Pending Points Civil
Pending Points Civil
Sl.
No.
1
Indore Dia
Sump pit height should be increased according to the yard level. Their cover also
need to be placed.
Cable trench covers with lifting lugs shall be placed at interval of 10 cover slabs.
Excavated material from earthing activity on side parallel to boundary wall should be
cleaned and dumped outside the fence area.
Increase of turning radius at 3.75 meter road near reactor-1 (Spare indore dia).
Kiosk No. 2
JB cutouts & switchboard are not properly fitted, need to repair.
Kiosk No. 3
JB cutouts & switchboard are not properly fitted, need to repair.
Transformer Area
ICT 1 rail cum road rail is settle down from its PL level, need to reconstruct.
Reactor Area
Reactor 1 pheriphery wall height shall be increased as per site level conditions.
Common Points
Area levelling and proper slope for smooth drainage of rain water from switchyard to
pheriphery drains balance.
Wheel roller fixing and painting balance for five nos switchyard fencing gates.
New Points
Damaged Drain parallel to Indore dia needed to be repaired.
Damaged Drain parallel to Bus reactor dia needed to be repaired.
Damaged Drain behind ICT's and towards Store side needed to be repaired.
BUILDING
Sl.
No
.
1
LT Panel Room
JB cutouts in the ceiling are uncovered.
Battery Room
Skirting top not filled with white cement properly.
JB cutouts in the ceiling are uncovered.
Replacement of hatch bolt and door handle with approved quality and fixing of body
lock at door.
Reception Area
Door not opening properly and cleaning of door frame is required.
Replacement of hatch bolt and door handle with approved quality and fixing of body
lock at door.
Stair Case
Point on wall where the hand rail is fixed shall be repaired and fixed.
JB cutouts in the ceiling and walls are uncovered.
10
NT Panel Room
JB cutouts in the ceiling and walls are uncovered.
11
12
Pantry
Big JB cutouts in the ceiling and walls shall be covered
One power socket is required nearby slab.
Exhaust fan installation required
13
14
15
New Points
Leakage from false Ceiling of conference room, SCADA room.
Leakage from side walls in the stair case area.
Replacement of dirty fiber door glass of Auxiliary Panel in the NT Panel room.