Professional Documents
Culture Documents
Leighton LR
Leighton LR
HON G KON G
Ventilation
The MTRs conforming design proposal
included two separate ventilation tunnels
alongside the main running tunnel with
adit connections to the main tunnel at the
required intervals. As part of Leightons
alternative proposal, the separate ventilation tunnels were eliminated by incorporating the ventilation requirements into an
enlarged running tunnel with an integral
overhead ventilation plenum (OHVD)
(Diagram xxx).
Two permanent ventilation adits are located at a separation of 6.5km. The southern
adit is a vertical shaft some 90m deep and
therefore not suitable for the main tunnel
construction access. A temporary construction adit (to be back-filled on completion of
the project) was therefore specified close to
the southern contract limit to provide two
excavation faces in order to meet the challenging construction programme.
Temporary ventilation to the face is provided by twin 500kW fans located at the
surface with fresh air delivered at a rate of
up to 200m3/s through twin 2.6m diameter ventilation ducts. Mitigating the noise
impacts of these fans has been another
challenge.
Geology
The project was tendered on a Geotechnical Baseline Report (GBR) prepared by
MTR that confirmed existing knowledge
and MTRs experience on the West Rail
DB350 tunnelling contract. With the exception of some soft ground at the northern,
Pat Heung portal the excavation is predominantly in competent rock including
Granodiorite and tuff, with some granite
material. Some difficult ground conditions
have been encountered in completely decomposed granite (CDG) that has required
mechanical excavation at the face. In such
zones, Leighton has resorted to sequential excavation and support. Heading and
bench or two pilot drives either side of a
centre column were adopted in particularly
challenging ground conditions.
Regular probe drilling is being undertaken
as specified to provide a better understanding of the geology immediately ahead of
the face and to date no significant water
problems have been encountered.
Lining
In good competent rock, the majority of
the lining is predicted to be unreinforced,
although reinforcement is used in the centre
dividing wall on which work will start in
2013. Shotcrete (50mm thick) is used for
temporary support of the excavated profile
and is either plain, or steel fibre-reinforced.
Polypropylene fibres are added in all linings
at a rate of 1kg/m3 of concrete to increase
resistance against spalling in the event of
a fire. The concrete is then cast to 350mm
thickness between a PVC sheet waterproofing membrane and formwork; the thickness
varies at junctions, the lining can be up
to a 1m-thick unreinforced lining in good
competent rock.
Current status
At the time of the authors visit to the site
in mid-September 2012, Leighton was
drilling and blasting two faces simultaneously, having excavated around 1,500m
from the south and 600m from the north. A
third work site for the 90m deep shaft was
also nearing completion of the first phase,
a 30m deep basement located above the
shaft.
Tunnel works also included the installation
of a waterproofing membrane and permanent tunnel lining. Tunnelling continues
24/7 with day and night shifts, employing
around 250 people/shift.
FACTS
Sandvik DX700
Hole diameter 76-115mm
(3-4 1/2)
Rock tools
45 or 51mm
(1 3/4 or 2)
Rock drill
HL710,
19,5kW
Engine
TIER 3:
Caterpillar C
7, 168 kW/2
200 rpm
TIER 4:
Caterpillar C
7.1, 168 kW/1
800 rpm
Flushing air
8,1m3/min,
up to 10bar
23m3/min
Dust collector at 1000 mm
vacuum H2O
Width
TIER 3: 2.5m
TIER 4: 2.45m
Length
7.2m / 10.7m
Height
3.6m / 3.2m
Weight
TIER 3: 14
800kg
TIER 4: 14
900kg
Blasting
In order to meet the demand for explosives
the project also included the construction
of two explosives magazines to be supplied
from the government magazines. Whilst
Leighton retains overall management and
operational control of the two magazines
the facilities are shared by the other XRL
drill and blast contractors; XRL Contract
821 share So Kwun Wat magazine and
XRL Contract 824 the magazine at
Tai Shu Ha (Yuen Long).
FACTS
Sandvik DT1331i
Coverage
20 - 232m2
3 344 6 085 mm
Booms
3 x SB100i
Feed
3 x TF5i
12-21 ft
Rock drill
3 x RD525
Control and
operation
system
iDATA
Length (with
default feed)
17 780mm
Width
Drilling/
Tramming/
Transportation
3 860 / 3 050
/ 3 050mm
Height Drilling
/ Tramming
5 965 /
4 965mm
Weight
000 /
Standard / with 50
54 000kg
utility boom
Sandvik DT1231i
Coverage
20 - 211m2
3 344 6 085mm
Booms
2 x SB150i
Feed
3 x TF5i
12-21ft
Rock drill
3 x RD525
Control and
operation
system
iDATA
Length (with
default feed)
17 780mm
Width Drilling/
Tramming/
Transportation
3 860 / 3 050
/ 3 050mm
Height Drilling
/ Tramming
4 780 /
3 780mm
Weight
500 /
Standard / with 45
49 500kg
utility boom
Safety
Safety is of paramount importance on all
Leighton and MTR projects. The adoption
of leading technology to achieve the project
objectives requires skilled operatives at
Sandvik DT821-SC
Coverage
110m2
Up to
6 180mm
Booms
TB90
Feed
TF500
16ft
Rock drill
RD520
Control
system
THC561
Length (with
default feed)
14 930mm
Width Drilling/
Tramming/
Transportation
3 000 / 3 000
/ 2 500mm
Weight
000 /
Standard / with 27
29 400kg
utility boom
and/or harmful gases. The ambient conditions of high temperature, high humidity
and lack of natural light are further hazards,
in addition to the pre-existing conditions
that define it as a confined space. A detailed
risk assessment report has therefore been
prepared that identifies all the hazards and
proposes a raft of measures both procedural
and engineering measures to reduce the risks
to as low as reasonably practicable.
Prior to breakthrough of the tunnel the exit
route from the tunnel could be in excess
of 4km. Therefore the ability to clearly
identify the location of an emergency, the
ability to manage it, and ensure safe evacuation are issues that have been addressed in
liaison with the Hong Kong Fire Services
Department (FSD) who will lead any emergency rescue should it prove necessary.
Communications, ventilation and emergency lighting are key provisions. Fire prevention equipment and emergency communications are provided in the tunnel. Audio
and visual alarms are connected to the tally
room/Emergency Control Centre at the surface. These regular stations, situated every
60m also include a fire hydrant with 30m
of hose connected to a fire main running the
length of the tunnel, and fire extinguishers
at each location. First aid kits are maintained every 100m within the tunnel.
In order to facilitate evacuation and rescue
procedures chainage markers are located
every 50m along the tunnel wall to enable
accurate location of any incident. Segregated walkways are provided for regular and
emergency access/egress and are advised to
workers in the tally room before they enter
the tunnel on each shift. Emergency lighting
is provided in accordance with the specification.