Professional Documents
Culture Documents
1982 624 3 Thornton
1982 624 3 Thornton
CONTRACTOR :
TITLE :
AUTHOR :
Judith Thornto n
Department of Economic s
University of Washingto n
PRINCIPAL INVESTIGATOR :
DATE :
Judith Thornto n
624- 3
May 7, 198 2
THE IMPACT OF NUCLEAR POWER ON THE COST OF CAPITAL IN SOVIET ELECTRIC POWE R
Judith Thornto n
The estimation of the size and rate of growth of Soviet capital stock i s
an intractable problem . We can estimate the value of investment expenditure s
at current prices for aggregate sectors of the economy, but we cannot partitio n
the year-to-year change in value into a change in real capital and a change i n
the price of investment goods . For individual industries, we do not hav e
current-price investment series ; we have Soviet official " constant-price "
series, fragments of which are in the constant prices of different years .
Although we might like to take the word of our Soviet sources that their serie s
at constant prices would satisfy both Etienne Laspeyres and Hermann Paasche, th e
generally accepted evidence on inflation in the official machinery productio n
indices raises questions about the investment and capital stock series as well .
For capital stock itself, we have two accounts of the value of capital stoc k
at current prices for 1960 and 1972, but to move between or beyond these two year s
there are only official constant price series again .
Recently, in an exchange in Soviet Studies, two knowledgeable students o f
Soviet investment, Alec Nove and Stanley Cohn, raised some puzzling questions .
Nove postulates that, if the real cost of capital goods has been rising faste r
than the money allocated for expenditure, then a moderate rise in the financing
-3 extraction, and natural gas, all face still higher capital costs per unit o f
output . In electric power, more than 70 percent of the planned increase i n
productive capacity is to come from new nuclear and hydroelectric capacity . 3
All of the growth of power capacity in the Western regions will come fro m
these sources . But the capital cost of a nuclear plant is about twice tha t
of a gas-fired thermal electric plant ; the capital cost of pumped-storag e
hydroelectric capacity is at least three times higher than gas-fired . 4
So
the new plans for electric power will make heavy demands on the capita l
allocated to industry .
The pages that follow discuss four aspects of the issue . The firs t
section provides a brief overview of the status of the electric power industry .
The next section describes evidence on the cost of fixed capital in electri c
power and presents my estimates of constant-price capital stock . The followin g
pages provide information on the cost of nuclear capacity and estimates of th e
" overnight capital cost " of Soviet nuclear plants . Finally, the pape r
provides some preliminary estimates of the capital cost of the new Five Yea r
Plan for electric power .
-7 series for the Fifties and the Seventies, the implied price of capacity wa s
rising at 3 .3 percent per year for the whole period 1950 to 1979 . So, a t
least in the case of electric power, Coh n ' s confidence in the official Sovie t
series seems to be misplaced .
Would these numbers have been different, had we measured the capital cos t
of output rather than of capacity? Using Robert Campbell ' s estimates o f
power available for consumption of 255 .8 billion kwh . in 1960 and 887 .6 billio n
kwh . in 1975, the value of capital per unit of output grew from 3 .7 kopek s
in 1960 to 6 .75 kopeks in 1975, an increase of 4 .1 percent per year .
The changes in accounting values were distributed fairly evenly amon g
different types of capacity . Table 6 gives a breakdown of productive fixe d
capital assigned to thermal and hydroelectric production, transmission network ,
and other for the years 1970 and 1975 as well as the planned values for 1980 .
If we calculate the changes in costs per unit of the individual types of capacity ,
then, the cost of a unit of capacity was rising at the following rates : 3 .4 percen t
for total capacity, 2 .4 percent for hydroelectric capacity, 3 .2 percent for therma l
electric capacity, and 2 .7 percent for transmission capacity (assumed proportiona l
to the total length of lines .) The growing other category includes trainin g
facilities for nuclear engineers, some repair facilities, and possibly facilitie s
for the production of nuclear fuel elements .
The levels of cost in Table 6 coincide with other cost information that i s
available . A recent handbook on the construction of electric power station s
provides the estimate costs for 28 turbine, 38 co-generating, and six nuclea r
plants that were constructed or under construction during the 1970 ' s . Fo r
51 .8 million kilowatts of turbine capacity, the unit capital cost was 124 . 9
rubles per kilowatt ; for 3 .1 million kilowatts of co-generating capacity, th e
unit cost was 215 .3 rubles per kilowatt of power only, making no allocation for
-8 heat ; for 8 .6 million kilowatts of nuclear capacity, the unit capital cos t
was 213 .8 The capital costs of the transmission network network were almos t
as large as productinn capital costs, and they added a substantial incremen t
to the capital cost of delivering electric power .
The capital stock series provide measures of the average cost of past capita l
acquisitions . Presumably, when the cost of new capital goods rises, the ris e
brings up the cost of total capital stock slowly since most of the existin g
capital stock was purchased in earlier periods . So a rise in the cost o f
acquisitions of new capital should show up more strongly in current investmen t
costs . However, Soviet handbooks have published current-price measures fo r
newly commissioned capital for the years 1964-67 only . For other years ther e
are investment series described as being in constant prices again--in the price s
of 1969 for the last decade . Still, we can pursue the exercise of comparin g
investment allocations with capacity completions in various periods to see wha t
was happening to apparent investment cost . These numbers are likely to be les s
stable than the capital series since there are long time lags between appropriation s
of finance and completions of capacity, since I have made no adjustment fo r
changes in unfinished construction, and since capacity is completed in large units .
Unit investment costs are probably biased downward in the last year of each Fiv e
Year Plan and biased upward slightly in the other years by the tendency to finis h
capacities in the last year of a plan .
Still, with all these reservations, the investment data generally confirm th e
results of the capital stock calculations . Table 8 gives the allocation o f
investment, completion of capacity, and unit investment cost for 1970, 1975, an d
1977 . In that period, the unit investment cost of capacity rose from 251 ruble s
to 378 .5 rubles, at a rate of 6 percent per year ; the unit cost of thermal
-9 electric power rose from 146 to 234 rubles, and the unit cost of hydroelectri c
power fell from 412 .5 rubles to 318 rubles . There is one exception to the pattern
of rising capital costs . Although a unit of nuclear capacity was twice as costl y
as a unit of thermal capacity in 1975, the level of nuclear unit costs fel l
between 1970 and 1975 and was expected to fall still further in the estimat e
values of the 1976-80 plan . Nuclear capacity is discussed in detail later .
Since the existing capital stock series do contain implicit price inflation ,
I include an estimate of the value of capital stock at the constant prices of 197 3
in Table 7 .
Table 9 presents investment data for the period 1966-70, 1971-75 and 1976-80 .
According to these data, unit investment costs rose from 275 to 296 rubles betwee n
the Eighth and Ninth Five Year Plans and rose to 390 rubles during the Tent h
Five Year Plan (assuming that total investment in electric power was actuall y
about 19 .3 billion rubles .) This was an average rate of increase of 3 .6 percen t
per year . In these series, the calculated investment cost of all three types o f
power, non-nuclear thermal, nuclear and hydroelectric fell during the Ninth Fiv e
Year Plan and then wen up, if those sectors actually received the planned allocations .
(Since both sectors failed to meet targets, it is possible that the financing o f
investment was behind plan as well .) The authors of Teploenergetika i teplotekhnika
derive their own estimates of capital investment per kilowatt of capacity b y
correcting the data in Table 9 for a change in unfinished construction of 15 percen t
for thermal power and of 28 percent for hydroelectric power, taking account o f
10
capital initiated in the Sixties and completed in the period 1971-75 .
-10 -
Thermal
Hydroelectric
Network
Thermal heat network
1966-70
1971-7 5
154
337
56 .2
7 .5
20 4
35 5
62 . 8
9 .9
Their estimates imply a rise of 6 percent per year in the cost of therma l
electric capacity and a rise of 1 percent per year in the unit cost of hydro electric capacity .
In sum, unit capital costs seem to have been rising at 3 .3 percent pe r
year, based on the constant price capital stock data and 3 .6 to 6 percen t
based on the investment data . But the measured cost of nuclear power appear s
to be falling . Still, the shift toward nuclear and hydroelectric capacity i s
a factor in the over-all rise in unit investment costs since both types o f
capacity are more capital-intensive than traditional turbine plants .
If real capital stock has been growing less rapidly than we thought, the n
conventional measures of capital productivity are better than we thought previously .
Perhaps the most important implication of these numbers is that Alec Nove i s
right--at least in the case of this sector . The actual level of real capital formatio n
did fall in the last Five Year Plan, which must be a major factor in the declinin g
rate of growth .
-11 One consequence of the delay was the still-rising level of consumption o f
mazut by thermal electric plants . 1 1
Nominally, cost was not a factor in the disappointing performance . Delay s
were ascribed variously to delayed documentation from the project-making organizations ,
underfulfillment of construction plans, and lags in the production of reactor unit s
and turbine generators . Lags in equipment deliveries, in turn, followed fro m
delays in the completion of manufacturing capacity . For example, the Atommas h
plant at Volgodonsk, which has responsibility for the supply of the VVER-100 0
megawatt reactor, was only half completed at the end of 1980 . The Rovno nuclea r
plant in Kuznetsovsk in the Western Ukraine, slated to receive a VVER-100 0
reactor, installed a VVER-440 reactor as its first unit instead . An alarme d
report in Pravda on July 11, 1981 describes the situation at Volgodonsk in som e
detail as follows : (in paraphrase) the Volgodonsk plant is responsible fo r
the supply of eight 1000 megawatt reactors during the coming Five Year Pla n
(one-third of the total new nuclear capacity .) But the plant is short 400 workers ,
and worker turnover is high . Construction of everything in Volgodonsk is behin d
schedule . The plant itself is only half finished . In Volgodonsk, a city o f
150,000 people, there are facilities for only 26,000 . Pre-school and schoo l
needs are only two-thirds met, even on a double shift . Construction of facilitie s
in Volgodonsk requires 120 to 150 million rubles a year, but the Ministry o f
Power and Electrification has allocated only 85 million annually for this purpose .
The Ministry of Heavy Industry and Specialized Construction and the Ministry o f
the Food Industry are doing nothing . The Atommash factory has assigned 1500 o f
its own personnel to city construction, paying them the difference between th e
earnings of a construction worker and their 200-ruble monthly wage .
-12 Table 11 presents the estimate values of capital costs for several of th e
large nuclear power facilities, Chernoby l ' , Smolensk, Kursk, Kola, Armenia, an d
Beloyarsk . These, like other Soviet capital values are
costs " ; they make no calculation for interest foregone during construction .
For the 8 .6 million kilowatts of capacity represented by those plants, th e
estimate value of unit capital cost was 213 .8 rubles per kilowatt . The tota l
capital investment of 18 .4 billion rubles in these plant consisted of 7 .4 7
billion allocated to construction and assembly and 10 .9 billion allocated t o
machinery and equipment .
Table 12 presents the 1970 estimate values for individual units of capacit y
installed at Novovoronezh between 1964 and 1980 . These estimate costs projec t
costs of 127 rubles as the unit capital costs of the VVER-440 and 130 ruble s
for the VVER-1000 .
estimated to have a unit cost of 235 rubles a unit, a difference that seems
large, even in view of the remoteness of the Kola site . In 1975, Sheles t
12
estimated that the VVER-1000 had a unit capital cost of 170-200 rubles .
So
-13 -
Prior to 1970
1971-75
1976-80
Average Cos t
(rubles )
269 . 8
225 . 6
20 1
2666
213
How badly do the estimate values of nuclear capital stock deviate fro m
current book values? One measure is the comparison with total investment in th e
nuclear power sector between 1966 and 1980 .
Prior to 1970
1971-75
1976-80
Capital Investment
(mil . rubles)
396
1760
4420
6576
52 6
Clearly, the total value of investment exceeds the estimate value of capita l
created by 3910 million rubles . It is two and one-half times larger . Th e
difference probably consists of three parts : partly completed capacity ,
possible understatement of true capital cost of generating facilities, an d
investment in the nuclear power industry other than power plant . Can we pu t
values on these items? Probably not, but there is additional informatio n
available . The value of unfinished construction in electric power is 5,51 8
in 1979 ; it was about 5711 in 1980 . Nuclear capacity constituted 16 percen t
of total capacity in electric power last year . It was planned to be 34 .5 percen t
of new capacity during the coming Five Year Plan . So we can estimate tha t
unfinished nuclear capacity amounted to 883 - 1904 million rubles . Using th e
mid-point of those two numbers as the approximate value of unfinished construction ,
we can estimate the amount of past investment in the nuclear sector to b e
6576 less 1393, or about 5183 million rubles . This value would imply a uni t
-14 capital cost of 286 rubles per kilowatt for the cost of past capital .
Finally, in Tables 13-16 we have the estimate values of capital cost s
used in drawing up the new Five Year Plan . Using the estimated values o f
unit capital cost of nuclear power in Table 13, we find that, at curren t
estimate values, existing nuclear facilities would be worth about 4420 millio n
rubles, or about 66 percent more than historical estimate costs .
-15 Five Year Plan . It would require a shift of resources away from othe r
sectors towards electric power .
In sum, what have I learned in this investigation? First, the cost of powe r
capacity has been increasing at an annual rate of at least 3 .3 percent per year .
Secondly, the amount of real capital investment in electric power actually fel l
during the Tenth Five Year Plan . This factor alone is sufficient to explain th e
slow-down in the growth of that sector . If real capital investment in othe r
sectors changed in a similar manner, then investment may be playing a muc h
larger role in the current decline in Soviet growth rates than we appreciate d
heretofore . Finally, the shift toward nuclear and hydroelectric power wil l
make heavier demands on planned investment . Whether the new plans will be me t
is another whole story .
FOOTNOTE S
1.
Cohn ' s comment and Nove ' s reply appear in Soviet Studies, Vol . 33, No . 2
(April 1981), pp . 296-301 .
2.
3.
N . A . Tikhonov, " Basic Guidelines for the Economic and Social Developmen t
of the USSR in 1981-85 and in the Period up to 1990 , " Pravda, February 2 8
1981, pp . 2-4 .
4.
5.
M . Styrikovich, op
6.
7.
8.
9.
. cit ., p . 3 .
TABLE 1
Total
1295
(1293)
1114 .5
CAPACITY
(mil . kwt . )
26 7
(260 )
214 . 5
of which :
Nuclear
Non-nuclear Turbine
70 .5
1036
12 . 5
(12 .3 )
192 . 4
including :
Condenser KES
694 est
118 . 4
342 est
74
Non-turbine (Diesel)
Hydroelectric stations
8
177 .5
9. 6
52 . 5
of whic h
TETS
(Lower output and capacity numbers in parentheses are used in later article s
in Elektricheskie stantsii . )
Sources : " Itogi razvitiia elektroenergetiki za 1980 godu i zadachi na 1981, "
Elektricheskie stantsii, January , 1981, pp . 2-4, " Razvitie elektroenergetik i
v odinnadtsatoi piatiletke, " Elektricheskie stantsii, May, 1981, pp 2-5 .
TABLE 2
OUTPU T
(bil . kwh .)
1970
1975
1980P
USSR
740 .9
1038 .0
1295
RSFSR
470 .2
639 .9
Ukraine
137 .6
Belorussia
1980
CAPACITY
(mil . kwt . )
1970
197 5
166 .2
217 . 2
801 .2
105 .1
132 . 5
194 .5
237 .9
27 .9
38 . 2
15 .1
26 .7
33 .4
3 .7
5. 6
Uzbekistan
18 .3
33 .6
31 .5
4 .7
6. 7
Kazakhstan
34 .8
52 .4
67 .8
8 .8
11 . 5
9 .0
11 .6
14 .6
2 .1
128 . 6
12 .0
14 .6
15
2 .7
3. 0
Lithuania
7 .4
9 .0
11 .3
1 .5
2. 1
Moldavia
7 .6
13 .7
15 .4
1 .7
2. 3
Latvia
2 .7
2 .9
4 .4
1 .2
1.6
Kirgizia
3 .5
4 .3
9 .0
1 .0
2. 3
Tadzhikistan
3 .2
4 .6
14 .4
0 .8
1.8
Armenia
6 .1
9 .1
13 .4
1 .7
2. 5
Turkmen
1 .8
4 .4
6 .8
0 .7
1. 2
Estonia
11 .6
16 .7
18 .9
2 .6
3. 2
Georgia
Azerbaidzhan
Source :
Teploenergetika i teplotekhnika .
Moscow :
Energiia,
1980, pp .
60-61
TABLE 3
1971-75
1976-80 Plan
1976-80
1981-85 Pla n
Total
57 .5
71 .0
49 .5
71
44 .6
43 .7
34
34
Condenser
31 .2
24 .9
15 . 7
TETS
13 .4
16 .3
14 . 2
Nuclear
3 .8
13 .8
7 .8
Hydro electric
9 .1
13 .5
incl .
12
24-2 5
12
TABLE 4
January 1
of Year
Soviet Official
1950
1951
1952
1953
1954
1955
1956
1957
1958
1959
1960
1961
1962
1963
1964
1965
1966
1967
1968
1969
1970
1971
1972
1973
2 .5
2 .8
3 .3
3 .7
4 .4
5 .3
6 .4
7 .9
8 .8
9 .1
9 .5
11 .9
13 .3
14 .9
17 .6
19 .9
22 .8
24 .6
26 .9
30 .0
32 .9
36 .1
40 .2
43 .5
Campbell
2 .8
4 .3
5 .1
6 .0
7 .4
8 .2
9 .3
9 .5
12 .3
13 .4
15 .0
17 .7
20 .2
22 .8
25 .3
27 .4
30 .7
33 .4
36 .9
40 .7
44 .0
Implied Price *
(Rubles )
12 7
12 7
13 1
12 9
13 4
14 2
14 7
16 3
16 4
153 . 5
160 . 8
17 8
17 9
18 1
18 9
19 2
19 8
20 0
20 4
210 . 5
21 4
21 7
23 1
Soviet official series are estimated from the share of electric power in tota l
industrial capital stock times productive fixed capital in industry (January 1
of each year, constant prices of 1960 .) Campbell series are from : Rober t
Campbell, Trends in the Soviet Oil and Gas Industry, Baltimore : Johns Hopkins ,
1975 and Robert Campbell, Basic Data on Soviet Energy Branches, Rand ,
December 1979 .
* Implied price is estimated as the value of capital stock per unit of capacity .
TABLE 5
*
End of Year
1957
1958
1959
1960
1961
1962
1963
1964
1965
1966
1967
1968
1969
1970
1971
1972
1973
1974
1975
1976
1977
1978
1979
Soviet Official
44 .37
48 .79
52 .70
56 .09
59 .94
64 .60
68 .59
72 .98
77 .76
82 .24
Cohn Estimates
9. 8
11 . 6
13 . 4
15 . 8
18 . 7
20 . 7
22 . 8
25 . 2
27 . 5
30 . 3
33 . 4
37 . 1
40 .9
45 .0
48 .6
52 . 7
56 .3
59 .9
63 .9
78 .8
84 .6
Implied Pric e
(Rubles )
265 . 9
267 . 0
278 . 2
286 . 8
291 . 8
297 . 0
300 . 0
306 . 9
316 . 8
322 .2
Soviet official series are estimated from the share of electric power in tota l
industrial capital stock times productive fixed capital in industry (end o f
year, constant prices of 1973 .) Cohn series are unpublished estimates provide d
by the author .
* Implied price is estimated as the value of capital stock per unit of capacity .
TABLE 6
Hydro
Thermal
Incl .
Nuclea r
Nuclear*
Network
Othe r
1970
35 .0
210 r
6 .6
210 r
14 .0
104 r
.24
270 r
12 .9
.029 r
1.5
1975
54 .0
248 r
9 .6
237 r
21 .5
121 .5r
1 .10
226 r
20 .1
.033 r
2.8
1980P
76 .6
287 r
13 .7
261 r
28 .1
137 r
2 .69
201 r
26 .6
.035 r
8.2
Source :
Teploenergetika i teplotekhnika . Moscow : Energiia, 1980 ; slightl y
different figures are also in Energetika SSSR v 1976-80 godakh . Moscow :
Energiia, 1977 .
* Thornton estimates described later .
TABLE 7
End of Year
Capacity
Capital Stoc k
(Million kilowatts) (Billion rubles )
1955
37 .246
10 . 7
1960
66 .721
19 . 1
1965
115 .033
33 . 0
1970
166 .150
47 . 7
1971
175 .365
50 . 3
1972
186 .239
53 . 4
1973
195 .560
56 . 1
1974
205 .442
58 . 9
1975
217 .484
62 . 4
1976
228 .307
65 . 5
1977
237 .805
68 . 2
1978
245 .441
70 . 4
1979
255 .282
73 . 2
1980
267*
76 . 6
Source :
Capacity and 1973 Capital Stock from Narodnoye Khoziaistvo ,
various years . Other capital stock figures estimated using th e
constant price of capital of 1973 .
* 1980 capacity from Elektricheskie stantsii, May 1981 .
TABLE 8
Total
196 0
Investment
(Million Rubles )
New Capacity
(Million Kwt . )
Implied Cost
(Rubles )
197 0
Investment
(Million Rubles )
New Capacity
(Million Kwt . )
Implied Cost
197 5
Investment
(Million Rubles )
New Capacity
(Million Kwt . )
Implied Cost
(Rubles )
197 7
Investment
(Million Rubles )
New Capacity
(Million Kwt . )
Implied Cost
(Rubles )
Thermal
Incl .
Nuclea r
Hydro
Network*
Othe r
1551 .5
713 .7
657 .8
18 0
168 7
7 .4 5
19 9
3103
12 .36
251
3747
12 .0
312
3596
9 .5
378 .5
10 .64
146
1888 .5
8 .5
222
1729 .7
7 .4
234
1 .73
412 .5
704
3 .54
31 . 8
.020 7
798
34 . 7
199
.023 0
665
791
2 .1
318
35 6
40 6
31 . 9
24 8
TABLE 9
Sector
1966-70
1971-7 5
1976-8 0
22
26
17
57 . 5
295 .7
21 *
49 . 5
39 0
7 .04
41 . 2
17 1
7 .5 4
34
22 2
Nuclea r
New Capacit y
Implie d Cost
695
1 .7 6
3. 8
46 3
4 .4 2
7. 8
56 7
Hydr o
New Capacity
Implied Cost
3 .0 6
8 .4
364
3 .1 9
9. 1
35 0
4 .1 6
12
34 6
5 .85
7 .15
6 .7 6
Heat Transmission
.40
.66
.7 0
Other
.45
Electric Investment 17 . 2
All Industrie s
Other Industries
Electric Powe r
New Capacit y
Implied Cost
Network
Source :
3 .5
14 .0
51
274 .5
.39 6
.57
Teploenergetika i teplotekhnika .
2 .2
Moscow :
2 .4 2
TABLE 1 0
NUCLEAR POWER OUTPUT AND CAPACITY
1964
1965
1966
1967
1968
1969
1970
1971
1972
1973
1974
1975
1976
1977
1978
1979
1980
CAPACIT Y
(Mil . Kwt .)
OUTPUT
(Bil . KWH )
.3
.3
.3
.5
.5
.9
.9
1 .3
1 .8
3 .2
3 .7
4 .7
6 .1
7 .1
8 .1
9.6
12 .5*
. 1
1.4
1.7
1.8
2.9
2.3
3. 7
3. 9
7.3
11 . 7
18 . 0
20 . 2
25 . 0
34 . 0
45
70 .5
TABLE 1 1
Nuclear Plant s
Chernobyl'
Smolensk
Kursk
Kola
RBMK-1000
RBMK-1000
RBMK-1000
2000
500
379 .9
155 .7
224 .2
19 0
2000
500
396 .6
166 .7
229 .9
198 . 5
2000
500
349 .4
153 .2
196 .2
17 5
440/
22 0
440/
22 0
100
206 .7
105 .8
100 .9
23 5
159 .74
262 . 5
179
332 . 5
VVER-440
880
Armenia VVER-405,410
815
Beloyarsk AMB-100,200
BN-600
900
205 .64
299 .1
45 .9
120 .1
Source :
Stroitel ' stvo teplovykh j atomnvkh elektrostantsii, Moscow : Stroiizdat ,
1979, p . 894 .
TABLE 1 2
ESTIMATE VALUES OF CAPITAL COSTS FOR NOVOVORONEZH NUCLEAR POWE R
Unit
Capacit y
(Megawatts)
Unit Capita l
Cos t
(Rubles)
Implied Tota l
Cos t
(Mil . Rubles )
-1
210
326
68 .46
-2
365
186
67 .89
-3
440
127 (235)
55 .88 (103 .4 )
-4
440
127 (235)
55 .88 (103 .4 )
-5
1000
130 (200)
Source :
130 .
(200 . )
TABLE 1 3
4400
0 .2
0. 1
Cente r
24 0
6700
0 .36 4
Ural s
25 0
6700
0 .37 9
Siberi a
27 0
6700
0 .41 0
Siberi a
Nuclea r
GRES, ga s
Cente r
12 5
313
6700
0 .20 1
Surgu t
16 5
313
6700
0 .26 6
14 0
339
6700
0 .23 0
16 0
328
6700
Cente r
15 0
323
6700
0 .24 5
Ural s
15 0
323
6700
0 .245
0.263
TABLE 1 4
Source
Capital Investment
Per Unit of Capacity
(rubles/kwt)
Hydroelectri c
in Siberia
498 .7
0 .355
1 .4 6
Nuclea r
in the Center
380
0 .697
1 .1 5
GRES, gas-fire d
in the Center
328
0 .854
1 .0 8
407
0 .753
1 .3 2
374 .8
0 .624
1 .2 2
389 .5
0 .672
1 .2 8
343 .5
1 .075
1 .35
in Surgut
GRES, coal-fire d
in Ekibastuz
in Kansk-Achinsk basin
GRES, Kuznets coa l
in Center
TABLE 1 5
Capital Investmen t
Per Unit o f
Capacit y
(rubles/kwt)
Hydroelectri c
in Siberia
466 .5
0 .331
1 .3 8
Nuclea r
in the Urals
391 .5
0 .709
1 .1 9
GRES, ga s
in Surgut
324 .9
0 .654
1 .0 8
GRES, coa l
in Ekibastuz
287 .0
0 .520
0 .9 6
0 .630
1 .1 8
0 .744
1 .02
Source
274 .5
Source : A . A . Trotskii, USSR Gosplan, " Basic Trends in Electrical Energy Developmen t
under Conditions of the Future Fuel Balance , " Elektricheskie stantsii, December 1978 ,
pp . 1-18 .
TABLE 1 6
4
Capital Investmen t
Per Unit of Capacit y
Total Cos t
of Outpu t
(rubles/kwt)
Operating Cos t
of Outpu t
(Sebestoimost ' )
(kopeks/kwh)
Hydroelectri c
in Siberia
300
0 .100
0 .9 2
Nuclea r
in Siberia
413
0 .740
1 .2 5
GRES,coa l
in Ekibastuz
278 .2
0 .508
0 .9 3
0 .443
0 .74
(kopeks/kwh )