Professional Documents
Culture Documents
Echnical Eport: Drill Cuttings JIP
Echnical Eport: Drill Cuttings JIP
Echnical Eport: Drill Cuttings JIP
20 January 2000
Sponsors of the Drill Cuttings JIP
Phase I Summary Report (Rev 2)
Client:
Title of Report:
Indexing Terms:
Summary:
This report summarises all the research work done under Phase I of
the Drill Cuttings JIP
Louis Backwell, Susan Stephens, Amy Annand, M Stewart
(support), Andy Bolsover
Prepared by:
Approved by:
29003500
L Backwell
A. J. Bolsover
Issue Date
7th Jan00
17 Jan00
20 Jan00
p:\a9\atc\0001-0050\003500\r2\003.doc
Prepared by
LBACK
LBACK
LBACK
Approved by
SMS
AJB
AJB
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
CONTENTS
Page
EXECUTIVE SUMMARY (2 Pages)
1.0 INTRODUCTION
4.0 REFERENCES
p:\a9\atc\0001-0050\003500\r2\003.doc
20
20
21
22
24
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
EXECUTIVE SUMMARY.
The 1998 OSPAR meeting in Sintra led to the regulation of the decommissioning of
offshore installations. At that time there was little information on:
the means to avoid or minimise the disturbance of associated drill cuttings,
the effect of releasing the contents,
the effects of different disposal methods for cuttings pile materials.
As a result a Joint Industry Project (JIP) commissioned a 1 million research
programme to establish the best ways of dealing with these issues.
The 15 research areas funded by the JIP were targeted towards three key areas. These
are problem definition, potential solutions and developing a framework for evaluation
of management options. The key findings are as follows.
Problem definition.
An improved knowledge on volumes and composition of cuttings piles and the lack of
any correlation between these and well history was determined. There is little toxicity
information available other than for hydrocarbon content where a no-effect
concentration of 10 mg/kg has been suggested. Recolonisation begins 1-2 years after
discharge cessation by opportunistic species and the rate increases relative to distance
from the pile centre. A rapid rate of organic matter decomposition has been identified
and precipitation of metal sulphides within a pile (reducing bioavailability) and low
exchange rates with overlying seawater was observed. A wide range of contaminants
has the potential to be naturally biodegraded, but time scales are likely to be long and
vary between and within piles. Erosion is likely to be of greater significance than
sedimentation. Non-validated, but pragmatic disturbance mechanism data were input
into an existing mathematical model, and examples of contamination dispersion have
been produced based on identified mechanisms and natural events.
Potential solutions.
Degradation by both anaerobic and aerobic means is likely, but limited by availability
of electron acceptors e.g. oxygen, and strategies have been developed for acceleration
of degradation. Containment is reasonably practicable, but contained aquatic disposal
would cause significant environmental impact during construction and a cover would
slow degradation. Recovery systems are potentially capable of accessing the majority
of cuttings and achieve > 90 % recovery. Substantial dilution with seawater is likely,
however, in most techniques. The impacts from these systems have been assessed. It is
suggested their impacts are more dependent on pile characteristics than on the removal
techniques employed, and will probably be within the area effected by original drilling
operations. Most will use the same amount of power. On-shore processing capacity in
the UK and Norway is sufficient and typical energy consumption is reported. Landfill
capacity is available except for untreated oily waste, but limited to England, requiring
long distance transportation. Treatment and disposal costs are reported. Re-use
opportunities are limited and would require processing. Re-injection is currently the
only established technique for processing cuttings offshore, but if no suitable formation
is available, on-shore processing is currently the only technique to satisfy existing
regulations. Techniques reviewed are limited by weight/space demands and emerging
technologies could become viable in the future.
p:\a9\atc\0001-0050\003500\r2\003.doc
PAGE 1of 2
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
Evaluation framework.
A three-tier framework has been suggested encompassing
(i) preliminary site assessment; (ii) generic quantitative assessment of specific
chemical, physical and biological data, risk assessment, including modelling of cuttings
dispersion scenarios and assessment of the potential that any disturbance may affect the
local ecosystem; and (iii) an assessment of the management options to aid decision
making in the determination of BEP and BAT for the remediation of any specific pile.
While all research areas have been completed on time, the conclusions identified above
have in some cases been developed against a background of data limitations that have
qualified the results. Such limitations and other gaps in the research areas of Phase I
are identified in the report. As a result of the uncertainties remaining there is a
requirement for more work in addition to and associated with field trials in Phase II.
p:\a9\atc\0001-0050\003500\r2\003.doc
PAGE 2of 2
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
1.0
INTRODUCTION
DNV has been requested by the sponsors of the Drill Cuttings Joint Industry Project
(JIP), supported by UKOOA, to prepare an overall summary of the results of the
research activities undertaken in Phase I of the programme. While all research areas
have been completed on time, the conclusions have in some cases been developed
against a background of data limitations that have qualified the results. As a result of
the uncertainties remaining there is a requirement for more work. Recommendations
for such work to be carried out in Phase II will be formulated and prioritised at a second
stakeholder meeting to be held in February 2000. Phase II is intended to further
knowledge about cuttings piles and investigate a set of potential options, based on the
results and feedback from Phase I, by conducting further research and field trials.
The R&D, Phase I programme of the JIP, developed from the Drill Cuttings Initiative,
was established by UKOOA in collaboration with the E&P Forum (now the
International Association of Oil and Gas Producers) and supported by the Norwegian
Offshore Association, in June 1998. It was further refined during the stakeholder
workshop held in November 1998, when additional priorities were identified. Details
of this workshop can be obtained from the Environmental Council web-site www.theenvironment-council .org.uk.
The objective of the programme is to identify the Best Environmental Practice (BEP)
and Best Available Technology (BAT) (Reference1) 1 for dealing with drill cuttings
piles in the North Sea, in accordance with the principles set out by the OSPAR
Convention.
The first phase of the JIP programme mainly comprised desktop studies with the
objectives to:
establish the current state of knowledge
investigate various solutions for the management of cuttings piles encompassing
the complete range of options from leaving in place to their removal.
The process of achieving the deliverables of Phase I, the research areas identified and
the details of the R&D groups awarded the work, can be found on the UKOOA website, www.ukooa.co.uk. Details of the Scientific Review Group and their function to
add independent quality assurance to the science can also be found at this site.
The work conducted in Phase I have fallen into three main areas:
Problem Definition
Potential Solutions
Evaluation Framework
Problem Definition
In order to advance an acceptable methodology and allow for improved assessment, it
has been necessary to establish the current state of knowledge of the problem issues,
namely:
p:\a9\atc\0001-0050\003500\r2\003.doc
PAGE 1
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
1.2
2.1
In-Situ Environmental
Impact
In-Situ Environmental
Impact
2.2
p:\a9\atc\0001-0050\003500\r2\003.doc
Title
Determination of the physical characteristics of
cuttings piles, using existing survey data and
drilling information
Determination of the toxicity characteristics of
cuttings piles, using existing survey data and
drilling information
Faunal colonisation of cuttings piles based on
literature review and field studies
Contaminant leaching from drill cuttings piles
based on literature review and field studies.
PAGE 2
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
2.3
In-Situ Environmental
Impact
3.1
Environmental Effects
from Disturbance
3.2
Environmental Effects
from disturbance
Potential Solutions
4.1
Bioremediation
Solutions
5.1
Covering Solutions
6.1
Removal solutions
6.2
Removal Solutions
6.3
Removal Solutions
7.1
Onshore Disposal
Solutions
Offshore Disposal
Solutions
New Technology
7.2
8.1
Evaluation of Options
9.1
Cuttings Pile
Acceptance Criteria
p:\a9\atc\0001-0050\003500\r2\003.doc
PAGE 3
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
2.0
2.1
Achievements
Gaps
PAGE 4
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
Correlation analysis showed that all the examined parameters vary without any obvious
pattern of, or, through the piles. Therefore no conclusions can be drawn indicating a
relationship between accumulation composition and the other factors considered. The
only exception to this is an indication that cadmium concentrations are higher and polyaromatic hydrocarbon concentrations are lower towards the pile surface although the
reason for this is uncertain
The difficulty in determining distribution patterns could be due to reasons such as
disturbance by other operational factors, the low number of pile sampling studies
performed, the variable characteristics of sampling devices and locations, or the
inherent heterogeneity of the piles.
2.2
Gaps
PAGE 5
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
2.3
Gaps
p:\a9\atc\0001-0050\003500\r2\003.doc
PAGE 6
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
community may be close to the original situation or significantly different for a long
time depending on factors such as remaining contaminant level.
The exact mechanism of the long-term recolonisation process, rates and succession, is
poorly understood due partly to the lack of a standardised methodology and protocol for
biological sampling during benthic surveys across all North Sea sectors.
2.4
Gaps
p:\a9\atc\0001-0050\003500\r2\003.doc
PAGE 7
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
The data set obtained from the field trials yields evidence for high rates of
biogeochemical diagenetic reaction close to the apex of the pile, decreasing rapidly with
radial distance. Gradients in oxidant and reactants within the pore water of the pile
have sharp interfaces through the pile thickness. The process of redox digenesis
produces dissolved sulphide, which may lead to a mechanism of heavy metal
stabilisation.
Three notable pointers to the fate of contaminants were identified:
1. The rapid rate of organic matter decomposition which is of the order of 40 g
carbon/m2/y (used up in degradation)
2. Precipitation of metal mono and disulphides were directly observed within the pile.
This means they become non-bioavailable.
3. Fluxes suggest low exchange rates of metals with overlying seawater.
The investigation into food chain uptake yielded no further information.
2.5
Gaps
p:\a9\atc\0001-0050\003500\r2\003.doc
PAGE 8
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
2.6
PAGE 9
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
The report primarily focuses on disturbance mechanisms used for cuttings displacement
rather than the untested removal or containment techniques that have still to be trialed
as part of Phase II of the JIP.
While the numbers generated from this research area are not validated estimates they
nonetheless represent the best, pragmatic information available however considerable
care in their use is required. Phase II will provide an opportunity to calibrate these
estimates.
2.7
Gaps
p:\a9\atc\0001-0050\003500\r2\003.doc
PAGE 10
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
Environmental data on currents and waves have been derived from measurements made
in the North Sea and general references on North Sea wave data. From the assembled
data two virtual cuttings piles have been defined for different North Sea locations to
provide conditions of maximum and minimum dispersion.
A range of disturbance mechanisms was defined based on data generated from research
area 3.1. These modelling of these mechanisms gave results ranging from widespread
distribution to limited local impacts. Disturbances giving insignificant spread were
excluded from further modelling. Where there were a range of results for a specific
activity the worst case was used.
Trawling had a minor impact based on a single trawl pass but did not capture the effect
of redistribution by dragging material. For all mechanisms the oil content in the
cuttings often gave a higher seabed concentration of oil within an assumed bioturbation
depth (5cm). That resulted in elevated risk ratios of Predicted Environmental
Concentration to No Effect Concentration (PEC/ NEC) with potential biological impact.
A No Effect Concentration (NEC) value of 10mg/kg total hydrocarbons for the test
species Corophium volutator (mud shrimp) has been derived from the work in research
area 1.2. This value is very close to what is generally considered to be the upper limit of
background values and may be considered to be conservative.
Natural disturbance was modelled with and without storm wave influence. The model
showed little or no erosion of the pile under the action of current flows alone. Under
severe storm conditions the pile was found to erode at a rate of approximately
180m3/day (a 70,000m3 pile would take 390 days of such storm activity to remove
entirely) and may indicate that piles will erode gradually with time. This is susceptible
to the uncertainties in present knowledge on erosion thresholds.
Phase II will provide an opportunity to calibrate these results.
2.8
Achievements
Gaps
PAGE 11
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
2.9
Achievements
Gaps
p:\a9\atc\0001-0050\003500\r2\003.doc
PAGE 12
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
It is considered that a mattress cap would be costly, time consuming, less safe to
construct, and more prone to damage by other sea activities than placement of armour
stone. CAD is significantly more expensive than in-situ capping. It is more likely to be
economic to install either armour stone or CAD for a large pile.
The use of CAD moves the cuttings material into a containment pit when significant
release of contaminants may occur. It therefore has a greater environmental impact
than capping the pile.
It is likely that the armour stone design would resist erosion by storm events, however
the stone would be hazardous to trawling so an additional covering layer may be
necessary.
Achievements
Gaps
PAGE 13
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
With the majority of techniques all the cuttings lying outside the footprint of the main
structure and most of those in an outer substructure area can be recovered at present.
Only one technique appears able to address those within a template.
All techniques are likely to be able to excavate the majority of cuttings. It is possible
that if cuttings with high shear strength (of the order of 100kPa) are encountered some
techniques based on simple suction methods will yield very low rates of recovery.
Techniques which incorporate jetting systems and mechanical devices to break up
strong materials are preferred to maximise recovery but will increase disturbance.
All techniques except grabs are expected to substantially dilute the cuttings with
seawater during recovery. Cuttings in-situ contain approximately 50% solids by
volume, it is estimated that average solid concentrations in the flow to the surface will
be in the order of 5-10% increasing the bulk to be handled by a factor of 5-10. Higher
solids concentrations may be possible with some techniques but would require high
levels of operational accuracy and control. The ability to closely control pumping rates
is fundamental to achieving low dilution. At present only one technique claims to
provide this facility. Maintaining close contact between the excavation tool and the
cuttings will also influence dilution. Some techniques have poor contact and this will
be an issue when considering debris and confined work areas.
With the possible exception of grabs all techniques are vulnerable to delays due to
damage and blockage but there is little basis for differentiating between them.
As these techniques have not yet been tried, quantitative estimates of material release
during recovery operations are based on an intuitive ranking assessment. The
conclusions of this assessment are:
The greatest release of material is likely with grab based techniques
Relatively high releases will result with reverse circulation drilling and trailing
hopper dredger techniques
All other techniques are likely to give rise to lower releases but there is little to
distinguish between them at this stage
The actual rate of release will be highly dependant on the degree of operational care
which can be taken and that may be more important than the design of the technique in
determining losses during recovery.
All techniques are considered capable of recovering the majority of cuttings (>90%)
where the installation structure is still in place, based on information presented.
p:\a9\atc\0001-0050\003500\r2\003.doc
PAGE 14
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
Gaps
This report identifies and assesses the environmental impact of systems that could be
used to recover and lift drill cuttings to the surface (Research Area 6.1/6.2).
The assessment has shown that cuttings disturbance and redistribution will be the most
likely cause of environmental impacts during the removal process. All techniques will,
by their action, result in varying degrees of pile material disturbance. Modelling results
suggest that the area of seabed affected by the re-deposited material will be dependent
more on the characteristics of the material (e.g. cohesivity) than on variations in the
methodology of excavation.
The extent of any impacts generated by pile disturbance during recovery operations will
probably be within the area of effect from the original drilling operations. Distances for
major, moderate and minor ecotoxicological impacts are suggested.
During operations, the majority of re-suspension will occur during the excavation and
debris removal process. The excavation equipment and the operating procedures
chosen will be a main factor in determining the amount of material release into the
water column these include:
Working from the side of the pile with crawler based equipment is likely to produce
a greater impact than operating suspended or ROV based equipment from the top of
the pile
Operating from vessels, particularly in rough weather, will potentially disturb more
material than installation based operations
Sediment losses arising from mechanical breakdown of pumped lifting systems is a
major contribution to the environmental impact.
The use of mechanical agitators and jetting techniques will re-suspend more material
than simple suction alone.
A proportion of the cuttings pile will be re-suspended in the water column during
recovery. The concentration of oil and the relatively short exposure time of plants and
animals to the plume suggest that toxic concentrations will only be reached
episodically. The impact on the water column is considered to be minor.
Energy use calculations indicate that most techniques will use approximately the same
amount of power except where they are vessel based.
p:\a9\atc\0001-0050\003500\r2\003.doc
PAGE 15
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
Due consideration to nearby spawning/nursery areas and seabed fishing activity should
be part of the decision taking process (see 9.1) when planning the timing of the
operation.
Achievements
Gaps
This report examined the practicalities and impacts of dealing with recovered drill
cuttings onshore and the potential for re-using the raw materials.
The total capacity of the identified processing options in the UK is estimated at about
300,000 tonnes year and 120,000 tonnes in Norway. The present UK and Norwegian
treatment capacities are generally considered sufficient to handle all existing cuttings
piles if they were brought onshore under a planned timetable. However, if all cuttings
from one of the largest fields in the UK were taken onshore in one year, and processed,
the capacity is insufficient.
Average processing costs are estimated at 192 per tonne but are almost double this in
Norway.
Present processing technologies are susceptible to changes in input quality and none are
established for treatment of old cuttings. The heterogeneity, including water content,
of any cuttings returned to shore implies uncertainty in the functionality of these
technologies. In addition, the effect of any offshore pre-treatment could have a
significant impact on material handling and processing onshore. It is implicit that the
radioactivity level of the material is compliant for onshore handling.
In the UK a number of landfill sites licensed to accept oily waste were identified with a
total capacity estimated at 360,000 tonnes per year of sludge and 1.5 million tonnes per
year of solids. Untreated cuttings could be classified as sludge; thus capacity is limited
for direct disposal. Processing to lower water content would be preferable to enable the
waste to be classified as solid. Capacity for solids is considered sufficient however
p:\a9\atc\0001-0050\003500\r2\003.doc
PAGE 16
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
Achievements
Gaps
This project focused on the practicality of dealing with recovered cuttings offshore.
The only currently established technique for dealing with cuttings offshore is
reinjection into a suitable formation. There are, however, a number of emerging
technologies, in addition to established onshore techniques, for cleaning cuttings that
have potential for offshore application. Onshore techniques (for use offshore)
considered were; grinding; direct thermal desorption; and indirect thermal desorption.
p:\a9\atc\0001-0050\003500\r2\003.doc
PAGE 17
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
Achievements
Gaps
The conceptual approach proposed for the provision of a methodology for the
evaluation of handling options takes the form of a tiered risk-based assessment
framework. This type of risk-based assessment is already used for regulatory decision
making on contaminated land issues in the UK, Europe and North America. The
application of this type of tiered framework to cuttings pile assessment and
management is intended to focus on the appropriate level of assessment for each site on
a case by case basis. The framework is designed to focus resources on those sites
which present most environmental risk whilst allowing sites identified as presenting
little or no risk to exit the assessment process at each stage.
p:\a9\atc\0001-0050\003500\r2\003.doc
PAGE 18
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
p:\a9\atc\0001-0050\003500\r2\003.doc
PAGE 19
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
3.0
3.1
Summary of Findings
The research areas in Phase I have all been completed successfully and useful
conclusions drawn, although in some cases against a background of data limitations,
with varying degrees of success which have qualified the results.
The research areas, as mentioned in the background section, fall into three categories:
Problem Definition
Potential Solutions
Evaluation Framework
These are discussed in turn.
Problem Definition
The problem has been better defined but results have been limited largely as a result of
inconsistent sampling techniques and lack of data. The following are the main findings.
The volume of cuttings is now estimated as almost double that previously, based on
information from twice the number of sites. The heterogeneous nature of the piles
mean that they differ significantly both from site to site and within an individual pile. It
will therefore be necessary to assess each pile individually in order to conduct a
sufficient assessment to allow for appropriate evaluation of management options.
The toxic effects of the piles are generally unknown but the effects of total
hydrocarbons show acute and chronic effects in the region of 100 mg/kg and 10 mg/kg
respectively.
There is confirmation of recolonisation beginning 1-2 years after cuttings discharge
cessation by opportunistic species that dominate for the first few years. Thereafter
recovery is dependent on remaining contaminant level.
Contaminant release is now better understood, particularly with respect to heavy metals
which have low exchange rates with the overlying seawater and hydrocarbons which
decompose rapidly except for those below the surface zone which remain unchanged.
No further information on contaminant uptake into the food chain has been determined.
The surface of the piles is continually changing as a result of erosion, bioturbation,
sedimentation, recolonisation and microbial activity but the main bulk remains
relatively inert unless physically disturbed. This is largely due to lack of oxygen. The
rate of the surface activities depends on location and time of the year but generally
activities which erode the pile are faster than sedimentation.
The modelling tool, with its present limitations, can demonstrate cuttings material
redistribution, resulting oil concentration and potential ecotoxicological (simplistic)
effect when disturbed either naturally or as a result of operations. Its main benefit is
p:\a9\atc\0001-0050\003500\r2\003.doc
PAGE 20
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
3.2
Outstanding Issues
It is clear from these findings that there are still a number of gaps. Furthermore, there
are a number of additional questions arising from Phase I that should be addressed
during Phase II.
p:\a9\atc\0001-0050\003500\r2\003.doc
PAGE 21
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
Sampling Methods
A consistent method of taking samples of cuttings pile material and benthic surveys
would provide better data as the basis for future work. The protocol(s) being developed
by the Norwegian Offshore Association (OLF) are designed to address this issue. They
are expected to be issued in 2000.
Toxic Effects of Cuttings Material
There is a lack of information on the leaching of toxic contaminants and the toxic
effects of the cuttings material as a whole and its components other than total
hydrocarbons. This covers the immediate effects, accumulations and effects up the
food chain.
Ecotoxicological studies have been sponsored by Phase I of the JIP to gain some further
knowledge on these issues.
Natural Degradation
There is still a lack of understanding of natural degradation processes and rates.
Additionally the source of the organic matter giving the rapid rate of decomposition
suggested in research area 2.2 is unclear.
Dispersion Modelling Uncertainties
Phase II trials can be used to validate both model input data and the dispersion
modelling.
Potential Solutions
None of the potential solutions have yet been proven by field trials. This uncertainty
will have reduced the quality and reliability of the current environmental impact
assessments.
Disposal of Seawater
The techniques for lifting the piles all dilute the cuttings with seawater. The treatment
and disposal implications of handling this volume of water have not yet been
adequately addressed.
Evaluation Framework
There is a lack of detail in the proposed methodology with particular respect to Tier 3.
3.3
Further Comments
The results of the dispersion modelling are based on the output from research area 3.2,
which is based on the output from 1.1, 1.2 and 3.1. Even though there are significant
uncertainties in those areas the dispersion modelling tool which has been developed will
be useful in highlighting the likely differences in environmental impact between
p:\a9\atc\0001-0050\003500\r2\003.doc
PAGE 22
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
p:\a9\atc\0001-0050\003500\r2\003.doc
PAGE 23
20 January 2000
Drill Cuttings JIP
Phase I Summary Report (Rev 2)
4.0
REFERENCES
1.
2.
3.
UKOOA Drill Cuttings Initiative Research and Development Programme Project 1.2:
Cuttings Pile Toxicity, Environment & Resource Technology Ltd and Rogaland
Research, Final, 15 Dec 99
4.
UKOOA Drill Cutting Initiative, Research and Development Programme, Activity 2.1,
Faunal Colonisation of Drill Cuttings Pile Based on Literature Review, Dames & Moore
and NIOZ, Final, 24 Dec 99
5.
Contaminant Leaching from Drill Cuttings Piles of the Northern and Central North Sea:
A Review and Field results from the Beryl A cuttings pile, Scottish Association for
Marine Science and Centre for Coastal & Marine Sciences, Final Jan 00
6.
UKOOA Drill Cuttings Initiative Research and Development Programme, Project 2.3:
Natural degradation and estimated recovery time-scales, Environment & Resource
Technology Ltd and Rogaland Research, Final, 16 Dec 99
7.
8.
UKOOA Drill Cuttings Initiative Research and Development Programme Study 3.2:
Mathematical Model of Pile Dispersal Following Disturbance, BMT Marine Information
Systems, Final 18 Jan 00
9.
10.
11.
UKOOA Drill Cuttings Initiative, Research Areas 6.1 and 6.2, Removal Solutions
Identification and Effectiveness of Methods to Remove Drill Cuttings Piles from Seabed,
Dredging Research Ltd and CEFAS, Final Jan 00
12.
13.
UKOOA Drill Cuttings R&D Program, Impact from Onshore Disposal Study Item 7.1,
Det Norske Veritas, Rev 1(Final), 17 Jan 00
14.
Task 7.2: Techniques for Offshore Treatment and Disposal of Retrieved Drill Cuttings
Piles, Environmental Resources Management, Final 17 Jan 00
15.
UKOOA Drill Cutting Initiative, Research and Development Programme, Activity 9.1,
Determination of Acceptance Criteria for Cuttings Pile Management, Final 14 Jan 00
PAGE 24