JU UNIVERZITET U TUZLI

Rudarsko-Geoloko-Graevinski fakultet
Graevinski odsjek
Organizacija Graenja
Analiza cijena

1.Izrada drvene ograde,izrada ograde od ianog pletiva sa stubovima 14x14


cm,obraun po m2
100 103 2.1
GN
440303
Izrada:
Potrebna radna snaga:
-T V
0,32 h x 3,6 KM/h=1,15 KM
-T IV
0,16 h x 3,4 KM/h=0,54 KM
UKUPNO Eid................................................................................................. =1,69 KM
Potreban graevinski materijal:
-Gredice 14x14
0,018m 3 x 300KM/m3=5,4KM
-Gredice 8x10cm
0,014 m 3 x 300KM/m3=4,2KM
-Ekseri
0,05kg x 2KM/kg=0,10KM
-Karbolineum
0,10kg x 1KM/kg=0,10KM
-Mrea od ice
1,05m 2x2KM/m2=2,10KM
UKUPNO Em......................................................................................... .......=11,90 KM

CP=Em+Eid x k
Cizrada drvene ograde=11,90+1,69 x 3,5=17,82 KM/m2

2. Izrada prelaznog puta od tucanika sa podlogom od lomljenog


kamena,obraun po m2
100 106
GN
440601
Izrada:
Potrebna radna snaga:
-M VII
0,05 h x 4,0 KM/h=0,20 KM
-M VI
0,05 h x 3,8 KM/h=0,19 KM
-R IV
0,54 h x 3,4 KM/h=1,84 KM
-R III
0,11 h x 3,2 KM/h=0,35 KM
UKUPNO Eid................................................................................................. =2,58 KM

Potreban graevinski materijal:


-Tucanik
0,22m 3 x 30KM/m3=6,6KM
-Sitni kamen
0,033 m 3 x 30KM/m3=0,99KM
-Spojni materijal
0,011 m 3 x 30KM/ m3=0,33KM
-Voda
0,05 m 3 x 1,0KM /m3=0,050KM
-Nafta
0,296kg x2,0KM/kg=0,592KM
-Benzin
0,007kgx2,0KM/kg=0,0140KM
-Mainsko Ulje
0,0058kgx5KM/kg=0,029KM
-Tovatna mast
0,0023kgx5KM/kg=0,0012KM
UKUPNO Em.............................................................. ......................... ..........=8,61 KM

CP=Em+Eid x k
Cizrada prilaznog puta=8,61+2,58 x 3,5=17,64 KM/m2

3. Izrada Vodovodne mree na gradilitu,montaa pocinkovanih cijevi


3/4,obraun po m
100 107
GN
440703

Montaa cijevi 3/4:


Potrebna radna snaga:
-M VI
0,28 h x 3,8 KM/h=1,06 KM
-M V
0,029 h x 3,6 KM/h=0,10 KM
-M IV
0,31 h x 3,4 KM/h=1,05 KM
-M III
0,02 h x 3,2 KM/h=0,06 KM
UKUPNO Eid................................................................................................. =2,27 KM
Potreban graevinski materijal:
-Kudelja
0,07 kg x 1,0KM/kg=0,07KM
-MUF 1/2
0,25kom x 2,0KM/kom=0,50KM
-Koljeno
0,15kom x 1,0KM/ kom=0,15KM
-Cijevi 3/4
1,77 kg x 1,5KM /kg=2,65KM
-MUF 1/4
0,25 kom x 2,0KM/kom=0,50KM
-Koljeno 3/4
0,15 komx 2,0 KM/kom=0,30KM
UKUPNO Em.............................................................. ......................... ..........=4,17 KM

CP=Em+Eid x k
Cizrada vodovodne mree=4,17+2,27 x 3,5=12,11 KM/m1

4. Izrada elektrine linije na gradilitu,montaa dovodne linije od mjesta


prikljuka do gradilita.Obraun po m1
100 108
GN
440802
Montaa dovodne linije:
Potrebna radna snaga:
-M III
0,50 h x 3,2 KM/h=1,6 KM
UKUPNO Eid................................................................................................. =1,60 KM

Potreban graevinski materijal:


-Izolatori
0,12 kom x 2,0KM/kom=0,24KM
-ica NC 4mm
3m x 0,6KM/kom=0,18KM
UKUPNO Em.............................................................. ......................... ..........=0,42 KM

CP=Em+Eid x k
Cizrada elektrine linije=0,42+1,60 x 3,5=6,02 KM/m1

5. Izrada Armirakog stola.Obraun po komadu.


100 108
GN
441002
Izrada armirakog stola:
Potrebna radna snaga:
-T V
8,0 h x 3,6 KM/h=28,8 KM
-T IV
2,4 h x 3,4 KM/h=8,16 KM
UKUPNO Eid............................................................................................... =36,96 KM
Potreban graevinski materijal:
-Daska 24mm
0,016 m 3x 300KM/ m3=4,8KM
-Daska 48mm
0,18 m 3x 300KM/ m3=54KM
-Obla graa
0,12 m 3x 300KM/ m3=36KM
-Gredice 12/12cm
0,028 m 3x 300KM/ m3=8,4KM
-Ekseri
0,40 kgx 2KM/ kg=0,8KM
UKUPNO Em.............................................................. ......................... .......=104,0 KM

CP=Em+Eid x k
Cizrada armirakog stola=104,00+36,96 x 3,5=233,36 KM/kom

6. Izrada poljskog klozeta.Obraun po komadu.


100 108
GN
441004
Izrada poljskog klozeta:
Potrebna radna snaga
-T IV
7,29 h x 3,4 KM/h=24,78 KM
-T III
4,63 h x 3,2 KM/h=14,82 KM
-R II
3,75 h x 3,0 KM/h=11,25 KM
UKUPNO Eid............................................................................................... =50,85 KM
Potreban graevinski materijal:
-Daska 24mm
0,198 m 3x 300KM/ m3=59,4KM
-Daska 48mm
0,168 m 3x 300KM/ m3=50,4KM
-Gredice 12/12cm
0,232 m 3x 300KM/ m3=69,6KM
-Ekseri
1,15 kgx 2KM/ kg=2,30KM
-Krovna Hartija
2,5 m 3x 5KM/ m3=12,5KM
-Reza
1,0 komx 5KM/ k0m=5,0KM
-arke
2,0 komx 7KM/ kom=14KM
UKUPNO Em.............................................................. ......................... .....=213,20 KM
CP=Em+Eid x k
Cizrada poljskog klozeta=213,20+50,85 x 3,5=391,17 KM/kom

7. Runo kopanje zemlje u irokom otkopu III kategorije u prirodno vlanom


zemljitu.Obraun po m3
200 101
GN
020103
Potrebna radna snaga
-R II
2,00 h x 3,0 KM/h=6,00 KM
UKUPNO Eid............................................................................................... =6,00 KM
CP=Em+Eid x k
Ciroki otkop=0+6 x 3,5=21,5 KM/m

8.Runo kopanje zemljita za kanalske rovove ili temelje objekta 0,6-1m u


prirodno vlanom zemljitu dubine 0-2m III kategorije.Obraun po m3
200 103
GN
020809
Potrebna radna snaga
-R II
3,00 h x 3,0 KM/h=9,00 KM
UKUPNO Eid............................................................................................... =9,00 KM
CP=Em+Eid x k
Ciskop trakastih temelja=0+9 x 3,5=31,5 KM/m3

9.Razastiranje i nabijanje kamenog materijala (ljunka) u slojevima debljine


10cm.Obraun po m2
200 203
GN
021103

Razastiranje materijala
Potrebna radna snaga
-R II
0,36 h x 3,0 KM/h=1,08 KM
UKUPNO Eid............................................................................................... =1,08 KM
Potreban graevinski materijal:
-ljunak prirodni
0,1 m 3x 30KM/ m3=3,0KM
UKUPNO Em.............................................................. ............................... .....=3,0 KM
CP=Em+Eid x k
Crazastiranja materijala=3+1,08 x 3,5=6,78 KM/m2
Nabijanje materijala
GN

200 203
020902

Potrebna radna snaga


-R II
1,00 h x 3,0 KM/h=3,00 KM
UKUPNO Eid............................................................................................... =3,00 KM
CP=Em+Eid x k
Cnabijanje materijala=0+3,0 x 3,5=10,5 KM/m3
Ukupna cijena:
Crazastiranja i nabijanje materijala=6,78/0,10+10,50=67,8+10,50=78,3 KM/m3
Crazastiranja i nabijanje materijala=6,78+10,50x0,10=6,78+1,050=7,83 KM/m2

10.Razastiranje i nabijanje zemljanog materijala iznad temeljnih traka.Obraun


po m3.

Nasipanje i nabijanje materijala


GN

200 203
020902

Potrebna radna snaga


-R II
1,00 h x 3,0 KM/h=3,00 KM
UKUPNO Eid............................................................................................... =3,00 KM
Cnabijanje

materijala

=0+3,0 x 3,5=10,5 KM/m3

11. Razastiranje i nabijanje zemljanog materijala ispod podne ploe .Obraun


po m2.
200 203
GN
021105
Razastiranje materijala
Potrebna radna snaga
-R II
0,42 h x 3,0 KM/h=1,26 KM
UKUPNO Eid............................................................................................... =1,26 KM
Potreban graevinski materijal:
-ljunak prirodni
0,15 m 3x 30KM/ m3=4,5KM
UKUPNO Em.............................................................. ............................... .....=4,5 KM
CP=Em+Eid x k
Crazastiranja materijala=4,5+1,26 x 3,5=8,91 KM/m2
Nabijanje materijala
GN

200 203
020902

Potrebna radna snaga


-R II
1,00 h x 3,0 KM/h=3,00 KM
UKUPNO Eid............................................................................................... =3,00 KM
CP=Em+Eid x k
Cnabijanje materijala=0+3,0 x 3,5=10,5 KM/m3
Ukupna cijena:
Crazastiranja i nabijanje materijala=8,91/0,10+10,50=89,1+10,50=99,6 KM/m3
Crazastiranja i nabijanje materijala=8,91+10,50x0,10=8,91+1,05=9,96 KM/m2

GN

400 309
151007

12.Runo betoniranje trakastih temelja betonom MB 30.Obraun


3

po m .

Spravljanje:
Potrebna radna snaga
-R II
1,73 h x 3,0 KM/h=5,19 KM
UKUPNO Eid............................................................................................... =5,19 KM
Ugraivanje materijala
Potrebna radna snaga
-B IV
1,08 h x 3,2 KM/h=3,45 KM
-R II
1,08 h x 3,0 KM/h=3,24 KM
UKUPNO Eid............................................................................................... =6,69 KM
Spravljanje:
Potrebna radna snaga
-R II
2,35 h x 3,0 KM/h=7,05 KM
UKUPNO Eid............................................................................................... =5,19 KM
Materijal:
400 202
GN
150168

Potreban graevinski materijal:


-Cement PC 350
350 kgx 0,3KM/ kg=105,00KM
-ljunak granulisani
0,53 m 3x 30KM/ m3=15,9KM
- ljunak granulisani
0,72 m 3x 30KM/ m3=21,6KM
-Voda
0,2 m3x 1KM/ m3kom=0,2KM
UKUPNO Em.............................................................. ......................... .....=142,7 KM

CP=Em+Eid x k
Cbetoniranje trakastih temelja=142,7+(5,19+6,69+5,19) x 3,5=202,45 KM/m3

13.Betoniranje temeljnog sokla betonom MB 30 u potrebnoj oplati.Obraun po


m3.
Spravljanje betona:
400 202
GN
150168

Potrebna radna snaga


-R II
2,24 h x 3,0 KM/h=6,72 KM
UKUPNO Eid............................................................................................... =6,72 KM
Potreban graevinski materijal:
-Cement
350 kgx 0,3KM/ kg=105,00KM
-ljunak granulisani
0,53 m 3x 30KM/ m3=15,9KM
- ljunak granulisani
0,72 m 3x 30KM/ m3=21,6KM
-Voda
0,2 m3x 1KM/ m3kom=0,2KM
UKUPNO Em.............................................................. ......................... .....=142,7 KM
Cspravljanje betona=142,7+6,72x 3,5=166,22 KM/m3

Ugraivanje betona:
400 308
GN
150907

Potrebna radna snaga


-B IV
1,40 h x 3,2 KM/h=4,48 KM
-R II
1,40 h x 3,0 KM/h=4,20 KM
UKUPNO Eid............................................................................................... =8,68 KM
Prijenos materijala
Potrebna radna snaga
-R II
2,35 h x 3,0 KM/h=7,05 KM
UKUPNO Eid............................................................................................... =7,05 KM
CP=Em+Eid x k
Cugraivanja=0+(8,68+7,05) x 3,5=55,05 KM/m3

GN

600 201
160402

Izrada oplate ravnih betonskih zidova od daske.Obraun po m 2.

Izrada:
Potrebna radna snaga
-T V
0,20 h x 3,6 KM/h=0,72 KM
-T III
0,20 h x 3,2 KM/h=0,64 KM
UKUPNO Eid............................................................................................... =1,36 KM
Montaa:
Potrebna radna snaga
-T V
0,18 h x 3,6 KM/h=0,648 KM
-T III
0,18 h x 3,2 KM/h=0,576 KM
UKUPNO Eid............................................................................................... =1,22 KM
Demontaa:
Potrebna radna snaga
-T III

0,07 h x 3,2 KM/h=0,224 KM

-R II
0,11 h x 3,0 KM/h=0,33 KM
UKUPNO Eid............................................................................................... =0,55 KM

ienje i vaenje eksera:


Potrebna radna snaga
-R II
0,13 h x 3,0 KM/h=0,39 KM
UKUPNO Eid............................................................................................... =0,39 KM
Potreban graevinski materijal:
-Daska 24mm
0,0047m 3 x 300KM/ m3=1,41KM
-Gredice
0,0035 m 3x 300KM/ m3=1,05KM
-ica Paljena
0,07 kgx 2,5KM/ kg=0,175KM
-Ekseri
0,15 kgx 2KM/ kg=0,30KM
-Klamfe
0,1 kgx 3KM/ kg=0,3KM
UKUPNO Em.............................................................. ......................... .....=3,23 KM
CP=Em+Eid x k
Cizrada oplate=3,23+(1,36+1,22+0,55+0,35) x 3,5=15,41 KM/m2
1m3 betona/0,25m=4m2 oplate na 1m3 betona
Za izradu 1m3 betona potrebno je 4m2 oplate sa jedne strane, sa dvije je to 8m2
Cizrada oplate za 1m3=15,56 KM/m2x8m2=124,48 KM

Cbetoniranje skolenog zida= Cspravljanje betona+ Cugraivanje betona+ Coplate=


Cbetoniranje skolenog zida=166,22+55,05+124,48 =345,75 KM
14.Betoniranje ab podne ploe betonom MB 30.Obraun po m3.
Spravljanje betona:
400 202
GN
150168

Potrebna radna snaga


-R II
2,24 h x 3,0 KM/h=6,72 KM
UKUPNO Eid............................................................................................... =6,72 KM
Potreban graevinski materijal:
-Cement
-ljunak granulisani

350 kgx 0,3KM/ kg=105,00KM


0,53 m 3x 30KM/ m3=15,9KM

- ljunak granulisani
0,72 m 3x 30KM/ m3=21,6KM
-Voda
0,2 m3x 1KM/ m3kom=0,2KM
UKUPNO Em.............................................................. ......................... .....=142,7 KM
Cspravljanje betona=142,7+6,72x 3,5=166,22 KM/m3
Ugraivanje betona:
400 308
GN
150907

Potrebna radna snaga


-B IV
1,40 h x 3,2 KM/h=4,48 KM
-R II
1,40 h x 3,0 KM/h=4,20 KM
UKUPNO Eid............................................................................................... =8,68 KM
Prijenos materijala
Potrebna radna snaga
-R II
2,35 h x 3,0 KM/h=7,05 KM
UKUPNO Eid............................................................................................... =7,05 KM
CP=Em+Eid x k
Cugraivanja=0+(8,68+7,05) x 3,5=55,05 KM/m3

Cbetoniranje podne ploe= Cspravljanje betona+ Cugradnja betona=166,22+55,05=221,27 KM/m3

16.Betoniranje trotoara oko objekta betonom MB 15.Obraun po m 3.


400 901
GN
158001
Spravljanje maltera:
Potrebna radna snaga
-R II
0,15 h x 3,0 KM/h=0,45 KM
UKUPNO Eid............................................................................................... =0,45 KM

Prijenos betona:
Potrebna radna snaga

-R II
0,14 h x 3,0 KM/h=0,42 KM
UKUPNO Eid............................................................................................... =0,42 KM
Ugraivanje,zalivanje fugni i postavljanje gredica:
Potrebna radna snaga
-B IV
0,22 h x 3,4 KM/h=0,75 KM
-B III
0,31 h x 3,2 KM/h=0,99 KM
-T V
0,19 h x 3,6 KM/h=0,68 KM
UKUPNO Eid............................................................................................... =2,42 KM
Izrada kouljice:
Potrebna radna snaga
-Z VI
0,48 h x 3,8 KM/h=1,82 KM
UKUPNO Eid............................................................................................... =1,82 KM
Prijenos materijala:
Potrebna radna snaga
-R II
0,12 h x 3,0 KM/h=0,36 KM
UKUPNO Eid............................................................................................... =0,36 KM

Potreban graevinski materijal:


-Beton 15Mpa
-Cementni malter 1:3
-Bitumen
-Gredice 5x8
-Drvo ogrevno
-Ekseri

0,08 m 3x
0,02m 3x
0,60 kgx
0,004 m 3x
0,50 kgx
0,02 kgx

Cijena Betona 15Mpa:


-Cement Mp 35
250 kgx 0,3KM/ kg=75,00KM
-ljunak prirodni
1,18 m 3x 30KM/ m3=35,4KM
-Voda
0,16 m3x 1KM/ m3kom=0,16KM
UKUPNO Em.............................................................. ......................... .....=110,56 KM
Cijena Cementnog malera 1:3:
-Cement PC 250
470 kgx 0,3KM/ kg=141,00KM
-Pijesak
1,01 m 3x 30KM/ m3=30,3KM
-Voda
0,35 m3x 1KM/ m3kom=0,35KM
UKUPNO Em.............................................................. ......................... .....=171,65 KM
-Beton 15Mpa
-Cementni malter 1:3
-Bitumen

0,08 m 3x 110,56KM/ m3=8,84KM


0,02m 3x 171,65KM/ m3=3,43KM
0,60 kgx 5KM/ kg=3,00KM

-Gredice 5x8
0,004 m 3x 300KM/ m3=1,2KM
-Drvo ogrevno
0,50 kgx 1KM/kg=0,5KM
-Ekseri
0,02 kgx 3KM/kg=0,06KM
UKUPNO Em.............................................................. ......................... .....=16,67 KM
Cizrada trotoara=16,67+(0,45+0,42+2,42+1,82+0,36) x 3,5= 35,81KM/m2

17. Betoniranje AB stubova, serklaa , nadvratnika i nadprozornika betonom


MB 30 u odgovarajuoj oplati.Obraun po m3.
GN

400 401
151407

Spravljanje betona:
Potrebna radna snaga
-R II
1,73 h x 3,0 KM/h=5,19 KM
UKUPNO Eid............................................................................................... =5,19 KM

Ugraivanje betona:
Potrebna radna snaga
-B VI
2,40 h x 3,8 KM/h=9,12 KM
-B III
2,40 h x 3,2 KM/h=7,68 KM
UKUPNO Eid............................................................................................... =16,8 KM
Prijenos betona:
Potrebna radna snaga
-R II
1,21 h x 3,0 KM/h=3,63 KM
UKUPNO Eid............................................................................................... =3,63 KM
Spravljanje betona:
Potrebna radna snaga
-R II
1,73 h x 3,0 KM/h=5,19 KM
UKUPNO Eid............................................................................................... =5,19 KM
Ugraivanje betona:
Potrebna radna snaga
-B VI
2,40 h x 3,8 KM/h=9,12 KM
-B III
2,40 h x 3,2 KM/h=7,68 KM
UKUPNO Eid............................................................................................... =16,8 KM
Prijenos betona:
Potrebna radna snaga
-R II
1,21 h x 3,0 KM/h=3,63 KM
UKUPNO Eid............................................................................................... =3,63 KM
Potreban graevinski materijal za izradu betona MB 30:
-Cement
350 kgx 0,3KM/ kg=105,00KM
-ljunak granulisani
0,53 m 3x 30KM/ m3=15,9KM
- ljunak granulisani
0,72 m 3x 30KM/ m3=21,6KM
-Voda
0,2 m3x 1KM/ m3kom=0,2KM
UKUPNO Em.............................................................. ......................... .....=142,7 KM
Cspravljanje betona=142,7+6,72x 3,5=166,22 KM/m3
OPLATA:
GN

601 217
161901

Izrada:
Potrebna radna snaga
-T VII
0,47 h x 4,0 KM/h=1,88 KM
-T V
0,24 h x 3,6 KM/h=0,86 KM
UKUPNO Eid............................................................................................... =2,74 KM

Montaa:
Potrebna radna snaga
-T VII
0,40 h x 4,0 KM/h=1,60 KM
-T V
0,20 h x 3,6 KM/h=0,72 KM
UKUPNO Eid............................................................................................... =2,32 KM
Demontaa:
Potrebna radna snaga
-T V
0,08 h x 3,6 KM/h=0,288 KM
UKUPNO Eid............................................................................................... =0,288 KM

ienje i vaenje eksera:


Potrebna radna snaga
-R II
0,15 h x 3,0 KM/h=0,45 KM
UKUPNO Eid............................................................................................... =0,45 KM
Potreban graevinski materijal:
-Daska 24mm
0,0057m 3 x 300KM/ m3=1,71KM
-Gredice
0,0020 m 3x 300KM/ m3=0,60KM
-Letva
0,0017 m 3x 300KM/ m3=0,51KM
-ica Paljena
0,15 kgx 2,5KM/ kg=0,375KM
-Ekseri
0,25 kgx 3KM/ kg=0,75KM
-Bunarska motka
0,10mx 1KM/ m=0,1KM
-Daska 24mm
0,0015 m 3x 300KM/ m3=0,45KM
-Ekseri
0,09 kgx 2KM/ kg=0,27KM
UKUPNO Em.............................................................. ......................... .....=4,67 KM
Coplate=4,67+(2,74+2,32+0,288+0,45) x 3,5= 24,963KM/m2

Nadvratnici i nadprozornici:
1m betona/0,25m=4m oplate na 1m3 betona
Za izradu 1m3 betona potrebno je 4m2 oplate sa jedne strane, sa tri strane je to
12m2
Cizrada oplate za 1m3=15,56 KM/m2x12m2=186,72KM
3

Cbetona izrada nadvratnika i nadprozornik sa oplatom= 168,32+186,72=355,04


=355,04 KM/m3
Stubovi:
Potrebno je 75,23 m oplate za izradu Stubova
Potrebno je 6,14 m3 Betona za izradu Stubova
2

Cbetoniranja stubova = 168,32+25,05 x 75,23/6,14=475,24


=475,24 KM/m3
Horizontalni serklai
OPLATA:
GN

601 202
160504

Izrada:
Potrebna radna snaga
-R VII
0,11 h x 4,0 KM/h=0,44 KM
-R V
0,11 h x 3,6 KM/h=0,39 KM
UKUPNO Eid............................................................................................... =0,85 KM
Montaa:
Potrebna radna snaga
-R VII
0,11 h x 4,0 KM/h=0,44 KM
-R V
0,11 h x 3,6 KM/h=0,40 KM
UKUPNO Eid............................................................................................... =0,84 KM
Demontaa:
Potrebna radna snaga
-R III
0,04 h x 3,2 KM/h=0,128 KM
-R II
0,04 h x 3,0 KM/h=0,12 KM
UKUPNO Eid............................................................................................... =0,248 KM

ienje i vaenje eksera:


Potrebna radna snaga
-R II
0,04 h x 3,0 KM/h=0,12 KM
UKUPNO Eid............................................................................................... =0,12 KM
Potreban graevinski materijal:
-Daska 24mm
0,0084m 3 x 300KM/ m3=2,52KM
-ica Paljena
0,10 kgx 2,5KM/ kg=0,25KM
-Ekseri
0,25 kgx 3KM/ kg=0,75KM
UKUPNO Em.............................................................. ......................... .....=3,52 KM
Coplate=3,52+(0,85+0,84+0,248+0,12) x 3,5= 10,72KM/m1
Duina Serklaa je 164,9m
Potrebno je 9,80 m3 betona

164,9
9,80
Cbetona izrada hor.serklaa sa oplatom= 168,32+10,72x

=348,70 KM/m3

18.Betoniranje ab ploe iznad prizemlja u odgovarajuoj oplati betonom MB


30.Obraun po m3.
400 701
GN
156213
Spravljanje betona:
Potrebna radna snaga
-R II

0,21 h x 3,0 KM/h=0,63 KM

UKUPNO Eid...............................................................................................

=0,63 KM

Ugraivanje betona:
Potrebna radna snaga
-B VI
0,35 h x 3,8 KM/h=1,33 KM
-B III
0,35 h x 3,2 KM/h=1,12 KM
UKUPNO Eid............................................................................................... =2,45 KM
Prijenos betona:
Potrebna radna snaga
-R II
0,18 h x 3,0 KM/h=0,54 KM
UKUPNO Eid............................................................................................... =0,54 KM
Potreban graevinski materijal:
-Beton MB 30

0,12 m 3x

Potreban graevinski materijal za spravljanje 1m 3 betona MB 30


-Cement
350 kgx 0,3KM/ kg=105,00KM
-ljunak granulisani
0,53 m 3x 30KM/ m3=15,9KM
- ljunak granulisani
0,72 m 3x 30KM/ m3=21,6KM
-Voda
0,2 m3x 1KM/ m3kom=0,2KM
UKUPNO Em.............................................................. ......................... .....=142,7 KM
Cspravljanje betona=142,7+6,72x 3,5=166,22 KM/m3
Potreban graevinski materijal:
-Beton MB 30

0,12 m 3x142,7KM/m3=17,12KM

Cm2 izbetonirane ploe bez opolate =17,12+(0,63+2,45+0,54)x 3,5=29,97 KM/m 2


Oplata za plou:
GN

601 204
160701

Izrada:
Potrebna radna snaga
-T V
0,24 h x 3,6 KM/h=0,86 KM
-T III
0,24 h x 3,2 KM/h=0,768 KM
UKUPNO Eid............................................................................................... =1,628 KM
Montaa:

Potrebna radna snaga


-T V
0,25 h x 3,6 KM/h=0,90 KM
-T III
0,25 h x 3,2KM/h=0,80 KM
UKUPNO Eid............................................................................................... =1,70 KM
Demontaa:
Potrebna radna snaga
-T III
0,18 h x 3,2 KM/h=0,576 KM
UKUPNO Eid............................................................................................... =0,576 KM

ienje i vaenje eksera:


Potrebna radna snaga
-R II
0,14 h x 3,0 KM/h=0,42 KM
UKUPNO Eid............................................................................................... =0,42 KM
Potreban graevinski materijal:
-Daska 24mm
0,004m 3 x 300KM/ m3=1,20KM
-Gredice
0,0020 m 3x 300KM/ m3=0,60KM
-Ekseri
0,06 kgx 3KM/ kg=0,18KM
-Bunarska motka
0,25mx 1KM/ m=0,25KM
-Daska 24mm
0,0007 m 3x 300KM/ m3=0,21KM
-Ekseri
0,09 kgx 3KM/ kg=0,27KM
UKUPNO Em.............................................................. ......................... .....=2,71 KM
Coplate po m2=2,71+(1,628+1,7+0,576+0,42) x 3,5=17,84KM/m2
Potrebna koliina oplate za betoniranje ploe iznad prizemlja je 110,54 m 2 oplate
Ukupna koliina oplate za plou na objektu je 160,12 m 2 oplate
Potrebna koliina oplate na 1m3 betona je 1,0/0,12=8,33m 2 oplate
Cijena oplate po m2 ploe: Coplate=0,69x17,84= 12,31 KM/m2
Coplate po m3=17,84KM/m2x8,33m2/m3=148,60KM/m3
Potrebna koliina betona je:
0,12m 3x148,60KM/m3=17,83KM
Cm2 izbetonirane ploe sa oplatom =29,97+17,83=47,80 KM/m2

19.Betoniranje unutranjeg ab stepenita zajedno sa stepenicama betonom MB


30 u odgovarajuoj oplati .Obraun po m3.
400 407
GN
152007
Spravljanje betona:
Potrebna radna snaga

-R II
1,73 h x 3,0 KM/h=5,19 KM
UKUPNO Eid............................................................................................... =5,19 KM
Ugraivanje betona:
Potrebna radna snaga
-B IV
1,40 h x 3,6 KM/h=5,04 KM
-B II
1,40 h x 3,0 KM/h=4,20 KM
UKUPNO Eid............................................................................................... =9,60 KM
Prijenos betona:
Potrebna radna snaga
-R II
1,21 h x 3,0 KM/h=3,63 KM
UKUPNO Eid............................................................................................... =3,63 KM
Potreban graevinski materijal:
-Beton MB 30

1,0 m 3x

Potreban graevinski materijal za spravljanje 1m 3 betona MB 30


-Cement
350 kgx 0,3KM/ kg=105,00KM
-ljunak granulisani
0,53 m 3x 30KM/ m3=15,9KM
- ljunak granulisani
0,72 m 3x 30KM/ m3=21,6KM
-Voda
0,2 m3x 1KM/ m3kom=0,2KM
UKUPNO Em.............................................................. ......................... .....=142,7 KM
Cbetoniranje stepenita bez oplate=142,7+(5,19+9,60+3,63)x 3,5=207,17 KM/m 3
Oplata potrebna za izradu stepenita:
GN

601 211
161404

Izrada:
Potrebna radna snaga
-T VII
0,45 h x 4,0 KM/h=1,80 KM
-T V
0,36 h x 3,6 KM/h=1,29 KM
UKUPNO Eid............................................................................................... =3,096 KM

Montaa:
Potrebna radna snaga
-T VII
0,60 h x 4,0 KM/h=2,40 KM
-T V
0,30 h x 3,6 KM/h=1,08 KM
UKUPNO Eid............................................................................................... =3,48 KM
Demontaa:

Potrebna radna snaga


-T V
0,07 h x 3,6 KM/h=0,252 KM
-T III
0,18 h x 3,2 KM/h=0,576 KM
UKUPNO Eid............................................................................................... =0,828 KM

ienje i vaenje eksera:


Potrebna radna snaga
-R II
0,10 h x 3,0 KM/h=0,30 KM
UKUPNO Eid............................................................................................... =0,30 KM
Potreban graevinski materijal:
-Daska 24mm
0,0057m 3 x 300KM/ m3=1,71KM
-Gredice
0,0015 m 3x 300KM/ m3=0,45KM
-Letva
0,001 m 3x 300KM/ m3=0,30KM
-Ekseri
0,15 kgx 3KM/ kg=0,45KM
-Bunarska motka
0,25mx 1KM/ m=0,25KM
-Daska 24mm
0,0015 m 3x 300KM/ m3=0,45KM
-Ekseri
0,06 kgx 3KM/ kg=0,18KM
UKUPNO Em.............................................................. ......................... ..... =3,79 KM
Coplate=3,79+(3,096+3,48+0,828+0,30) x 3,5=30,75KM/m2
Potrebna koliina oplate za izradu stepenita je:11,92 m 2
Potrebna koliina betona za izradu stepenita je:1,08 m 3

Cbetoniranje stepenita sa oplatom=207,17+30,75x11,92/1,08=546,55KM/m3

20. Runo sjeenje , savijanje , postavljanje i vezivanje rebraste armature.


armature.
GN

400 101
140102

Sjeenje:
Potrebna radna snaga
-A IV
0,0058 h x 3,4 KM/h=0,019 KM
-B III
0,0058 h x 3,2 KM/h=0,018 KM
UKUPNO Eid............................................................................................... =0,038 KM
Savijanje:
Potrebna radna snaga
-A IV
0,0060 h x 3,4 KM/h=0,020 KM
-B III
0,0060 h x 3,2 KM/h=0,019 KM
UKUPNO Eid................................................................................................=0,039 KM
Postavljanje i vezivanje:
Potrebna radna snaga
-A IV
0,0110 h x 3,4 KM/h=0,037 KM
-B III
0,0110 h x 3,2 KM/h=0,035 KM
UKUPNO Eid................................................................................................=0,072 KM
Prijenos materijala:
Potrebna radna snaga
-R II
0,0060 h x 3,0 KM/h=0,018 KM
UKUPNO Eid............................................................................................. =0,018 KM

Potreban materijal:
-Betonski rebrasti elik

14 i vie

1,04 kgx

2KM/kg=2,08KM
-ica Paljena
0,0032 kgx 3KM/kg=0,096KM
UKUPNO Em.............................................................. ......................... .....=2,17 KM
Csjeenje,savijanje,postavljanje i vezivanje rebrastearmature=2,17+(0,038+0,039+0,072+0,018)x3,5=
2,62KM/kg

21.Prenos, postavljanje i vezivanje mreaste armature

GN

400 111
141005

Postavljanje:
Potrebna radna snaga
-A VII
0,0180 h x 4,0 KM/h=0,072 KM
UKUPNO Eid................................................................................................=0,072 KM
Vezivanje:
Potrebna radna snaga
-A III
0,0180 h x 3,2 KM/h=0,057 KM
UKUPNO Eid................................................................................................=0,057 KM
Prijenos materijala:
Potrebna radna snaga
-R II
0,0001 h x 3,0 KM/h=0,0003 KM
UKUPNO Eid........................................................................................... =0,0003 KM
Potreban materijal:
-Mrea R 6,5-9
1,0 kgx 2KM/kg=520KM
-Metalni podmetai
1,16 komx 0,10KM/kom=0,116KM
-Podmetai od ice
1,16 kmx 0,10KM/kom=0,116KM
UKUPNO Em.............................................................. ......................... .....=2,23 KM
Cprijenos,postavljanje i vezivanje mreaste armature=2,23+(0,072+0,057+0,0003)x3,5= 2,68KM/kg

22.Zidanje zidova debljine 25cm blokom u produnom malteru 1:2:6.Obraun


po m3.

GN

301 700
124104

Spravljanje maltera:
Potrebna radna snaga
-R II
0,26 h x 3,0 KM/h=0,78 KM
UKUPNO Eid............................................................................................... =0,78 KM
Zidanje:
Potrebna radna snaga
-Z VI
3,70 h x 3,8 KM/h=14,06 KM
-R II
1,2 h x 3,0 KM/h=3,60 KM
UKUPNO Eid............................................................................................... =17,66 KM
Prenos blokova:
Potrebna radna snaga
-R II
2,87 h x 3,0 KM/h=8,61 KM
UKUPNO Eid............................................................................................... =8,61 KM
Prenos maltera:
Potrebna radna snaga
-R II
0,36 h x 3,0 KM/h=1,08 KM
UKUPNO Eid............................................................................................... =1,08 KM
Potreban materijal:
blok 25x25x19
-Produni malter

51kom x
0,10m 3 x

Potreban materijal za produni malter 1:2:6:


-Cement Pc 250
210kgx 0,3KM/kg=63KM
-Kre
0,29m 3x 120KM/m3=34,8KM
-Pijesak
0,87 m 3x 30KM/m3=26,1KM
-Voda
0,27 m3x 1,0KM/m3=0,27KM
UKUPNO Em.............................................................. ......................... .....=124,17 KM
-uplji giter blok 25x25x19
51komx 0,80KM/kom=40,80KM
-Produni malter
0,10m 3x 124,17KM/m3=12,42KM
UKUPNO Em.............................................................. ......................... .....=53,22 KM
Czidanje zida debljine 25cm=53,22+(0,78+17,66+8,61+1,08)x3,5= 151,67KM/m 3

23. Zidanje zidova debljine 20 cm blok opekom u produnom malteru


1:2:6.Obraun po m3.
301 804
GN
124607
Spravljanje maltera:
Potrebna radna snaga
-R II
0,26 h x 3,0 KM/h=0,78 KM
UKUPNO Eid............................................................................................... =0,78 KM
Zidanje:
Potrebna radna snaga
-Z VI
3,96 h x 3,8 KM/h=15,05 KM
-R II
1,180 h x 3,0 KM/h=3,54 KM
UKUPNO Eid............................................................................................... =18,59 KM
Prenos blokova:
Potrebna radna snaga
-R II
1,730 h x 3,0 KM/h=5,19 KM
UKUPNO Eid............................................................................................... =8,61 KM
Prenos maltera:
Potrebna radna snaga
-R II
0,201 h x 3,0 KM/h=0,603 KM
UKUPNO Eid............................................................................................... =0,603 KM
Potreban materijal:
-Blok opeka
20x25x19
-Produni malter

64,5kom x
0,10m 3 x

Potreban materijal za produni malter 1:2:6:


-Cement Pc 250
210kgx 0,3KM/kg=63KM
-Kre
0,29m 3x 120KM/m3=34,8KM
-Pijesak
0,87 m 3x 30KM/m3=26,1KM
-Voda
0,27 m3x 1,0KM/m3=0,27KM
UKUPNO Em.............................................................. ......................... .....=124,17 KM
-Blok opeka
20x25x19
64,5komx 0,70KM/kom=45,15KM
-Produni malter
0,10m 3x 124,17KM/m3=12,42KM
UKUPNO Em.............................................................. ......................... .....=53,57 KM
Czidanje zida debljine 25cm=57,57+(0,78+18,59+8,61+0,603)x3,5= 157,61KM/m 3

24. Zidanje zidova debljine 15 cm blok opekom u produnom malteru


1:2:6.Obraun po m3.
301 800
GN
124201
Spravljanje maltera:
Potrebna radna snaga
-R II
0,05 h x 3,0 KM/h=0,15 KM
UKUPNO Eid............................................................................................... =0,15 KM
Zidanje:
Potrebna radna snaga
-Z VI
0,90 h x 3,8 KM/h=3,42 KM
-R II
0,45 h x 3,0 KM/h=1,35 KM
UKUPNO Eid............................................................................................... =4,77 KM
Prenos blokova:
Potrebna radna snaga
-R II
0,23 h x 3,0 KM/h=0,69 KM
UKUPNO Eid............................................................................................... =0,69 KM
Prenos maltera:
Potrebna radna snaga
-R II
0,045 h x 3,0 KM/h=0,135 KM
UKUPNO Eid............................................................................................... =0,135 KM
Potreban materijal:
-Blok opeka
d=15
-Produni malter

12,5kom x
0,02m 3 x

Potreban materijal za produni malter 1:2:6:


-Cement Pc 250
210kgx 0,3KM/kg=63KM
-Kre
0,29m 3x 120KM/m3=34,8KM
-Pijesak
0,87 m 3x 30KM/m3=26,1KM
-Voda
0,27 m3x 1,0KM/m3=0,27KM
UKUPNO Em.............................................................. ......................... .....=124,17 KM
-Blok opeka
d=15
12,5komx 0,70KM/kom=8,75KM
-Produni malter
0,02m 3x 124,17KM/m3=2,48KM
UKUPNO Em.............................................................. ......................... ..... =11,23 KM
Czidanje zida debljine 15cm=11,23+(0,15+4,77+0,69+0,139)x3,5= 31,35KM/m 2

25.Grubo i fino malterisanje zidova i plafona u dva sloja sa PCM 1:2.6 sa


predhodnim pricanjem cementnim pric malterom.Obraun po m 2
omalterisane povrine.
301 401
GN
126906
Spravljanje maltera:
Potrebna radna snaga
-R II
0,074 h x 3,0 KM/h=0,22 KM
UKUPNO Eid............................................................................................... =0,22 KM

Grubo Malterisanje I sloj:


Potrebna radna snaga
-R VI
0,32 h x 3,8 KM/h=1,22 KM
-R II
0,11 h x 3,0 KM/h=0,33 KM
UKUPNO Eid............................................................................................... =1,55 KM
Fino Malterisanje II sloj:
Potrebna radna snaga
-R VI
0,36 h x 3,8 KM/h=1,37 KM
-R II
0,08 h x 3,0 KM/h=0,24 KM
UKUPNO Eid............................................................................................... =1,61 KM
Prenos maltera:
Potrebna radna snaga
-R II
0,11 h x 3,0 KM/h=0,33 KM
UKUPNO Eid............................................................................................... =0,33 KM
Potreban materijal:
-Produni malter 1:2:6
-Cementni malter 1:3

0,023m 3 x
0,005m 3 x

Potreban materijal za produni malter 1:2:6:


-Cement Pc 250
210kgx 0,3KM/kg=63KM
-Kre
0,29m 3x 120KM/m3=34,8KM
-Pijesak
0,87 m 3x 30KM/m3=26,1KM
-Voda
0,27 m3x 1,0KM/m3=0,27KM
UKUPNO Em.............................................................. ......................... .....=124,17 KM

Potreban materijal za cementni malter 1:3:


-Cement Pc 250
470kgx 0,3KM/kg=141KM
-Pijesak
1,01 m 3x 30KM/m3=30,3KM
-Voda
0,35 m3x 1,0KM/m3=0,35KM
UKUPNO Em.............................................................. ......................... .....=171,65 KM
Potreban materijal:
-Produni malter 1:2:6
0,023m 3 x 124,17KM/m3=2,85KM
-Cementni malter 1:3
0,005m 3 x 171,65KM/m3=0,85KM
UKUPNO Em.............................................................. ......................... .....=3,70 KM
Cmalterisanja=3,70+(0,22+1,55+1,61+0,33)x3,5= 16,68KM/m 2

26.Izrada vertiklane hidroizolacije na betonskom zidu suterena.Obraun po m 2.


GN

301 500
128701

Izrada:
Potrebna radna snaga
-Z V
0,10 h x 3,6 KM/h=0,036 KM
-R II
0,08 h x 3,0 KM/h=0,24 KM
UKUPNO Eid............................................................................................... =0,276 KM
Potreban graevinski materijal:
-Bitulit A
1,00kg x 1KM/kg=1,00KM
-etke
0,0005kom x 1KM/kom=0,0005KM
UKUPNO Em.............................................................. ......................... .....=1,0005 KM
CIzrada vert izolacije=1,0005+(0,276)x3,5= 1,667KM/m2

27.Oblaganje zidova keramikim ploicama veliine 15x15 u kuhinji i


kupatilu.Obraun po m2.
501 101
GN
180101
Oblaganje:
Potrebna radna snaga
-R VI
1,18 h x 3,8 KM/h=4,48 KM
-R II
0,70 h x 3,0 KM/h=2,1 KM
UKUPNO Eid............................................................................................... =6,58KM
Potreban graevinski materijal:
-Keramike ploice 20x20 I klasa
26kom x 0,5KM/kom=13,00KM
-Bijeli cement
0,04kg x 0,15KM/kg =0,006KM
-Voda
0,01m 3 x 1KM/m3 =0,01KM
-Lijepak
2,0kg x 3KM/kg =6,00KM
UKUPNO Em.............................................................. ......................... .....=19,007 KM

Coblaganje zidova ker.plo=19,007+(6,58)x3,5= 42,037KM/m2

28.Nabavka i postavljanje podnih keramikih ploica u sloju ljepila na podu


prizemlja kao i na stepenicama.Obraun po m2.

GN

501 101 2
180101

Oblaganje:
Potrebna radna snaga
-R VI
1,16 h x 3,8 KM/h=4,40 KM
-R II
0,52 h x 3,0 KM/h=1,56 KM
UKUPNO Eid............................................................................................... =5,96 KM
Potreban graevinski materijal:
-Keramike ploice 20x20 I klasa
26kom x 0,5KM/kom=13,00KM
-Cementni malter 1:3
0,02m 3 x 171,65KM/m3 =3,43KM
-Bijeli cement
0,04kg x 0,15KM/kg =0,006KM
-Voda
0,01m 3 x 1KM/m3 =0,01KM
UKUPNO Em.............................................................. ......................... .....=14,94 KM
Potreban materijal za cementni malter 1:3:
-Cement Pc 250
470kgx 0,3KM/kg=141KM
-Pijesak
1,01 m 3x 30KM/m3=30,3KM
-Voda
0,35 m3x 1,0KM/m3=0,35KM
UKUPNO Em.............................................................. ......................... .....=171,65 KM
Coblaganje podova ker.plo=14,94+(5,96)x3,5= 35,80KM/m2

29.Nabavka i postavljanje parketa na podu na gotovoj podlozi.Obraun po m 2.

GN

691 205
280701

Postavljanje i prijenos:
Potrebna radna snaga
-P VI
0,40 h x 3,8 KM/h=1,52 KM
-R II
0,20 h x 3,0 KM/h=0,60 KM
UKUPNO Eid............................................................................................... =2,12KM
Potreban materijal za polaganje hrastovog parketa:
-Hrastov parket I klasa
1,05m 2x 50KM/m2=52,5KM
-Lijepak
0,80kgx 1,0KM/kg=0,80KM
UKUPNO Em.............................................................. ......................... ..... =53,30 KM
Coblaganje podova parketom=53,30+(2,12)x3,5= 60,72KM/m2

30.Nabavka i postavljanje gotovih ugaonih lajsni.Obraun po m1.

GN

691 302
281202

Postavljanje i lakiranje:
Potrebna radna snaga
-R VI
0,12 h x 3,8 KM/h=0,45 KM
UKUPNO Eid............................................................................................... =0,45 KM
Potreban materijal za postavljanje ugaonih lajsni:
-Lajsna truglasta hrastova
1,10m 1x 2KM/m1=2,20KM
-Ekseri
0,003kgx 3,0KM/kg=0,009KM
-Lak za parket
0,05kgx 5,0KM/kg=0,25KM
UKUPNO Em.............................................................. ......................... ..... =2,459 KM
Coblaganje podova parketom=2,459+(0,45)x3,5= 4,03KM/m1

31. Nabavka materijala i farbanje svih unutranjih zidova i plafona bijelom


bojom u dva premaza.Obraun po m2.

GN

531 101
330101

Gipsanje rupa:
Potrebna radna snaga
-R III
0,041 h x 3,2 KM/h=0,13 KM
UKUPNO Eid............................................................................................... =0,13 KM
Bruenje:
Potrebna radna snaga
-R III
0,021 h x 3,2 KM/h=0,067 KM
UKUPNO Eid............................................................................................... =0,067 KM
Kreenje I put:
Potrebna radna snaga
-R III
0,035 h x 3,2 KM/h=0,112 KM
UKUPNO Eid............................................................................................... =0,112 KM
Kreenje II put:
Potrebna radna snaga
-R III
0,030 h x 3,2 KM/h=0,096 KM
UKUPNO Eid............................................................................................... =0,096 KM
Kreenje aparatom I put:
Potrebna radna snaga
-R II
0,016 h x 3,0 KM/h=0,048 KM
-R IV
0,016 h x 3,4 KM/h=0,054 KM
UKUPNO Eid............................................................................................... =0,102 KM
Kreenje aparatom I put:
Potrebna radna snaga
-R II
0,013 h x 3,0 KM/h=0,039 KM
-R IV
0,013 h x 3,4 KM/h=0,044 KM
UKUPNO Eid............................................................................................... =0,083 KM
Potreban materijal za kreenje:
-Kre gaeni
0,59 kgx 1,5 KM/kg=0,885KM
-Voda
0,0006 m 3x 1,0 KM/m3=0,0006KM
UKUPNO Em.............................................................. .............................. =0,8856 KM

Cfarbanje zidova i plafona=0,8856+(0,13+0,067+0,112+0,096+0,102+0,083)x3,5= 2,95KM/m 2

32.Izrada crtea za krovne konstrukcije prema datim klasifikacijama.


GN

601 405
163612

Potrebna radna snaga


-T VI
8,0 h x 3,8 KM/h=30,40 KM
-T VIII
8,0 h x 4,2 KM/h=33,60 KM
UKUPNO Eid............................................................................................... =64,00KM
CIzrada crtea=0+(64)x3,5= 224KM/m2

33.Letvanje krova letvom 3/5cm.Obraun po m 2 kose povrine krova.


601 443
GN
167405
Letvisanje:
Potrebna radna snaga
-T V
0,06 h x 3,6 KM/h=0,216 KM
-T IV
0,06 h x 3,4 KM/h=0,204 KM
-R II
0,06 h x 3,0 KM/h=0,180 KM
UKUPNO Eid............................................................................................... =0,60KM
Potreban materijal letvisanje krova:
-Letva 3/5
0,005m 3x 300KM/kg=1,50KM
-Ekseri
0,04kgx 3,0KM/kg=0,12KM
UKUPNO Em.............................................................. ......................... ..... =1,62 KM

Cletvisanje krova=1,62+(0,60)x3,5= 3,75KM/m2

34.Pokrivanje krova falcovanim crijepom.Obraun po m2 kose povrine krova.


361 104
GN
130401
Pokrivanje krova i prijenos materijala:
materijala
Potrebna radna snaga
-R V
0,12 h x 3,6 KM/h=0,432 KM
-R II
0,18 h x 3,0 KM/h=0,540 KM
UKUPNO Eid.............................................................................................. =0,972KM

Potreban graevinski materijal za pokrivanje krova:


-Crijep falcovani 20 42
16 kom x 0,90 KM/k0m=14,40KM
UKUPNO Em.............................................................. ......................... ..... =14,40 KM
Cpokrivanjee krova falcovanim crijepom=14,40+(0,972)x3,5= 17,80KM/m2

35.Pokrivanje sljemena sljemenacima.Obraun po m 1.


361 104
GN
130407
Postavljanje sljemenaka i prijenos materijala:
materijala
Potrebna radna snaga
-R V
0,15 h x 3,6 KM/h=0,540 KM
-R II
0,15 h x 3,0 KM/h=0,450 KM
UKUPNO Eid.............................................................................................. =0,99 KM
Potreban graevinski materijal za pokrivanje sljemena sljemenacima:
-Sljemenaci
2,5 kom x 3,0 KM/kom=7,50KM
-Cementni malter 1:3
0,002 m 3 x 171,65 KM/m3=0,343KM
UKUPNO Em.............................................................. ......................... ..... =7,84 KM
Potreban materijal za cementni malter 1:3:
-Cement Pc 250
470kgx 0,3KM/kg=141KM
-Pijesak
1,01 m 3x 30KM/m3=30,3KM
-Voda
0,35 m3x 1,0KM/m3=0,35KM
UKUPNO Em.............................................................. ......................... .....=171,65 KM

Cpokrivanje sljemena sljemenacima=7,84+(0,999)x3,5= 11,30KM/m1

36. Nabavka materijala izrada i postavljanje viseih oluka kvadratnog presjeka14/14


od pocinanog lima d=0,55mm.Obraun po m1.
771 113
GN
481306
Potrebna radna snaga
-R VI
0,15 h x 3,8 KM/h=0,57 KM
-R III
0,15 h x 3,2 KM/h=0,48 KM
UKUPNO Eid.............................................................................................. =1,05 KM
Potreban materijal izradu viseih oluka:
-Pocinkovani lim
1,88kgx 5,0KM/kg=9,4KM
-Ekseri
0,015 kgx 3KM/kg=0,045KM
-Gvozdeni zakivci br 7
2 komx 0,5KM/kom=1,0KM
-Gvozdeni zakivci br 1
7 komx 0,5KM/kom=3,5KM
-Kalaj
0,015 kgx 2,0KM/kg=0,30KM
-Solna Kiselina
0,015 kgx 1,0KM/kg=0,15KM
-Drveni ugalj
0,025 kgx 1,0KM/kg=0,25KM
-Pocinkovane kuke
0,025 kgx 5,0KM/kg=0,125KM
UKUPNO Em.............................................................. ......................... ..... =14,77 KM
Cpostavljanje viseih oluka=14,77+(1,05)x3,5= 18,445KM/m1

37. Nabavka materijala izrada i postavljanje vertikalnih oluka kvadratnog presjeka


14/14 u cijenu uraunate i obujnice od trakastog zeljeza za privrenje o
zid.Obraun po m1.
771 115
GN
481507
Potrebna radna snaga
-R VI
0,80 h x 3,8 KM/h=3,04 KM
-R III
0,80 h x 3,2 KM/h=2,56 KM
UKUPNO Eid.............................................................................................. =5,60 KM
Potreban materijal izradu viseih oluka:
-Pocinkovani lim
3,28kgx 5,0KM/kg=16,4KM
-Pocinkovani drai fi12
0,10 komx 0,5KM/kom=0,05KM
-Pocinkovani zavrtnjevi
0,35 kgx 5,0KM/kom=1,75KM
-Gvozdeni zavrtnjevi
1 kom x 3,0KM/kom=3,0KM
-Kalaj
0,06 kgx 2,0KM/kg=0,12KM
-Solna Kiselina
0,06 kgx 1,0KM/kg=0,06KM
-Drveni ugalj
0,06 kgx 1,0KM/kg=0,06KM
UKUPNO Em.............................................................. ......................... ..... =21,44 KM
Cpostavljanje vertikalnih oluka=21,44+(5,60)x3,5= 41,04KM/m1

38.. Runo prskanje fasade mjeavinom za prskanje fasade. U cijenu uzeta montaa
i demontaa skele. Obraun po m2.
421 101
GN
170101
Spravljanje maltera:
Potrebna radna snaga
-R II
0,14 h x 3,0 KM/h=0,42 KM
UKUPNO Eid.............................................................................................. =0,42 KM
I sloj grundiranje i prenos:
Potrebna radna snaga
-R VI
0,50 h x 3,8 KM/h=1,9 KM
-R II
0,22 h x 3,0 KM/h=0,66 KM
UKUPNO Eid.............................................................................................. =2,56 KM
II sloj izrada i prenos:
Potrebna radna snaga
-R VI
0,40 h x 3,8 KM/h=1,52 KM
-R II
0,20 h x 3,0 KM/h=0,60 KM
UKUPNO Eid.............................................................................................. =2,12 KM
Krpljenje:
Potrebna radna snaga
-R VI
0,12 h x 3,8 KM/h=0,456 KM
UKUPNO Eid.............................................................................................. =0,456 KM
Potreban materijal za fasadu:
-Produni malter 1:2:6
-Cementni malter 1:3

0,032 m 3 x
0,0005 m 3 x

Potreban materijal za cementni malter 1:3:


-Cement Pc 250
470kgx 0,3KM/kg=141KM
-Pijesak
1,01 m 3x 30KM/m3=30,3KM
-Voda
0,35 m3x 1,0KM/m3=0,35KM
UKUPNO Em.............................................................. ......................... .....=171,65 KM
Potreban materijal za produni malter 1:2:6:

-Cement Pc 250
210kgx 0,3KM/kg=63KM
-Kre
0,29m 3x 120KM/m3=34,8KM
-Pijesak
0,87 m 3x 30KM/m3=26,1KM
-Voda
0,27 m3x 1,0KM/m3=0,27KM
UKUPNO Em.............................................................. ......................... .....=124,17 KM
Potreban materijal za fasadu:
-Produni malter 1:2:6
0,032 m 3 x 124,17KM/m3=3,97 KM
-Cementni malter 1:3
0,0005 m 3 x 171,75KM/m3=0,085 KM
UKUPNO Em.............................................................. ......................... .... =4,05 KM
Cfasada bez skele =4,05+(0,42+2,56+2,12+0,45)x3,5= 23,47KM/m 2
Cjevasta Skela
GN

421 110
171001

Montaa,demontaa,ienje,naftiranje i slaganje:
Potrebna radna snaga
-R VI
0,33 h x 3,8 KM/h=1,25 KM
-R IV
0,10 h x 3,4 KM/h=0,34 KM
-R II
0,25 h x 3,0 KM/h=0,75 KM
UKUPNO Eid.............................................................................................. =2,34 KM
Potreban materijal za skelu:
-Nafta
0,05kgx 2,5KM/kg=0,125KM
-Krpa stara
0,01 kgx 1,0KM/kg=0,01KM
-ica
0,015 kg x 2,5KM/kg=0,037KM
UKUPNO Em.............................................................. .............................. =0,172 KM

Ccjevaste skele =0,172+(2,34)x3,5=8,36 KM/m2


Cfasada sa skelom = 23,47+8,36=31,83KM/m2

39. Izrada krovne konstrukcije.Obraun po m2.


GN

601 406
163717

Izrada Krovne konstrukcije:


Potrebna radna snaga
-T V
0,15 h x 3,6 KM/h=0,54 KM
-T VI
0,30 h x 3,8 KM/h=1,14 KM
-T VII
0,55 h x 4,0 KM/h=2,20 KM
UKUPNO Eid............................................................................................... =3,88KM
Potreban materija za izradu krovne grae:
-Strugana Graa
0,06m 3x 300KM/kg=18KM
-Okov za krov
0,57kgx 3,0KM/kg=1,71KM
-Ekseri
0,04kgx 3,0KM/kg=0,12KM
UKUPNO Em.............................................................. ......................... ..... =19,82 KM
Cizrada krovne grae=19,82+(3,88)x3,5= 33,40KM/m2