Professional Documents
Culture Documents
BF Corp V CA. Shangri-La Properties Inc (SPI) - Romero G.R. No. 120105, March 27, 1998 - 288 SCRA 267
BF Corp V CA. Shangri-La Properties Inc (SPI) - Romero G.R. No. 120105, March 27, 1998 - 288 SCRA 267
a r b i t | joycgc
02
a r b i t | joycgc
02
a r b i t | joycgc
filed with the RTC of Makati City a verified Petition for the
Declaration of Presumptive Death, which Petition was granted.
In 1998, Petitioners, as heirs of Salas, Jr. filed in the RTC of Lipa City
a Complaint for Declaration of Nullity of Sale, Reconveyance,
Cancellation of Contract, Accounting and Damages against
Respondents.
02
a r b i t | joycgc
02
a r b i t | joycgc
Pertinent topic:
settlement.
Legal history discloses that "the early judges called upon to solve
private conflicts were primarily the arbiters, persons not specially
trained but in whose morality, probity and good sense the parties in
conflict reposed full trust. Thus, in Republican Rome, arbiter and
judge (judex) were synonymous. The magistrate or praetor, after
noting down the conflicting claims of litigants, and clarifying the
issues, referred them for decision to a private person designated by
the parties, by common agreement, or selected by them from an
apposite listing (the album judicium) or else by having the arbiter
02
a r b i t | joycgc
02
a r b i t | joycgc
02
a r b i t | joycgc
02
a r b i t | joycgc
02
a r b i t | joycgc
02
a r b i t | joycgc
02
a r b i t | joycgc
Rock Products, Inc.) for petitioner, and Nelia G. Cid and Atty.
Esteban A. Bautista for respondent spouses.
Petitioner claims, on the other hand, that this Agreement was
withdrawn by respondents on April 8, 1994, because of the
exclusion of the seven engineers of petitioners in the arbitration
case. This withdrawal became the basis for the April 13, 1994 CIAC
Order dismissing the arbitration case and referring the dispute back
to the RTC. Consequently, the CIAC was divested of its jurisdiction
to hear and decide the case.
This contention is untenable. First, private respondents removed
the obstacle to the continuation of the arbitration, precisely by
withdrawing their objection to the exclusion of the seven engineers.
Second, petitioner continued participating in the arbitration even
after the CIAC Order had been issued. It even concluded and signed
the Terms of Reference on August 21, 1995, in which the parties
stipulated the circumstances leading to the dispute; summarized
their respective positions, issues, and claims; and identified the
composition of the tribunal of arbitrators. The document clearly
confirms both parties intention and agreement to submit the
dispute to voluntary arbitration. In view of this fact, we fail to see
how the CIAC could have been divested of its jurisdiction.
Finally, as pointed out by the solicitor general, petitioner
maneuvered to avoid the RTCs final resolution of the dispute by
arguing that the regular court also lost jurisdiction after the arbitral
tribunals April 13, 1994 Order referring the case back to the RTC. In
so doing, petitioner conceded and estopped itself from further
questioning the jurisdiction of the CIAC. The Court will not
countenance the effort of any party to subvert or defeat the
objective of voluntary arbitration for its own private motives. After
submitting itself to arbitration proceedings and actively
participating therein, petitioner is estopped from assailing the
jurisdiction of the CIAC, merely because the latter rendered an
adverse decision.
02
a r b i t | joycgc
02
a r b i t | joycgc
02
Facts:
-
a r b i t | joycgc
02
a r b i t | joycgc
02
a r b i t | joycgc
KOGIES. The CA found that the RTC did not gravely abuse its
discretion in issuing the assailed July 23, 1998 and September 21,
1998 Orders. Moreover, the CA reasoned that KOGIES contention
that the total contract price for USD 1,530,000 was for the whole
plant and had not been fully paid was contrary to the finding of the
RTC that PGSMC fully paid the price of USD 1,224,000, which was
for all the machineries and equipment. According to the CA, this
determination by the RTC was a factual finding beyond the ambit of
a petition for certiorari.
On the issue of the validity of the arbitration clause, the CA
agreed with the lower court that an arbitration clause which
provided for a final determination of the legal rights of the parties
to the contract by arbitration was against public policy.
ISSUE: W/N the Arbitration clause is contrary to public policy.
RULING:
The arbitration clause which stipulates that the
arbitration must be done in Seoul, Korea in accordance with the
Commercial Arbitration Rules of the KCAB, and that the arbitral
award is final and binding, is not contrary to public policy. This
Court has sanctioned the validity of arbitration clauses in a catena
of cases. In the 1957 case of Eastboard Navigation Ltd. v. Juan
Ysmael and Co., Inc.,iii this Court had occasion to rule that an
arbitration clause to resolve differences and breaches of mutually
agreed contractual terms is valid. In BF Corporation v. Court of
Appeals, we held that [i]n this jurisdiction, arbitration has been
held valid and constitutional. Even before the approval on June 19,
1953 of Republic Act No. 876, this Court has countenanced the
settlement of disputes through arbitration. Republic Act No. 876
was adopted to supplement the New Civil Codes provisions on
arbitration. And in LM Power Engineering Corporation v. Capitol
Industrial Construction Groups, Inc., we declared that:
Being an inexpensive, speedy and amicable
method of settling disputes, arbitrationalong with
mediation,
conciliation
and
negotiationis
encouraged by the Supreme Court.
Aside from
unclogging judicial dockets, arbitration also hastens
the resolution of disputes, especially of the
commercial kind. It is thus regarded as the wave of
the future in international civil and commercial
disputes. Brushing aside a contractual agreement
calling for arbitration between the parties would be a
step backward.
i
ii
iii