Problem-01:
Fred Jacobs, assistant manager of Home and Hearth, is reviewing the cost associated with the stores best-selling frying pan. The
data available to Mr. Jacobs concerning this frying pan follow.
a)
b)
Demand = 20units/week
Order cost = $75/ order
Holding cost = $15/ unit/yr.
Home and Hearth operates 50 weeks per year.
The current order quantity is 125 units per order. What is the annual ordering Cost, holding cost and total cost?
Jacobs has recently learned of the economic order quantity in his Operations management class. If Home and Hearth
implemented the EOQ, what are the changes Jacob found in ordering cost, holding cost and total cost?
a)
b)
c)
d)
e)
It is time for periodic review. How much kitty litter should be re-ordered?
Calculate the items EOQ. What is the average time between orders in weeks?
Find the safety stock and re-order point that provides a 95% cycle service level.
For these policies, what are the annual cost of (i) holding the cycle inventory and (ii) placing orders.
A withdrawal of 15 units just occurred, is it time to re-order?
A Golf specialty wholesaler operates 50 weeks per year. Management is trying to determine an inventory
policy for its 1-irons which have the following characteristics:
Demand
= 2000 units/year
Ordering and set-up cost
= $ 40 per order
Holding cost
= $ 5 per unit per year
Lead time
=4 weeks
Standard deviation of weekly demand
= 3 units
Cycle service level
= 90% (Z = 1.4)
a) If the company uses a periodic review system, what should P and T be? Round P to the nearest weeks.
b) If the company uses a continuous review system, what should R be?
EOQ
2 DS
2(4,680)($ 54)
159,949.37
$3.16
= 399.93, or 400 bags.
dLT d L = 15 3 = 25.98 or 26
Safety stock = 0.84 * 26 = 21.82, or 22 bags
R 270 22 292
When the EOQ is used these two costs are equal. When Q 500 , the
annual holding cost is larger than the ordering cost, therefore Q is too
large. Total costs are $789.75 + $505.44 = $1,295.19.
e. Annual holding cost
Q
400
27% $11.70
H
2
2
$631.80
Total cost using EOQ is $1,263.60, which is $31.59 less than when the
order quantity is 500 bags.
Problem-05: (Exercise problem 16 page 442 krajewski)
Sams Cat Hotel with a P system
a. Referring to Problem 7, the EOQ is 400 bags. When the demand rate
is 15 per day, the average time between orders is (400/15) = 26.67 or
about 27 days. The lead time is 3 weeks 6 days per week = 18 days.
If the review period is set equal to the EOQs average time between
orders (27 days), then the protection interval (P + L) = (27 + 18) =
45 days.
For an 80% cycle-service level
z = 0.84
P L d P L
P L (6.124) 27 18 = 41.08
Safety stock = z P L = 0.84(41.08) = 34.51 or 35 bags
T = Average demand during the protection interval + Safety stock
T = (15*45) + 35 = 710
b. In Problem 7, the Q system required a safety stock of 22 bags to
achieve an 80% cycle-service level. Therefore, the P system requires
a safety stock that is larger by (35 22) = 13 bags.
c. From Problem 7, inventory position, IP = 320.
EOQ
2 2, 000 40
2 DS
894.4
H
2
or 894 units
z d L
EOQ
2 20, 000 40
2 DS
894.4
H
2
or 894 units
EOQ
894
P is rounded to 2 weeks.
f. For a 95% cycle-service level, z = 1.65. Therefore
Safety stock z P L
P L d P L
178.88
H
5
or 179 1-irons
P
EOQ 179
Suppose that the policy variable, was 0. How many containers would be needed now? What is the effect
of the policy variable in this example?
Find the policy variable, , that expresses the amount of implied safety stock in this system
b) Use the implied value of from part (a) to determine the required reduction in waiting time if one container
was removed. Assume that all other parameters remain constant.
Problem-05: (Exercise problem 4 page 317 krajjewski)
An assembly line requires two components: gadjits and witjits. Gadjits are produced by center 1 and widjits by
center 2. Each unit of end item called a jit-together, requires 3 gadjits and 2 widjits. The daily production quota on
the assembly line is 800 jit-togethers.
The container of gadjit s holds 80 units. The policy variable for center is set at 0.09. The average waiting time for a
container of gadjits is 0.09 day and 0.06 day is needed to produce a container. The container for widjits holds 50
units and the policy variable for center 2 is 0.08. The average waiting time for container of widjits is 0.14 day, and
the time required to process a container is 0.20 day.
a)
Problem: 03
Spradleys Sprockets
d ( w )(1 )
c
k=
500(0.20 1.80)(1 0.05)
20
k=
k = 52.5
Problem: 04
LeWin
a. Solving for implied policy variable,
d ( w )(1 )
c
k=
12
1 a
300
12 300
1.0256
1.0256 1 0.0256
b. Reduction in waiting time
1,800 w 0.90 1.0256
1,846 w 1, 661.47
11
300
300
Problem: 05
Gadjits and Widjits
a. Containers for gadjits
d ( w )(1 )
c
k=
800(3)( 0.09 0.06)(1 0.09)
80
k=
= 4.905
k=5
b. Containers for widjits
d ( w )(1 )
c
k=
800(2)(0.14 0.20)(1 0.08)
50
k=
= 11.750
k = 12
Raw materials
RM-1
20,000
$1
RM-2
5,000
$5
Work-in-process
Finished Goods
RM-3
3,000
$6
RM-4
1,000
$8
WIP-1
6,000
$10
WIP-2
8,000
$12
FG-1
1,000
$65
FG-2
500
$88
Raw materials
RM-1
15,000
$3
RM-2
2,500
$5
RM-3
3,000
$1
WIP-1
5,000
$14
WIP-2
4,000
$18
FG-1
2,000
$48
FG-2
1,000
$62
Work-in-process
Finished Goods
$6,237,000
= $12,053,000
Weeks of supply
b. Inventory turnover
Average
Inventory (units) Value ($/unit)
RM-1
20,000
1.00
20,000
RM-2
5,000
5.00
25,000
RM-3
3,000
6.00
18,000
RM-4
1,000
8.00
8,000
WIP-1
6,000
10.00
60,000
WIP-2
8,000
12.00
96,000
FG-1
1,000
65.00
65,000
FG-2
500
88.00
44,000
= $336,000/$125,000
= 2.688 weeks.
B(2)
C(2)
C(2)
E(1)
D(2)
F(2)
Drive shaft
Lot Size:
50 units
Gross requirements
35
25
15
20
40
40
50
50
Scheduled receipts
80
Projected on hand10
55
30
15
45
15
15
15
50
50
50
Planned receipts
Planned
releases
50
order 50
50
50
50
b. L4L
Item:
Drive shaft
Lot Size:
L4L
Gross requirements
35
25
15
20
40
40
50
50
Scheduled receipts
80
Projected on hand10
55
30
15
40
40
50
50
50
50
Planned receipts
Planned order
releases
40
40
c. POQ with P = 4
Item:
Drive shaft
Lot Size:
POQ, P = 4
Gross requirements
35
25
15
20
40
40
50
50
Scheduled receipts
80
Projected on hand10
55
30
15
130
90
50
Planned receipts
135
Planned order
releases
135
50
50
MQ09
Description:
assembly
Lot Size:
Rear wheel
Week
Gross requirements
205
Scheduled receipts
300
Projected
on
hand 195
100
195
65
Planned receipts
Planned order
releases
FOQ: 300
4
85
280
300
300
280
70
60
95
210 150
55
b. Lot-for-lot
Item:
MQ09
Description:
assembly
Lot Size:
Rear wheel
Week
Gross requirements
205
Scheduled receipts
300
Projected
on
hand 195
100
195
130
85
65
Planned receipts
20
70
60
95
70
60
95
60
95
20
Planned order
releases
L4L
70
MQ09
Description:
assembly
Lot Size:
Rear wheel
Week
Gross requirements
205
Scheduled receipts
300
Projected
on
hand 195
100
195
130
85
65
130
Planned receipts
Planned order
releases
POQ, P = 4
130
70
60
95
60
150
150
0
95
95
C(2)
D(1)
F(2)
D(1)
E(1)
F(2)
E(2)
E(1)
F(1)
F(1)
F(1)
Data Category
Item
C
FOQ = 220
L4L
FOQ = 300
POQ (P = 2)
Lead time
3 weeks
2 weeks
3 weeks
2 weeks
Scheduled
receipts
280 (week
1)
None
300 (week
3)
None
On-hand
inventory
25
150
600
Lot-size rule
Item:
Lot Size:
Description:
Week
Gross requirements
Scheduled receipts
170
155
155
200
280
FOQ = 220
305
135
135
135
155
220
Planned
releases
Item:
order
220
Lot Size:
Description:
L4L
Week
Gross requirements
85
180
100
180
100
Scheduled receipts
Projected on hand 0
Planned receipts
Planned
releases
Item:
order
85
85
180
100
Lot Size:
Description:
Week
Gross requirements
85
Scheduled receipts
Projected on hand
150
order
180
100
360
85
25
25
25
25
300
65
65
Planned receipts
Planned
releases
FOQ = 300
185
300
300
Item:
Lot Size:
Description:
POQ = 2
Week
170
300
360
200
130
200
Gross requirements
Scheduled receipts
Planned receipts
Planned
releases
430
order 430
Two notices are identified: order 85 units of D and 430 units of F. Please
note that action notices were not asked for in the problem.