Professional Documents
Culture Documents
Good Weather Days
Good Weather Days
Good Weather Days
CORRECT METHOD
Once the good weather days are selected (for example, all days that were equal to or less than BF4
and/or DSS3 and with no adverse currents) then the performance speed of the vessel can be
calculated.
Ship performance speed = Average Speed - Current Factor
Good Weather Days
POSITIONS
DATE
GMT
LAT
LON
4.8
3:00
6.17S
81.23W
4.8
6:00
5.97S
81.28W
4.8
12:00
4.78S
81.55W
WIND
DISTANCE
(NM)
DIR
Daily
SIG.
Av.
WAVE
Current
SPEED
BF (M)
(KTS)
(KTS)
SSE
15.0
1.2
SSE
17.0
1.2
285.5
-0.41
4.8
18:00
3.60S
81.50W
13.0
1.0
4.9
0:00
2.44S
81.37W
10.0
1.2
4.9
3:00
1.48S
81.27W
4.9
6:00
1.30S
81.24W
SW
11.0
1.1
4.9
12:00
0.20S
81.05W
SW
13.0
1.0
275.0
-0.10
4.9
18:00
0.91N
80.86W
SSE
15.0
0.9
4.10
0:00
2.05N
80.67W
SSE
15.0
1.1
4.10
3:00
3.03N
80.50W
4.10
6:00
3.22N
80.47W
SW
13.0
1.1
283.3
0.10
4.10
12:00
4.38N
80.26W
WSW
13.0
1.0
4.10
18:00
5.49N
80.06W
SW
9.0
1.0
4.11
0:00
6.88N
79.85W
SW
7.0
0.8
4.11
3:00
7.67N
79.67W
INCORRECT METHOD
Days having adverse current are NOT excluded from good weather period below which goes against
the Charter Party definition and therefore is incorrect.
Ship performance speed = Average Speed - Current Factor
Good Weather Days selected incorrectly
POSITIONS
DATE
GMT
LAT
LON
4.8
3:00
6.17S
81.23W
4.8
6:00
5.97S
81.28W
4.8
12:00
4.78S
81.55W
WIND
DISTANCE
(NM)
DIR
Daily
SIG.WAVE
Av.
(M)
Current
SPEED
BF
(KTS)
(KTS)
SSE
15.0
1.2
SSE
17.0
1.2
285.5
-0.41
4.8
18:00
3.60S
81.50W
13.0
1.0
4.9
0:00
2.44S
81.37W
10.0
1.2
4.9
3:00
1.48S
81.27W
4.9
6:00
1.30S
81.24W
SW
11.0
1.1
4.9
12:00
0.20S
81.05W
SW
13.0
1.0
275.0
-0.10
4.9
18:00
0.91N
80.86W
SSE
15.0
0.9
4.10
0:00
2.05N
80.67W
SSE
15.0
1.1
4.10
3:00
3.03N
80.50W
4.10
6:00
3.22N
80.47W
4.10
12:00
4.38N
80.26W
SW
13.0
1.1
WSW
13.0
1.0
283.3
0.10
4.10
18:00
5.49N
80.06W
SW
9.0
1.0
4.11
0:00
6.88N
79.85W
SW
7.0
0.8
4.11
3:00
7.67N
79.67W
What weather and / or sea conditions were covered by the description good weather conditions?
There was a dispute as to whether good weather conditions meant winds of force 4 or below or force
3 or below on the Beaufort scale. Held , that the correct answer was winds of force 4 or below on the
Beaufort scale. There was no absolute yardstick by reference to which one could measure what
parties objectively intended by referring to good weather conditions. However, the figure of Beaufort
force 4 or below was so widely applied that unless parties expressly agreed another figure, their
objective contractual intention could be considered to be to adopt the generally applied figure of force
4 or below.
TIME LOST
Example 1:
LMLN 723 (2007)
Comparing the time required to perform the voyage of 10,900.50 miles at the warranted speed of 13
knots (838.50 hours) with the time taken at the average good weather speed of 12.28 knots (887.66
hours) the vessel lost a total of 49.16 hours between Tubarao and Majishan, equivalent to
US$130,819.28, net of address commission but including brokers' commission payable, according to
clause 27, by the owners to the brokers involved.
To summarize:
Total distance: 10,900.50 nm
Good weather distance: 1162.80 nm
Good weather time: 95.0 hours
Good weather performance speed: 12.28 knots
(Note: It looks like this is a miscalculation, because 1162.80 / 95 = 12.24 knots)
It should be noted that good weather current factor was discussed, but it was rejected because of
no proof of the same was submitted ? Weathernews can always provide evidence.
Therefore time lost should be calculated;
Example 2:
LMLN 670 (2005)
In the event, the good weather performance of the vessel (between 0130 on 19 and 0200 on 20
November) could be assessed in round terms as 12.21 knots (305.3 miles 24.50 hrs less 0.25 knots
current factor) against her warranted performance speed of 13.00 knots (13.50 less 0.5 knots for
about). There was therefore an under-performance. The tribunal had accepted the overall mileage
steamed as 5,224.60 nautical miles. Thus, had the vessel steamed throughout at 13.00 knots she
would have taken approximately 401.89 hrs (5,224.60 nms 13.00 kts). At her actual good weather
speed of 12.21 knots she would have taken approximately 427.89 hrs (5,224.60 nms 12.21 knots) a loss of approximately 26 hours.
To summarize:
Total distance: 5,224.60 nm
Good weather distance: 305.3. nm
Good weather time: 24.5 hours
Good weather performance speed: 12.21 knots
Good weather current factor: 0.25 knots
Bunker Calculations
Bunker calculations consist of an over-consumption evaluation and a fuel saving evaluation, where
the former applies an allowance of usually 5% upwards, but the latter does not give any allowance
(unless otherwise specified in the Charter Party). Complying with maritime Arbitration standards, Speed
and Bunker Analysis is not applied when there are no good weather days.
It should be noted that there are some other calculation methods, employing a weather factor for
the entire voyage, but they are not accepted in maritime Arbitration. (Please see 8 Weather Factor and
Entire Voyage Performance Speed.)
Nowadays almost all Charter Parties apply an about on speed and consumption with the word
about before speed and consumption values, and/or a phrase All details about in the vessel's
particulars section.
It seems that owners and charterers generally agree on an application of 0.5 knots for speed
about, but there are still some arguments regarding the consumption about. Weathernews' Speed
and Bunker Analysis applies an allowance of 0.5 knots on speed, 5% on fuel over-consumption and no
allowance on fuel saving when the Charter Party includes an about for both speed and consumption.
As English Law is about damages, there is no damage to the charterer if they are having to give
owners credit for bunkers under-consumed. This interpretation is reasonable for both owners and
charterers. London maritime Arbitration precedent LMLN723 (2007) expressed the same idea as
below. In this case, the consumption warranty stipulated in the Charter Party was 46 MT/day:
With regard to the extent of the allowance to be given for the term about, although on some
occasions in the past, Arbitration tribunals had referred to allowances of less than 5% on bunker
consumption, the current practice was almost invariably to apply an allowance of 5% unless there
were special circumstances. There was no reason to depart from that practice in the present case.
Accordingly, in considering whether the vessel had over performed, reference was to be made to a
daily consumption of 48.3 mts, whilst in determining if bunkers had been saved, reference was to be
made to a daily consumption of 46 mts.
Over-consumption:
LMLN 723 (2007)
The charterers calculated that on the days of contractually good weather conditions the vessel
consumed an average of 44.90 mts of IFO and 0.87 mts of MDO each day. Performing the entire
voyage of 10,900.50 miles on that daily consumption at the average good weather speed of 12.28
knots the vessels voyage consumption would have been 1,660.67 mts of IFO and 32.17 mts of MDO.
Those figures were to be compared with consumption for the voyage at the minimum warranted speed
of 13 knots on a daily consumption of 48.3 mts IFO and 1.05 mts of MDO, namely 1,687.48 mts of
IFO and 36.68 mts of MDO. There was therefore no over consumption of bunkers. Was there a
saving? Whether a speed of 13 knots or 13.5 knots was adopted, the vessels good weather
consumption figure of 1,660.67 mts IFO and 32.37 mts MDO exceeded consumption for the voyage at
a daily rate of 46 mts and 1 mt respectively. The vessels bunker consumption therefore neither
exceeded the maximum permitted nor fell below the level at which savings were made. In short, the
vessels consumption fell within the permitted range for the voyage and gave rise to no claim or credit.
To summarize:
Total distance: 10,900.50 nm
Good weather distance: 1162.80 nm
Good weather time: 95.0 hours
(Note: It looks like this is a mis-calculation, because 1162.80 / 95 = 12.24 knots)
It should be noted that good weather current factor was discussed, but it was rejected because of
no proof submitted.
FAQs
Weathernews analyzes and selects the periods that can be considered good weather days
according to the good weather definition in the Charter Party and then calculates the vessel
performance based on how the vessel performed on average within these good weather days.
As per London Maritime Arbitration precedent LMLN 357 (1993):
The first step in the exercise was to find the average speed for each passage in accordance with subclause 4 during periods when the weather was force 4 or less. That established the speed (and
consumption) of which the vessel was capable during the passage in question and therefore
determined whether or not the owners were in breach.
Once the speed of which the vessel was capable in fair weather had been established for each
passage, the warranty took effect. If the speed was less than the warranted speed or if the
consumption of bunkers was greater than the warranted consumption for that speed, the charterers
were entitled to recover compensation over the whole of the passage in question, not just that part of
the passage which was performed in good weather.
Thus any underperformance for a vessel during the good weather period would be extrapolated to
the entire voyage to arrive at the true loss for the charterers.
Q2. Shouldn't time lost be calculated only for The Good Weather
Period?
Weathernews' stance is to provide objective ship performance auditing reports based on London
maritime arbitration standards, using a good weather analysis method, as explained in English Law
precedents such as the MV Didymi case [1988] 2 Lloyd's Rep 108) and the MV Gas Enterprise case
(LMLN 357, 1993). London Maritime Arbitration Award LMLN 549 (2000) explains the method as
follows:
The appropriate approach was as follows (see The Didymi [1988] 2 Lloyd's Rep 108):
- (i) The vessels performance should be assessed in good weather conditions (generally Beaufort
wind force 4 or below or as defined in the charterparty) on all sea passages from sea buoy to sea buoy
excluding any slow steaming at charterers' request.
- (ii) If a variation of speed from the warranted charterparty speed was shown, the variance should be
applied with all necessary adjustments and extrapolated to all sea passages and in all weather
conditions (excluding slow steaming at charterers' request).
- (iii) If a variation of fuel consumption from that warranted in the charterparty was shown the variation
should be applied with the necessary adjustments and extrapolated to all sea passages and in all
weather conditions (including slow steaming at charterers' request).
Gas Enterprise case (LMLN 357, 1993):
Prima facie the charterers were entitled to be compensated for any breach of that warranty. A vessel
which could not comply with her contract speed or consumption in good weather was unlikely to be
able to comply with the contract when the weather was bad. One would therefore expect sub-clauses
4 and 5 to provide the machinery for assessing compensation for any breach of warranty irrespective
of the weather. There was no sensible business reason why the parties should have intended
that the charterers should be compensated for under performance in periods of good weather,
but not in periods of bad weather.
The extrapolation of a vessel's performance in good weather to the entire length of the voyage is the
correct method for assessing damages due to the ship under-performance and / or over-consumption.
The evaluation method applied by Weathernews is analyzed on a 6 hourly basis to determine a good
weather period is as follows:
1. The overall voyage is separated into individual days, where a day is taken to be the
period of time between consecutive daily noon positions. Therefore the duration of a day
can range from 23 to 25 hours depending on the direction and number of time zones a
vessel passes through.
2. The weather / seas at 00Z, 06Z, 12Z, and 18Z for each day are analyzed and categorized
as either Good (within the good weather definitions) or Bad.
3. If the majority of the above slots (over half the day) are categorized as Good, then the
whole day is considered a good weather day.
When the good weather definition includes no adverse current or an equivalent stipulation, step 3)
above should abide by this stipulation by taking into consideration the current factor when selecting
good weather days: wind / sea conditions need to be within the good weather definition thresholds and
the average daily current factor must be zero or a positive value. If this stipulation is neglected, the
analysis results in incorrect conclusions.
Q5. Does BF4 imply DSS3 even when it is not explicitly stated in the
Charter Party?
Usually, the correct good weather definition can be verified by analyzing the charter party good
weather definition, but there are some cases when the charter party itself is not clear enough and
causes disputes. One example: The charter party good weather definition is up to and including BF4;
there is no mention of wave height thresholds.
In such a case, it could be argued that, as there is a causal relationship between winds and waves,
the good weather definition for a charter party that only states BF4 should also include the threshold
DSS3 for waves. Owners may take this point of view if it suits the limitations that sets on the number of
days selected as good weather days. Charterers may argue that the charter party good weather
definition should be read exactly as it is and needs no interpretation: If it does not state a wave height
limit, then there is none. Sometimes owners and charterers can find a way to negotiate on the correct
reading of the charter party. But sometimes these disputes go to arbitration.
In Arbitration, good weather definitions have in the past been interpreted very strictly as meaning
exactly what they state, and no more. One example for such a case is 2006 LMLN 682:
Nothing was said in clause 29 about weather or sea conditions. The charterers said that that meant
that the owners warranted that the ship would perform under the charter at the stated speed and
consumption, whatever the weather. The owners said that, on the contrary, the warranties only
applied in perfect conditions, and that since between Algeiras and the Brazilian discharge port the
ship performed at 12.09 knots, ie about 12.50 knots, there was no breach.
Held, that the tribunal did not accept the owners' argument. In the tribunal's experience it was very
unusual to find such an unqualified warranty in a normal charter. Nevertheless, the tribunal did not see
how it could fairly read the relevant words in clause 29 as the owners suggested. The natural meaning
of the words was that the ship was to perform at the stated speed and consumption throughout the
trip. If the owners had wanted to qualify their obligations in some way, they should have inserted
words such as the common in good weather and smooth water, or even without guarantee.
Otherwise the words had to given the broad meaning argued for by the charterers.
This is a very strict interpretation, and it was surely a painful reminder that, as it stands, the risk of
signing unclear charter parties lies with the signatories. Weathernews therefore strongly urge all
owners and charterers to ensure that the contracts they sign are as clear as possible.
Q6. The Good Weather Period for this voyage is too short. Surely it
can not be sufficient?
The shortest allowable good weather period for a good weather analysis in London arbitration was
24.5 hours. It is important that charterers understand this condition for the good weather analysis and
that shorter time periods are not sufficient.
If the vessel does not perform to the Charter Party warranted speed & consumption for 24 hours or
longer in good weather during the voyage (excluding periods of bad weather, off hire, periods of slow
steaming at the Charterer's request, canal transit etc) then there must be a good reason given by the
Master for the speed reduction.
The award 670 LMLN 1 (2005, London Arbitration 15/05):
In the event, the good weather performance of the vessel (between 0130 on 19 and 0200 on 20
November) could be assessed in round terms as 12.21 knots (305.3 miles 24.50 hrs less 0.25 knots
current factor) against her warranted performance speed of 13.00 knots (13.50 less 0.5 knots for
about). There was therefore an under-performance.
The tribunal had accepted the overall mileage steamed as 5,224.60 nautical miles. Thus, had the
vessel steamed throughout at 13.00 knots she would have taken approximately 401.89 hrs (5,224.60
nms 13.00 kts). At her actual good weather speed of 12.21 knots she would have taken
approximately 427.89 hrs (5,224.60 nms 12.21 knots) - a loss of approximately 26 hours.
The calculations shown above indicate that the good weather period during a journey of well over
400 hours was only 24.5 hours. Important to note: When the good weather period is less than 24 hours,
it would be seen as insufficient.
(2007) 718 LMLN 3 London Arbitration 9/07
As to whether the voyages of less than 36 hours duration could be taken into account for the purpose
of assessing the vessel's good weather capability, the charterers had conceded that very short
voyages of less than 24 hours duration should not be taken into account. However, the charterers
were correct in contending that the vessel should have been able to achieve her warranted speed in
good weather on any voyage of 24 hours of more.
As the above stated, voyages of 24 hours or longer should be included in performance calculations.
Held, that there had been an over-consumption as contended for by the charterers, but the tribunal
would agree with the owners that the charterers' claim had to lie in damages, and that in calculating it,
credit had to be given for any savings in time or fuel oil consumption. .... In the present case, it was
sufficient to say that on any view the lower than warranted consumption of fuel oil substantially
outweighed, in terms of the value of the bunkers in question, the over-consumption of diesel oil. Thus,
although there was a breach, there were no damages and the charterers' claim had to fail.
2007 LMLN 718
Held, that dealing, first, with the cargo heating point, the owners' case was that on those voyages
where heating did take place less fuel was used in cargo heating than was warranted and therefore
they could set that off against any over-consumption in other respects. All the charterers had done, in
their calculations, was to give credit for the fuel actually used in heating............................
Therefore, the tribunal concluded that any under-consumption in cargo heating, whether at sea or in
port, should be credited against over-consumption or under-performance at sea measured by
reference to the relevant warranties.