power generation for India with lower gestation periods
Renovation, Modernization and Life Extension of Power Plants Opportunities and challenges
PwC
*Source: CEA Reports, PwC Research

February 2013
2

Section 1 R&M - opportunity

R&M is supported by policy and regulations


Current policies governing R&M practises in India
(a) Electricity Act 2003
The Electricity Act2003 (EA 2003) is
the primary legislative instrument
which governs the electricity supply
industry in India.
Section 61 (C) of the Act requires the
appropriate Commission to set tariff
by considering, the factors which
would encourage competition,
efficiency, economical use of resources,
good performance, and optimum
investments

(b) National Electricity


policy,2005
National Electricity Policy notified by
the Govt. of India (GOI) in 2005 under
the provisions of EA 2003states the
following
Renovation and modernization for
achieving higher efficiency levels
needs to be pursued vigorously and all
existing generation capacity should be
brought to minimum acceptable
standards

(d) Integrated Energy Policy 2006


Integrated Energy Policy notified in
2006 within overall objective for
sustainable growth with energy security
and improved efficiency
Rehabilitation of existing thermal
stations could raise capacity at least
cost in the short run and this should be
taken up urgently.

(c) National Tariff Policy, 2006


National Tariff Policy notified by the
Govt. of India in 2006 under the
provisions of EA 2003 states:
Multi-Year Tariff (MYT) framework
may be prescribed which should also
cover capital investments necessary
for renovation and modernization
and an incentive framework to share
the benefits of efficiency improvement
be fixed by the Appropriate
Commission.

(e) Guidelines for Renovation and


Modernization / Life Extension
works of Coal/Lignite based Thermal
Power Stations, 2009
The guidelines provided a framework
to be followed if generators are to be
benefit from debt financing from the
Power Finance Corporation (PFC) at
an interest rate subsidy of 3-4 percent
Guidelines provide detailed
methodology for implementation of
R&M and LE&U programmes

Renovation, Modernization and Life Extension of Power Plants Opportunities and challenges
PwC

February 2013
3

Section 1 R&M - opportunity

R&M is supported by policy and regulations


Current policies governing R&M practises in India
(f) CERC (Terms and Conditions of
Tariff) Regulations, 2009
In order to provide requisite
compensation to the generating utility
for R&M:
Generating company for meeting the
expenditure on Renovation and
Modernization (R&M) for the purpose
of extension of life or a unit thereof
shall make an application before the
Commission for approval of the
proposal with DPR.

(g) Tariff Regulations by State


Electricity Regulatory
Commissions

(h) National Perspective Plan for


Renovation &Modernization:

In line with provision of the CERC


tariff regulations various state
electricity regulatory commissions have
also incorporated relevant provisions
for recovery of expenditure incurred
on R&M as part of their tariff
regulations.

Identification of thermal units


requiring LE during 12th Plans

(i) Indian Boiler Regulations, 1950


Regulation 391 A of IBR, 1950
elaborates on the aging effects on
boilers and maximum permitted
working pressure allowed for operation
of various types of boilers

Objectives:

Assessment of total investment


required during 12th Plans for LE
programme.
Road map for smoother
implementation of R&M/LE schemes
Projection of expected benefits

(j) PAT Scheme of the Bureau of


Energy Efficiency
PAT is a market based mechanism to
enhance cost effectiveness of
improvements in energy efficiency in
energy-intensive large industries and
facilities (classified as Designated
Consumers), through certification of
energy savings that could be traded

144 Thermal Power Plants in the


country have also been identified as a
set of designated consumers
Renovation, Modernization and Life Extension of Power Plants Opportunities and challenges
PwC

February 2013
4

Section 1 R&M - opportunity

Meanwhile market has also evolved to support R&M activity


Characteristics/
Market Change

Before
enactment of
the EA 2003

Current
Scenario

Implications for R&M

Presence of
power markets

Absent

Present

Alternate power procurement avenues available to state utilities to prevent


outages when plants undergo R&M
Increased focus on efficiency improvement owing to competitive
procurement of power

Private
Sector
Participation

Low

Medium

Increased private sector participation across the value chain in the


electricity supply industry has resulted in better response, lower leadtime and risk sharing.

Equipment
vendors base

Small

Medium

Open market policy of GoI and increasing capacity expansion has attracted
many international players, particularly Chinese players against market
dominant players like BHEL

Focus on
Optimization

Low

High

PAT Scheme of the BEE is aimed enhancing energy efficiency in existing


power plants has set power sector as one of the Designated Consumers
(DC).
DCs have to achieve notified reduction in fuel consumption (kg/kWh) by
2014-15

Market
framework for
Environmental
Compliance

Absent

Present

With power sector contributing 40% to carbon emissions of India, R&M


with short gestation time can support short and medium term strategy to
achieve National Action Plan on Climate Change

Coal Constraint

No

Yes

In an extreme coal supply constrained scenario, focus on available coal


being used in most efficient form by the market participants is high, hence
trend favors R&M of thermal plants

Renovation, Modernization and Life Extension of Power Plants Opportunities and challenges
PwC
*Source: CEA Reports, PwC Research

February 2013
5

Section 1 R&M - opportunity

R&M compares favourably to fresh capacity addition

Key factors

Output from Renovation and


Modernization of a thermal plant

Output from new thermal


capacity addition

Timelines

10-12 months

38-42 months

Rs 2-2.5 Crore/MW

Rs 4-5 Crore/MW

None

High

Negligible

High

Already present

To be developed

Only marginal addition/MW

0.94 Kg/unit of CO2 emissions*

Network already present

To be developed

Only marginal addition/MW

15-20 % of average cost of


supply / unit *

Already present

To be developed

Costs
Land acquisition issues
Environmental Clearances
Fuel and water linkages
Emissions
Transmission Capacity
Labour costs

Power purchase agreements (PPAs)

Renovation, Modernization and Life Extension of Power Plants Opportunities and challenges
PwC
*Source: CEA Reports, PwC Research

February 2013
6

Section 1 R&M - opportunity

And there is significant opportunity size available for stakeholders


Aging condition of thermal plants presents an opportunity

Program for 12th Plan


Particulars

R&M Works

LE Works

No. of Units

30

105

6501

21679

12000

32897

Estimated Cost (
Rs. Crores)
Expected Benefits

Life Extension

Generation
sustenance
only

6900

Number

Capacity(MW)

Central Sector

68

13953

State Sector

103

20982

Total

171

34835

12th Five Year Plan- Capacity


of Works for R&M

12th Five Year Plan- Capacity


of works for LE

15 Years

With total size of current opportunity being


32000MW in India, R&M presents a
unique opportunity for investors as
well as bidders
Around 2/3 of opportunity in R&M lies with
the state sector with around 20,000 MW
viable for R&M works
In 12th plan, GoI has undertaken the around
4000MW of capacity in the central sector
for R&M works along with ard. 13000MW of
capacity for LE works

13199

4341
MW

Additional
Generation(MU/
annum)

Thermal Plants > 20 years of age

8480
2160

Central

State

Renovation, Modernization and Life Extension of Power Plants Opportunities and challenges
PwC
*Source: CEA Reports, PwC Research

MW

Capacity(MW)

Particulars

Central

State
February 2013
7

Section 2
R&M - challenges

Renovation, Modernization and Life Extension of Power Plants Opportunities and challenges
PwC

February 2013
8

Section 2 R&M - challenges

Financing requirement for R&M


Key constraint :Huge financing costs in up gradation of plants act as deterrent for R&M program
Plan

R&M Works ( @
Rs. 1 Cr./MW)

Life Extension Works ( Rs. Crore)


LE without up gradation (
@ Rs. 1.25- 1.5 Cr//MW)

Total
( Rs. Crore)

LE with up-gradation (EE R&M)


(@Rs 1.5-2.0 Cr/MW)
Indigenous
funding

With external
funding

11th Plan onwards

950

2334

2356

450

6090

12th Plan

630

4640

8760

14030

Total

1580

2334

6996

9210

20120

Funding from own


resources( 20% of
estimated costs)

316

467

1399

1842

4024

Fund requirement
from indigenous
institutions like
PFC/REC/ etc.

1240

1867

5597

8728

External Assistance

7368

7368

Out of above fund requirement for EE R&M during 11th & 12th Plan, funding from external agencies to the tune of 96
million Euro from KfW for 3 units (630MW) and 180 million USD from World Bank have been committed.
Combining the huge financial costs for R&M along with deteriorating financial health of distribution
utilities due to non cost of supply reflective tariffs and high demand-supply gap , R&M program would need a huge
Renovation, Modernization and Life Extension of Power Plants Opportunities and challenges
February 2013
push from government policies to remain relevant in the present power situation in the country.
PwC
9

Section 2 R&M - challenges

Why is there lack of investment in R&M?


Generation Companies

Debtors for Generation Companies ( % of Income)


173%
138%

138%

113%
85%

Electricity
Flow

Money
Flow

70%
49%

54%
43%
33%
18%

27%
14%

22%

30%

27%
12%

41%
0%

Financial position for Distribution Companies( Losses


Crs)
10
23

Distribution Companies

11

10

14

6
18

15

20

11
FY 09

Profit making

Losses< 500 crores

Renovation, Modernization and Life Extension of Power Plants Opportunities and challenges
PwC

FY 10

Loss between 500-1000 crores

FY 11

Losses> 1000 crores

February 2013
10

Section 2 R&M - challenges

R&M phases
Pre Implementation
Identification of plant units
Plant Assessment based on RLA studies,
Energy Audit, Past history of plant
Selection of agencies for technical studies/
implementation support

Execution

Post Implementation

Arrival of equipments via


procurement plan

Post R&M Performance


guarantee tests

Plan for shutdown of plants

Plant Performance Analysis

Start of execution of R&M work

Follow up activities to meet


deficiencies

Closure on R&M work

Sourcing of funds

Post R&M Training and


O&M of Plant

Submission of proposal to regulator

Benefit Assessment from R&M

Evaluation of alternatives

Issue of tenders and selection of bidders


Procurement Plan design
Negotiation and award of R&M Contracts

Bidders/Vendors, OEMs
Financer
Execution Agency/Consultant
Generating Company
Regulator

Renovation, Modernization and Life Extension of Power Plants Opportunities and challenges
PwC
*Source: CEA Reports, PwC Research

Regulator

February 2013
11

Section 2 R&M - challenges

Key stakeholder concerns: Pre implementation


Utility

Pre
Implementation
phase

Bidder

Financer

Regulator

Gaps in evaluation
framework for
identifying plants
suitable for R&M

Poor baselining of
initial data makes it
difficult to provide
post R&M guarantees

Financing constraints
for undertaking the
program

Delay in decision of
undertaking R&M
post RLA studies

Low credit worthiness


of the utilities make it
tough for investors to
seek guarantees on
payback

Low level of
transparency over data
baselining by utilities
leading to issues with
R&M expenditure
approvals by regulators

Lack of internal
expertise to evaluate
technically or
commercially

Concerns over
contracting clauses
including liquidated
damages

Limited agencies to
carry out R&M studies
end to end

Inflexible price clause


do not allow for price
escalation due to
owner delays

Concern over
adequacy of regulatory
benefits
Low risk appetite of
utilities makes the
complex multi party
R&M exercise a
concern

Accuracy of estimated
costs and benefits for
R&M
Concern over
sustainability of
benefits achieved via
R&M works

Stringent
qualification
requirements for
bidders makes it
tough for parties to
qualify
Lack of
standardization of
tendering documents
for R&M works

Renovation, Modernization and Life Extension of Power Plants Opportunities and challenges
PwC
*Source: CEA Reports, PwC Research

February 2013
12

Section 2 R&M - challenges

R&M Program in India- Execution phase


Utility

Bidder

Low project planning


and change
management capacity
of personnel in state
generators

Lack of reliable third


parties for providing
adequate quality and
quantity of
equipments desired
for implementation

Concern over
contractual
requirements for
providing power in
R&M phase

Execution phase

Delay in approvals for


plant shutdown due to
power situation in the
state
Lack of transparency
and control over R&M
activities for Turn key
contract
Inability to integrate
multivendor activities
across various packages

Financer
Concerns over
execution capability
within costs and
timelines planned by
utility

Regulator
Impact of cost and
time escalation
Cost of power
purchased during the
renovation and
modernization

Delay in
implementation
approvals for
procuring equipments
from state utilities
Lack of drawings and
historical data of
relevant plants make
the implementation
difficult
Weak dispute
resolution mechanism
constraining the
execution of work

Renovation, Modernization and Life Extension of Power Plants Opportunities and challenges
PwC
*Source: CEA Reports, PwC Research

February 2013
13

Section 2 R&M - challenges

R&M Program in India- Post implementation phase


Utility

Bidder

Sustainability of up
gradations in the plant.
Some key areas are:

Project closure issues


due to slow speed of
decision making of
utility

Sustainability of
project benefits
achieved from R&M
works

Open item / dispute


resolution mechanism
not satisfactory

Poor health of public


sector finances

Post
Implementation
phase

Non existent
operational
documentation

O&M culture of the


utility

Inefficient
organizational
structure

Lack of specialized
operational cells for
effective O&M
practises

Absence of ex-post
evaluation and
feedback loop in R&M
works

Financer

Renovation, Modernization and Life Extension of Power Plants Opportunities and challenges
PwC
*Source: CEA Reports, PwC Research

Regulator
Sustainability of change
achieved in the plant
Concern over the
effectiveness of the
R&M program
Lack of post R&M
guarantees from
implementation
agencies
Justification of
additional cost on R&M
projects

February 2013
14

Section 3
Way forward

Renovation, Modernization and Life Extension of Power Plants Opportunities and challenges
PwC

February 2013
15

Section 3 Way forward

We need to solve for ...


1.

Focus on financial health of generating utility

2. Incentivize R&M through regulatory support


3. Enhance O&M capability in power generating utilities - adoption of R&M
culture
4. Create a framework for increased tie up between state and central
generating utility
5. Modularize the R&M approach through segmentation in key steps that are
interlinked
6. Enhance engagement of external experts (from other utilities / market) for
support in R&M decision making, execution and post project benefit
realization

7.

Create success stories for replication

Renovation, Modernization and Life Extension of Power Plants Opportunities and challenges
PwC

February 2013
16

Appendix 1
Sustainability of up gradation

Renovation, Modernization and Life Extension of Power Plants Opportunities and challenges
PwC

February 2013
17

Appendix 1 Sustainability of up gradation

Sustainability of up gradation: Preventive maintenance practises


Key constraint : Lack of preventive maintenance schedules leading to lack of sustainability
One of the major concern of utilities and
regulators is maintaining the sustainability
of up gradations in the plant
Utilities suffering from lack of preventive
O&M practises face this issue
Some key issues include:
1. Lack of robust data monitoring for
effective consumption baselining
2. Lack of unit wise energy efficiency data
analysis
3. Lack of accurate measurement of quality
and quantity of coal in the plant
4. Non existent operational documentation
available to relevant staff
5. Lax O&M culture of the utility along with
inefficient organizational structure
6. Lack of specialized operational cells for
effective O&M practises
7. Redundant training schedules used as a
tick mark exercise by the utility

Organizational culture and


climate :
Clarity on job descriptions for
key positions in O&M practices
along with key performance
indicators
Standardization of training and
development schedules for
employees

Knowledge Management
Process:
Establishment of consumption
baseline
Establishment of robust
knowledge management
framework implemented
through department level
Information systems for
sharing all relevant data on a
proper knowledge sharing
platform

Renovation, Modernization and Life Extension of Power Plants Opportunities and challenges
PwC

Preventive maintenance:
Presence of specialized cells like
O&E cell, Trip Committee,
Energy audit committee,
centralized maintenance
planning team, condition
monitoring cell for enabling
preventive maintenance
procedures

Energy Audits for efficiency:

Energy audits (including


efficiency tests for boiler,
turbine and other sub systems)
for capturing unit wise energy
efficiency instead of plant wise
efficiency. Analysis of unit wise
auxiliary power consumption
for benchmarking
February 2013
18

Appendix 2
Case Study

Renovation, Modernization and Life Extension of Power Plants Opportunities and challenges
PwC

February 2013
19

Appendix 2 Case Study

Case Study: Impact of financial position of utility on maintenance


expenditure... (1/2)

Overall cash crunch of the power sector in the state restricted adequate maintenance of the plants.
With the increase in age, effective expenditure on maintenance, rather than increasing has
practically gone down.

Expenditure on Repair and


maintenance at 2007 Levels ( L
Rs/MW)

FY07

FY08

FY09

FY10

FY11

4.34

4.81

3.54

3.96

3.86

Liquidity issues have further constrained the timely availability of spares, adversely resulting in
the health of the units.
Action Plan to Improve

MPPGCL envisages adequate expenditure on maintenance

With availability of funds, healthier practice of preventive maintenance will also be adopted.

The alternate option of LROT is also being explored for these units.

In parallel MPPGCL is also envisaging need based R&M works.

Comprehensive R&M works, as per guidelines of CEA are also being planned for PH 1 of SGTPS
Birsinghpur.

Renovation, Modernization and Life Extension of Power Plants Opportunities and challenges
PwC

February 2013
20

Appendix 2 Case Study

Case Study: R&M results are showing...(2/2)


MPPGCL has undertaken Need Based R&M

It has done in unit 6 & 8 of STPS Sarni & SGTPS Unit 2 in FY 12, results are encouraging.
Performance Improvement in Satpura Unit No.6 (AOH From 29 -July to 29-Sept 11)
S. No.

Particular

Generation in MU

Before AOH

After AOH

Gain

Gain in Rs Lakh

304.3

681.5

225.06

2 PLF in %

52.0

77.6

25.62

3 Aux.Consumption in %

11.9

9.9

4.50

4 Sp. Coal Cons. Kg/kwh

1.10

0.93

37052

712.5

5 Oil Cons.in Ml/kwh

8.4

1.4

1583

772.7

6 Heat Rate Kcal/kwh

3534

3378

156

Total

48.9

1534.1

Performance Improvement in Satpura Unit No.8(AOH from 9 Sept to 8 Dec.11)


S. No.

Particular

Generation in MU

Before AOH

After AOH

Gain

Gain in Rs Lakh

412.5

435.1

160.17

2 PLF in %

44.7

70.8

26.05

3 Aux.Consumption in %

12.5

11.0

3.39

4 Sp. Coal Cons. Kg/kwh

1.1

0.9

44360

853.0

5 Oil Cons.in Ml/kwh

9.3

2.9

1438

701.7

6 Heat Rate Kcal/kwh

3589

3396

193

Renovation,
TotalModernization and Life Extension of Power Plants Opportunities and challenges
PwC

34.8

February
1589.62013
21

Thank You

This publication has been prepared for general guidance on matters of interest only, and does not constitute professional advice. You should not act upon the
information contained in this publication without obtaining specific professional advice. No representation or warranty (express or implied) is given as to the
accuracy or completeness of the information contained in this publication, and, to the extent permitted by law, PricewaterhouseCoopers Pvt. Ltd., its members,
employees and agents do not accept or assume any liability, responsibility or duty of care for any consequences of you or anyone else acting, or refraining to act,
in reliance on the information contained in this publication or for any decision based on it.
2013, PricewaterhouseCoopers Pvt. Ltd.. All rights reserved. In this document, PwC refers to PricewaterhouseCoopers Pvt. Ltd. which is a member firm of
PricewaterhouseCoopers International Limited, each member firm of which is a separate legal entity.

You might also like