Professional Documents
Culture Documents
Prosedur Kelulusan Sistem Pembetungan: April 2010
Prosedur Kelulusan Sistem Pembetungan: April 2010
PEMBETUNGAN
April 2010
Ir. Sohaimi b. Kling
Agensi Perakuan
Merujuk kpd WSIA 2006 (Akta 655):Seksyen 174 (1)- Suruhanjaya boleh mendaftarkan
agensi perakuan bagi maksud :(a) meluluskan pelan, spesifikasi atau reka bentuk
terperinci berkenaan dengan pembinaan sistem
bekalan air , sistem pembetungan, tangki septik,
perpaipan pembetungan
Seksyen 174 (2)-Sesuatu kelulusan oleh
agensi perakuan berdaftar hendaklah disifatkan
sebagai kelulusan oleh SPAN..
Approving Authority
SPAN , under the WSIA 2006, is the approving
authority for any sewerage system.
Certifying Agency
- appointed by SPAN to examine all sewerage
proposals, make recommendations in meeting
sewerage needs of the development and assigned
to inspect construction and recommend for CF.
7. Akta Industri
Perkhidmatan
Air 2006
8. Akta Keselamatan &
Kesihatan Pekerjaan
(OSHA 1994)
9. Akta Kualiti Alam
Sekeliling(EQA 1974)
Guidelines
-sets the minimum standard for certification of sewerage
works for developers and their consulting engineers
Qualified Person
-Person responsible to the design, construction and overall
quality of completed sewerage work
-Have sufficient sewerage technical expertise to ensure
sewerage works are properly engineered during design
and construction.
Project brief
Sewerage proposal
PE derivation
In line with catchment strategy
Adjacent lot development
STP area and buffer zone
Siting area
Effluent discharge & Water catchment
Appendix A
Figure A.4
600
Concrete Benching
"Rocker" Pipe
200 min 500 max
1:12
150 min
600
Max
300 Min.
50 Thk. Cementitious
Blinding
Appendix A
Figure A.16 : Vacuum Sewerage System, House Connection and exa mple of
Vacuum Station
Vacuum Sewer
Service
Gravi ty
Drai n
Connection
Collecti on
Chamber
Vacuum
sewer
House connection
Inspection
Chamber
Vent
W here Required
Vacuum reservoi r
moisture removal tank
Gravity Inlet
Control
Vacuum Sewer
Emergenc y Overflow
Panel
Vacuum
Pumps
Vacuum
Sewers
Rising Main
Rising Main
Forwarding Pumps
Forwarding Pump
Vacuum Vessels
Sewage
Figure A.15
Ammeter
Motor
Isolator Switch
Coupling
Shaft
Delivery
Valve
Gland
Volute Case
Access Cover
Rising Main
Suction Valve
Impeller
Travelling Gantry
Crane
Screen
Mechanism
Skip To
remove
Screenings
Extractor Fan
Motor
Ventilation
Duct
Control
Gates
Mechanically
Cleaned
Screen
Coupling
Shaft With
Mesh Guard
Ventilation Inlet
Duct
Rising Main
Bracket
Alarm Level
GRP Ventilation
Inlet Duct
Pump
Check Valve
Reducer
Concrete Plinth
Longitudinal section
Ground level, invert level, depth, distance
Gradient, pipe size, type of pipe, type of bedding,
type of MH
All utilities crossing
Form SSA/PDC/8
Checklist for Final Inspection -Checklist PDC 8a
Related Checklist PDC 8b/c/d
STP & NPS -Checklist PDC 8e & 8f
Copy of Sewerage Works Approval
A3 plans indicating related works under construction
Copy of valid contractors license
FINAL INSPECTION
Developer to carry out remedial works for
deficiencies and/or unsatisfactory quality of
works identified by SPANs Authorised Person
CA may request for re-inspection due to bad
workmanship
CA may withhold recommendation for CF
when the works deemed unfit and/ or lead to
safety/ health risk.
FINAL INSPECTION / CF
When sewerage system( network, NPS and
STP are in full compliance to Guidelines and
approved drawings, CA shall recommend for
CF to LA
Owner to provide letter of
undertaking for the transfer
of STP and/PS land title to
the Government.
ISU
1. Keperluan sistem pembetungan tidak dipatuhi
sepenuhnya semasa mengemukakan
permohonan.
2. Ulasan yang dikeluarkan tidak dipinda semasa
permohonan- semula.
3. Kedudukan logi tidak mengambilkira kesesuaian
berdasarkan kriteria teknikal, persekitaran dan
sensitiviti penduduk berdekatan.
4. Pembinaan sistem pembetungan tidak
mengikut pelan yang diluluskan.
5. Memastikan agar jururunding yang
berkelayakan dibenarkan mengemukakan
permohonan sistem pembetungan.
WSIA 2006
CONCLUSION
Wastewater engineering is a specialised field,
challenges.
TERIMA KASIH