Sr.
No.
1
1
2
GTB
Hospital
Shahdara, Delhi
CLIENT
Target ACHIEVEME
CUMULATIVE
for the NTS DURING ACHIEVEMENT
year
THE
DURING THE
QUARTER
YEAR in %
In %
REMARKS
a) Library block
b) Auditorium
EE-I
Office Bldg for National Centre for CE(NDZ)
Agricultural Economic & Policy
III
Research (NCAP) at Pusa, New
Delhi Structural Design
EE-II
190
337
-90
50
50
100
800
10
100
100
Architectural,
issued.
400
25
95
15
Project
3
at CE PWD
(Zone III)
(NCTD)
COST
(Rs. IN
LAKHS)
ANNEXURE-10
8
All Structural Design of Library issued. Structural
sizes of Auditorium sent to SA (DGHS)
Final
architectural drawings awaited.
EE-II
5
CE Zone
II (NCTD)
263
15
-do-
480
55
10
NVS
285
Page 1 of 7
Work completed
Fee awaited
Sr.
No.
1
8
9
CLIENT
2
3
Samaj Sadan at Lodi Road, New CE
Delhi
EE-I
MEA works at Kabul, Afghanistan. (NDZ)III
MEA
i)
11
12
6
50
7
80
8
Structural drawings upto Roof level issued.
100
100
100
100
90
90
-----
70
10
50
3484
CE
1652
(NDZ)III
CE(ODZ)
559
100
-
MEA
MOST
13
14
CE(ODZ)
1317
CE(ODZ)
464
CE(NCTD
) Zone II
327
15
16
REMARKS
5
100
Target ACHIEVEME
CUMULATIVE
for the NTS DURING ACHIEVEMENT
year
THE
DURING THE
QUARTER
YEAR in %
In %
4
190
10
COST
(Rs. IN
LAKHS)
ANNEXURE-10
Page 2 of 7
DE submitted,
Project withdrawn
Sr.
No.
16
1
17
2
Str. Design & detailed estimate
EE-III
Police Station Bldg. at
Jaffarabad , Delhi Str. Design &
detailed estimate
EE-III
CLIENT
COST
(Rs. IN
LAKHS)
CE(NCTD
) Zone II
3
327
CE(NCTD
) Zone II
514
ANNEXURE-10
Target ACHIEVEME
CUMULATIVE
for the NTS DURING ACHIEVEMENT
year
THE
DURING THE
QUARTER
YEAR in %
In %
5
REMARKS
DE submitted,
Project withdrawn
8
18
CE(NEZ )
Shillong
3000
50
10
50
19
20
2500
-
100
-
99
-
1200
_
45
_
15
_
95
700
21
22
23
-do-
300
Page 3 of 7
Sr.
No.
1
24
25
26
27
28
29
30
31
CLIENT
2
3
Afro Asian Legal Consultative
-doCommittee Bldg. at Chanakyapuri,
New Delhi. Str Design
EE (Geot)
Earthquake risk evaluation centre Metrologic
at Aya Nagar, Delhi. EE(Geo)
al
Departme
nt
Handicraft Bhawan at Baba
Kharak Singh Marg, New Delhi.
Arch
Constn. of Type V qurts for Delhi
Jal Board at Lajpat Nagar New
Delhi.-1100024
C/O ITI for Women at Vivek Vihar
N.Delhi.
EE-III
C/O Fire Station & Staff Qrts. At
Dallupura N.D.
EE-III
C/O additional block in between
Admn. & ExitBlock
Undertaking the complete
technical checkup of the work
executed for NIAW Ballabhgarh,
Faridabad
COST
(Rs. IN
LAKHS)
Target ACHIEVEME
CUMULATIVE
for the NTS DURING ACHIEVEMENT
year
THE
DURING THE
QUARTER
YEAR in %
In %
2500
ANNEXURE-10
REMARKS
6
-
7
5
Drawings issued.
Fee awaited.
Textile
Ministry
1100
Delhi Jal
Board
135
--
70
100
CE, PWD
Zone-II
212
70
20
50
CE, PWD
Zone-II
234
75
15
40
M/O
Statistics
&
Program
me Impt
Page 4 of 7
Sr.
No.
1
32
CLIENT
2
3
Redevelopment of Devnager Delhi NDZ-III
C/O Type-I/ 90 Nos., T-II/ 360
Nos.(4 storeyed)
C/O APT Hostel (G+9)/196 units
C/O T-III(G+10) 640 Nos. with
basement
C/O T-III(G+10) 400 Nos. with
basement,
T-IV(G+10)/18 Nos. with basement
33
34
35
CE, NDZIII
EE,PWD27 New
Delhi.
CE, PWD
Zone III
Delhi
COST
(Rs. IN
LAKHS)
4
1829
Target ACHIEVEME
CUMULATIVE
for the NTS DURING ACHIEVEMENT
year
THE
DURING THE
QUARTER
YEAR in %
In %
5
100
6
0.5
7
0.5
1036
852
10941
ANNEXURE-10
REMARKS
8
A/A & E/S received for 1829 lakh on 26.11.2002
Structural sizes are being worked outPreliminary
sizes for hostel block issued Planning work is to be
done by CE (NDZ) III, CPWD, New Delhi.
Page 5 of 7
-do-
Sr.
No.
CLIENT
1
36
2
3
C/o CWC Library and Information SE DCCBureau at RK Puram, New Delhi. XII
CPWD,
New
Delhi.
37
SE AIIMS
Ansari
Nagar
N.Delhi
38
KVS Delhi
39
40
COST
(Rs. IN
LAKHS)
4
576
Target ACHIEVEME
CUMULATIVE
for the NTS DURING ACHIEVEMENT
year
THE
DURING THE
QUARTER
YEAR in %
In %
ANNEXURE-10
REMARKS
5
93
6
5
7
100
8
All structural drawings issued
98
15
45
85
30
EE,PWD27
MOUD &
MOUEPA
__
__
__
__
Page 6 of 7
Sr.
No.
CLIENT
COST
(Rs. IN
LAKHS)
1
41
2
Repairs & Rehabilitation of
Habibia School at Kabul.
3
MEA
42
MEA
43
44
45
46
47
48
Target ACHIEVEME
CUMULATIVE
for the NTS DURING ACHIEVEMENT
year
THE
DURING THE
QUARTER
YEAR in %
In %
6
10
7
90
ANNEXURE-10
REMARKS
Min. of
Rural
Developm
ent
8
Work at site is in progress NITs for all the works,
structural drawings, for roof slab and Cycle shed
already issued.
Input from Govt. of Afghanistan to Committee in India
awaited.
For Development of rural roads in Bihar
MOSRTH
--
SE,
DCCX,
CPWD
SE, DCCX, CPWD
13
95
100
100
CE(ODZ),
CPWD
DoPT
1317
100
300
100
100
100
Estimate vetted