Hydropower in
Somerset and Dorset
Mill Owners Working Together
Keith Wheaton-Green
Original
Power
How it started
UK Governments expectation of local
authorities
South Somerset
Hydro resource & Mill sites
First Contact
Keith & Mandy Careys Mill
First Meeting
Funding Application
Energy Saving Trust Innovative Carbon
Reduction Pilot - 8k for feasibility
90k for implementation
SWEBs Green Electron Fund - 45k
Partnership Working
Original
Power
A
breakthrough
in costs for
small site?
Pico +
Less than
600 (inc
electronic
controls)
Head
1.25m
Flow 35 l/s
0.24 kW
230v
50 Hz
Crossflow Turbine
Francis Turbine
Armfield
Hydrogenerations Polymer
Francis Turbine
Feasibility Study
Electricity generating potential
This can be calculated using the formula P(kW) = Q x H x 9.81 x E
Catchment
Annual flows
Catchment area
= 10.42 km2
= 1052.5 mm
= 524 mm
= 5,522,600 m3
= 0.17 m3/s
Q95
m3/s
= 0.061
Residual flow
= 0.020 m3/s
= 0.15 m3/s
Q40
= 0.16 m3/s
(Qmean)
1.0
3.00
0.9
2.90
0.8
2.80
0.7
2.70
0.6
2.60
0.5
2.50
0.4
2.40
0.3
2.30
0.2
2.20
0.1
2.10
0.0
0%
10%
20%
30%
40%
50%
60%
exceedence
70%
80%
90%
2.00
100%
head (m)
flow (m3/s)
Canford School