Background / Overview
D
R
AF
Interim Proposal
Interim arrangements needed until bus operations can migrate to new facility (~18
months construction period)
Rationale for not using site in temporary capacity
Manukau Interchange already hard pressed to be delivered to budget. Using site while
building on it at the same time will mean additional cost and probable delay to the
project
Southern area of site proposed as parking (to mitigate HR staff issues with parking
allocation lost)
Temporary facilities at the site (rather than on street) will be harder to manage from a
build perspective not desirable outcome to be on site until Interchange built
easier and better operational and customer offering to provide adequate onstreet facilities
PT Operators and AT Metro preference when opening new facility is to be handed the
facility first before opening (4-6 weeks) to ensure drivers and staff have training without
interference this is a best practice approach.
Above approach endorsed at SMG meeting 15/4 (Mark Lambert agreement)
D
R
AF
Through/
Terminate
Through
Through
Terminate
2016
33
PapakuratoOtahuhu
361
368
WiriIndustrial clockwiseloop
369
WiriIndustrial anticlockwiseloop
Terminate
313
OnehungatoManukauviaMangere,westernPapatoetoeandPlunketAve
Terminate
362
WeymouthtoManukau
Terminate
365
PorchesterRdtoManukau
Terminate
366
TheGardentoManukau
Terminate
35
BotanytoManukauviaChapelRd
Terminate
10
355
BotanytoManukauViaFlatBush
Terminate
11
356
Flatbush Manukau
Terminate
12
325
Mangere,Otahuhu,OtaratoManukau
Terminate
13
352
PanmuretoManukauviaHighbrrokandEastTamaki
Terminate
14
353
BotanytoManukuaviaPrestonRd
Terminate
15
30
Airport
Terminate
47
64
D
R
AF
TotalBusperhour
33
PapakuratoOtahuhu
Layover
(Tentative/
Interchangeable)
0
2(DaviesAv.Bothdir.)
2(DaviesAv.Bothdir.)
Through/
Terminate
Peak Freq.
(bus per hour)
Through
Through
Route
Sl No
No
Terminate
1(DaviesAv.Onedir.)
Terminate
1(Ronwood Av.)
313 OnehungatoManukauviaMangere,westernPapatoetoeand
PlunketAve
362 WeymouthtoManukau
Terminate
1 (PutneyWay)
365 PorchesterRdtoManukau
Terminate
1(Ronwood Av.)
366 TheGardentoManukau
Terminate
1 (PutneyWay)
2(DaviesAv.Bothdir.)&
LO
1 (PutneyWay)
35
BotanytoManukauviaChapelRd
Terminate
1 (PutneyWay)
1 (PutneyWay)
10
355 BotanytoManukauViaFlatBush
Terminate
1 (PutneyWay)
1 (PutneyWay)
11
Terminate
Sharedwith355
Sharedwith355
12
325 Mangere,Otahuhu,OtaratoManukau
Terminate
1 (PutneyWay)
1 (PutneyWay)
13
Terminate
1(RainbowsEnd)
2(DaviesAv.Bothdir.)
14
353 BotanytoManukuaviaPrestonRd
Terminate
1(RainbowsEnd)
2(DaviesAv.Bothdir.)
15
30
Terminate
1(RainbowsEnd)
2(DaviesAv.Bothdir.)
47
11
D
R
AF
Total
1(DaviesAv.
Servicelane)
Shared with368
Airport
Terminate
Loading Bays
1(DaviesAv.Onedir.)
2(DaviesAv.Bothdir.)&
LO
1 (PutneyWay)
33
355
361
356
368
325
369
352
313
D
R
AF
362
Through routes = 2
Terminating routes = 13
365
366
35
353
30
D
R
AF
40m
33
361
325
D
R
AF
362
355
366
35
352
353
30
D
R
AF
Option 1 Layover at
Putney Way may be shared
Option 3 Layover at
Davies Av
10
D
R
AF
313
365
11
D
R
AF
368
369
D
R
AF
12
D
R
AF
Next Steps:
Interim layover options to be further analysed and finalised
Detailed design commences for interim proposal July / Aug
Design consultation Aug / Sept
TCC approval Oct / Nov
Construction Drawings / shelter orders etc Oct / Nov
Construction temporary on-street facilities Jan / Feb 2016
Go live temporary on-street facilities May 2016
Risks to N Network Go Live
Design/consult/construction process for temporary infrastructure
delayed
Budget