Professional Documents
Culture Documents
06 Pert PDF
06 Pert PDF
Project Networks
PERT
Developed to aid understanding of how variability in
the duration of individual activities impacts the
entire project schedule
Create 3 estimates of time to complete each activity
Optimistic
Most likely
Pessimistic
Estimated time = Optimistic + 4(Most likely) + Pessimistic
6
4
DESCRIPTION
IMMEDIATE
PREDECESSORS
D, E
F, G
Build Internal
Components
Construct
Collection Stack
Install Control
System
Start
Build Burner
Inspect
and Test
Modify Roof
and Floor
Pour Concrete
and Install Frame
Install Pollution
Device
Finish
Activity Times
In some situations, activity times are known with certainty
CPM assigns just one time estimate to each activity and this is
used to find the critical path
In many projects there is uncertainty about activity times
PERT employs a probability distribution based on three time
estimates for each activity
A weighted average of these estimates is used for the time
estimate and this is used to determine the critical path
7
Activity Times
The time estimates in PERT are
Optimistic time (a) = time an activity will take if everything goes
Activity Times
PERT often assumes time estimates follow a beta
probability distribution
Probability
Probability of 1 in 100 of
a Occurring
Probability of 1 in 100 of
b Occurring
Most
Optimistic
Time
Most
Likely
Time
(a)
(m)
Most
Pessimistic
Time
Activity Time
(b)
Activity Times
To find the expected activity time (t), the beta distribution
weights the estimates as follows
a 4m b
t
6
ba
Variance
10
Activity Times
Time estimates (weeks) for General Foundry
ACTIVITY
OPTIMISTIC,
a
MOST
PROBABLE,
m
PESSIMISTIC,
b
4/36
4/36
4/36
16/36
36/36
64/36
11
64/36
4/36
EXPECTED
TIME,
t = [(a + 4m + b)/6]
VARIANCE,
[(b a)/6]2
25
11
Start
2
Finish
13
14
2
2
2
C
2
2
2
4
4
F
4
10
E
4
4
Start
B
0
1
3
3
4
D
3
4
4
7
8
3
7
13
4
8
8
H
13
13
G
8
8
t
EF
LF
2
15
15
Finish
5
13
13
15
LATEST
FINISH,
LF
TOTAL
SLACK,
LS ES
ACTIVITY
EARLIEST
START,
ES
EARLIEST
FINISH,
EF
ON
CRITICAL
PATH?
Yes
No
Yes
No
Yes
10
13
No
13
13
Yes
13
15
13
15
Yes
Table 13.3
17
2
2
2
FS=0
C
2
2
TS=0
2
4
4
TS=6
FS=0
3
3
4
TS=1
FS=0
D
3
4
TS=1
FS=6
4
8
8
H
13
13
2
15
15
TS=0
FS=0
TS=0
FS=0
4
7
8
FS=1
3
7
13
E
4
4
Start
B
0
1
F
4
10
G
8
8
TS=0
Finish
5
13
13
FS=0
TS = Total Slack
FS = Free Slack
Free slack (or Free Float) - Free slack is unique. It is the amount of time an
activity can be delayed without delaying ES of any of immediately following
(successor) activity. Normally, Free Slack <= Total Slack.
18
ACTIVITY
VARIANCE
4/36
4/36
4/36
16/36
36/36
64/36
64/36
4/36
21
Figure 13.7
15 Weeks
(Expected Completion Time)
16 weeks 15 weeks
0.57
1.76 weeks
From Normal prob. Table, we find the probability of 0.71566 associated with
this Z value
That means there is a 71.6% probability this project can be completed in 16
weeks or less
23
Probability
(T 16 Weeks)
is 71.6%
15
Weeks
16
Weeks
Time
You should be aware that noncritical activities also has variability. In fact a
different critical path can evolve because of the probabilistic situation. This
may cause probabilistic estimate to be unreliable. In such a situation, it is
better to use simulation to determine probabilities.
24
26
27
Backup
28