CONTRACT NO: TNBT (T) 459/2014 (ERMS 550026978) PROPOSED 132KV GIS
BUILDING FOR FUTURE PMU 132/33/11KV PANDAN MESRA, SELANGOR.
METHOD OF STATEMENT
To Construct Boundary Drain
1.0
OBJECTIVE
This method of statement covers the requirements for the construction of boundary drain at
PMU Pandan Mesra.
2.0
3.0
2.2
All workers should have relevant documentation and the appropriate PPE and also
CIDB green card & NIOSH (NTSP) before work can commence.
3.2
3.3
Demarcation exercise shall be carried out to determine the position of the boundary
and a temporary benchmark (TBM) established to check the level of the existing
land. Please refer to drawing no. PZE11/13/TNB/AMP/RD-1D.
3.4
If the ground level is lower than invert level of drainage, we must do the backfilling
to require height as per design.
3.5
When the setting out done, we pull string line for the alignment of drainage. We do
the leveling pour concrete G15 as a lean concrete. A day after, we install both side
formworks and also one layer of BRC no. A7 then pour concrete G20 as a base of
drainage. Please refer to drawing no. PZE11/13/TNB/AMP/RD-2D.
3.6
3.7
After that, we will continue with the brick laying 225mm thick come with plaster
internal side as a wall drainage. Please refer to drawing no.
PZE11/13/TNB/AMP/RD-2D.
3.8
100x100 Strut with 4R10 and R6-150 links at 3000mm c/c need to install for drain
wall exceed 750mm deep.
3.9
100mm diameter PVC pipe also need to be install as a weep hole at 3000mm c/c.
3.10 From item 3.3 to 3.9 will repeat until the completion of the drainage works.
4.0
5.0
POTENTIAL HAZARD
4.1
Machinery (JCB, Mixer and lorry - Unskilled workers shall be given a safety
induction before work commences and also machinery must have valid
documentation such is permit, driving license etc.
4.2
4.3
Only pertinent personnel should be allowed to be in the vicinity. The area should be
cordoned off using barriers and access shall be restricted to relevant personnel only.
RESPONSIBILITY
Contractor
Site Safety Supervisor
Site Engineer
Site Supervisor
5.0
PLANNING
As per attached work schedule
8.0
QUALITY PLAN
SAFETY PLAN
As per standard set by Tenaga Nasional Berhad
10.0